UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 154 |
JOHN
B. KELLY, INC., |
|
Respondent. |
|
August 3, 1973
Before MORAN, Chairman; VAN NAMEE and CLEARY
Commissioners
CLEARY, COMMISSIONER:
On
July 17, 1972, Judge Herbert E. Bates issued a decision in this case holding
that respondent had violated section 5(a)(1) of the Occupational Safety and
Health Act of 1970 (29 U.S.C.A. 651 et seq., 84 Stat. 1590, hereinafter
referred to as ‘the Act’), because it did not take adequate safety precautions
while undercutting and removing masonry material from a free-standing wall. He
assessed a penalty of $1,000. Thereafter, pursuant to section 12(j) of the Act,
that decision was ordered to be reviewed by the Commission.
Having
examined the record in its entirety, the Commission finds no prejudicial error
therein.
Accordingly,
it is ORDERED that the Judge’s decision and order are hereby affirmed in all
respects.
MORAN, CHAIRMAN, dissenting:
This
case stretches the employer’s obligations under the Act far beyond anything
ever intended by finding an employer in violation of section 5(a)(1) of the Act
because of employee disobedience tantamount to willful and wanton misconduct.
The case was initiated when the employee involved, [redacted], died from the collapse of a wall upon him. The
allegations contained in the citation are based upon that accident.
[redacted] was engaged in making certain
material alterations to a free-standing wall which respondent had erected in
the lobby of a federal building under construction in Philadelphia pursuant to
a subcontract for masonry work thereon.
Soon
after the wall was erected, Mr. Erickson, the building’s architectural
engineer, informed respondent’s superintendent, Mr. Sutton, that the wall was
not safe due to improper placement of the mailbox aperture.
On
the morning of September 27, 1971, Sutton instructed two of respondent’s
employees to modify the wall by turning the wooden frame in the mailbox
aperture so that the long dimension would be running horizontally rather than
vertically. This undertaking required the undercutting of the masonry wall so
as to allow for the rotation of the wooden frame in the mailbox aperture.
Knowing that an improper modification might create the possibility of an unsafe
situation, Sutton gave specific instructions to employee [redacted] on how the modification was to be done properly. A
thorough and clear instruction was personally given [redacted] by Sutton immediately before the employee began the job.
This instruction included specific direction to brace the wall with two
diagonal 4x4 inch beams before removing the frame, as well as a statement that
the brace was to be ‘tied’ to the wall above the lintel and that it should run
diagonally to the ground.
When
Sutton returned to the site of the modification later that same morning, he saw
only a vertical 4x4 inch wooden shore in the aperture from which the frame had
been removed. He admonished [redacted]
for proceeding improperly and repeated his prior instruction. He warned that the
diagonal bracing must be properly installed, that the wall would be dangerous
when [redacted] began to undercut,
that when the frame was removed it would be even more dangerous and might
topple unless it was supported by diagonal bracings.
After
Sutton had left the site following his first conversation with [redacted], two employees of the general
contractor had also warned [redacted]
concerning the hazardous condition of the wall. The chief architectural
engineer for the project had given one such warning, and the general
contractor’s safety engineer had twice warned [redacted] of the danger of his work. Thus, although Sutton was
unaware of it at the time, when he returned to repeat his instructions about
the diagonal bracing, it was the seventh time [redacted] had been warned.
Despite
these numerous warnings, [redacted]
did not install the diagonal bracing. Just prior to the accident, [redacted] said to his co-worker,
Jefferson, ‘I wonder what is going to happen when I remove this vertical
shore.’ He then removed the vertical shoring, causing the wall to collapse upon
him.
As a
result, respondent was cited for a violation of section 5(a)(1)—the Act’s
general duty requirement—which provides that each employer shall furnish to
each of his employees ‘employment and a place of employment which are free from
recognized hazards that are causing or are likely to cause death or serious
physical harm to his employees.’
Recognition
that a particular fact situation constitutes a hazard is essential to establishment
of a violation of this provision. Such recognition must come from ordinary
prudent employers in respondent’s industry or from the knowledge of the public
at large. Secretary of Labor v. Vy Lactos Laboraties, Inc., OSAHRC
Docket No. 31, decided February 21, 1973. See also the discussion in Secretary
of Labor v. Engstrum and Nourse, OSAHRC Docket No. 74, decided February 12,
1973. In the instant case, the existence of a hazard because of the way [redacted] was performing alterations to
the wall was recognized by Sutton, Erickson, and Butler, all of whom were
experienced in the field of construction. However, the record clearly
establishes that the hazard would not have existed had [redacted] followed the instructions.
Section
5(a) cannot be applied in a vacuum. It must be read in conjunction with the
entire Act and particularly with section 5(b), which admonishes employees to
comply with rules and orders applicable to their own conduct. The
interrelationship of these two provisions are underscored by the Congressional
purpose and policy stated in section 2(b)(2), which provides that employers and
employees have separate but dependent responsibilities with respect to
achieving safe and healthful working conditions.
We
have often held that the employer has final responsibility for compliance with
the provisions of the Act. Secretary of Labor v. National Realty and
Construction Co., Inc., OSAHRC Docket No. 85, decided September 6, 1972; Secretary
of Labor v. Arnold Hansen, d/b/a Hansen Brothers Logging, OSAHRC Docket No.
141, decided October 16, 1972; cf. S. Rep. No. 91–1282, 91st Cong., 2d Sess. 11
(1970). However, we have also found that this responsibility is not absolute. Secretary
of Labor v. Standard Glass Co., OSAHRC Docket No. 259, decided July 28, 1972;
Secretary of Labor v. Mountain States Telephone & Telegraph Co.,
OSAHRC Docket No. 355, decided January 3, 1973.
Where
the record shows that respondent gave specific oral instructions to its
employees, that respondent’s employees were repeatedly reminded of the danger
involved, and where there is nothing in the record to show that respondent knew
or reasonably should have known that the employee would disobey these
instructions, ‘practicality and reason dictate that the respondent’s obligation
has been met within the requirements of section 5(a)(1) of the Act.’ Secretary
of Labor v. Hansen Brothers Logging, OSAHRC Docket No. 141, decided October
13, 1972. To require respondent to provide one-on-one supervision of its
employees would place it under an unreasonably burdensome duty. Id.
Here the employee was properly instructed to avoid a
dangerous situation, and was specifically instructed how to proceed safely.
Furthermore, the means to do so were clearly within the employee’s discretion
and control. However, the employee willfully violated the repeated and clear
instructions which were given him specifying how the work was to be done in a
safe manner. Such an act of the employee cannot constitute the basis for a
violation of section 5(a)(1) by the employer where, as here, the employer fully
discharged his responsibility under the Act.
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 154 |
JOHN
B. KELLY, INC., |
|
Respondent. |
|
July 17, 1972
BATES, JUDGE, OSAHRC:
This
is a proceeding under section 10(c) of the Occupational Safety and Health Act of
1970, 29 U.S.C. 651, et seq. (hereinafter referred to as ‘the Act’) to review
citations issued by the Secretary of Labor (hereinafter referred to as the
‘Complainant’) pursuant to section 9(a), and proposed assessment of penalties
thereon issued pursuant to section 10(a) of the Act.
The
complaint in the captioned case is evidenced by citations for serious and
nonserious violations under the statute and applicable standards dated October
27, 1971. The citation for the serious violation charges a violation of section
5(a) of the Act and ANSI Standard A 10.9(12.5), as adopted by 29 CFR
1518.700(a), as adopted by 29 CFR 1910.12. The alleged serious violation was
therein described as follows:
Employer did not furnish to each of his
employees employment and a place of employment which were free from recognized
hazards that were causing or were likely to cause death or serious physical
harm to his employees in that:
Employer did not take adequate precaution
in an operation to undercut and remove masonry material from a masonry wall
which resulted in the collapse of the wall.
The
violation of the aforementioned standard was: ‘Masonry wall was not temporarily
shored and braced until the designed lateral strength was reached to prevent
collapse due to wind or other forces.’
In
addition to the citation for the allegedly serious violation above, the
Respondent was cited for three ‘non-serious’ violations as follows:
1. During the course of construction, keep
passageways and work areas free of debris. 3rd floor near elevator shaft in
area surrounding mason sawing operation [29 CFR 1518.250(a)(3) and 1518.25(a)
as adopted by 29 CFR 1910.12].
2. Provide only that quantity of material
on mason’s scaffold which will be used in the immediate operation. 4th floor
west [29 CFR 1518.250(b)(5) as adopted by 29 CFR 1910.12].
3. Provide cover for floor hole created by
missing plank in elevator shaft cover on 5th floor [29 CFR 1518.500(b)(8) as
adopted by 29 CFR 1910.12].
The
proposed penalties for the three violations were $14, $14, and $16,
respectively. A penalty of $550 was proposed for the serious violation. The
dates on which these violations were to be corrected were set forth as
‘immediately.’
The
Respondent filed a timely notice of his intention to contest the aforesaid
citations in all respects, and the cause was referred to the Commission for
hearing pursuant to section 10(c) of the Act on November 8, 1971. On December
9, 1971, the undersigned was assigned to hear the case pursuant to section
12(e) of the Act.
After
some unavoidable delay, the hearing was held on March 28, 1972, in
Philadelphia, Pennsylvania.
At
the commencement of the trial the Respondent asserted that the three
non-serious violations (above) were in fact violations of the standards as
charged, and that the abatement periods and proposed penalties were reasonable
and proper (Tr. 37).
The
Respondent further averred that he did not object to the penalty proposed for
the serious violation, nor the abatement period proposed therefor (Tr. 38).
It
was agreed that the only issue in dispute was whether or not the Respondent
violated section 5(a)(1) of the Act, in the manner referred to above (Tr. 38).
Having
heard the testimony of the witnesses and having considered the same together
with the exhibits and the stipulations, representations and admissions of the
parties, it is concluded that substantial evidence, on the record considered as
a whole, supports the following findings of fact.
FINDINGS OF FACT
(NOTE: The letter ‘s’ following the transcript page
reference indicates those facts were stipulated to.)
1.
The Respondent, John B. Kelly, Incorporated, is a Pennsylvania corporation
maintaining its principal office and place of business at 1720 Cherry Street,
Philadelphia, Pennsylvania (Tr. 9).
2.
The Respondent is a large masonry construction firm operating within the
Philadelphia area, and generated in excess of one million dollars annual volume
of business for the years 1970–1971.
3.
The Respondent is engaged in the business of masonry subcontracting and is
engaged in construction and reconstruction. It regularly receives goods and
materials that have been produced and shipped in interstate commerce. It is an
employer engaged in business affecting commerce who has employees as defined by
section 3(5) of the Act, and is subject to the regulations and standards
promulgated thereunder (Tr. 9).
4.
The Respondent was, from sometime prior to July 1, 1971, and is still until the
present time, a subcontractor engaged in the performance of work under Contract
No. GS–02B–16026 awarded by the Government of the United States to McCloskey
& Company for the construction of a federal building at 6th and Market
Streets, Philadelphia, Pennsylvania (Tr. 9, 10).
5.
Sometime in August 1971 the Respondent’s employees constructed a wall at the
site of the federal building at 6th and Market Streets. This wall was
constructed of 8‘ cinderblock in the proposed lobby of the building (Tr. 10).
6.
The Respondent has no prior history of violations under the Occupational Safety
and Health Act (Tr. 10).
7.
The Respondent employed approximately 48 employees on or about September 27,
1971, at its workplace at 6th and Market Streets.
8.
The Respondent represents that it has properly posted the citation and notice
of hearing at its workplace (Tr. 10).
9.
Sometime in August 1971, an 8‘ cinderblock wall was constructed by the
Respondent in the proposed lobby of the new federal building at 6th and Market
Streets. The plan of that wall is shown on Petitioner’s Exhibit C–6. The wall
is a free standing wall in that it is not ‘tied in’ to the ceiling and is
approximately 17 feet in height. Running vertically through the wall is a space
left for a metal mail chute. At the bottom of the mail chute, approximately 3
feet above the floor, is a recessed aperture for a mailbox. At the time the
wall was constructed, the metal mail chute and mailbox were not available for
insertion in place and the space was left to accommodate the chute and box (Tr.
24)s.
10.
Shortly after the wall was constructed, Mr. Roy Erickson architectural engineer
at the building site, advised Mr. Erb, McCloskey & Company’s superintendent
on the building site, that the wall was in his opinion dangerous as originally
constructed and should be partially torn down and rebuilt (Tr. 53).
11.
Mr. Erickson’s employer, Federal Court Architects and Engineers of
Philadelphia, drafted the plans for the building, including the wall in
question. The General Services Administration approved those plans (Tr. 49,
58).
12.
Mr. Erickson’s duties on the building site were to oversee construction and see
that all construction was done according to the plans. It was his duty to
report any defective construction to the primary contractor, McCloskey and
Company (Tr. 58).
13.
Mr. Erickson on ‘at least several occasions’ told McCloskey and Company of the
defective wall after the wall was constructed and was assured by McCloskey and
Company that it would be torn down (Tr. 59, 60, 61).
14.
It was customary business practice on the part of Mr. Erickson and Federal
Court Architects and Engineers of Philadelphia to send written letters of
transmittal and reports to McCloskey and Company and John B. Kelly,
Incorporated, when serious defects in construction became known (Tr. 61, 62).
15.
Although during the time the dangerous wall was standing, many such letters of
transmittal and reports were sent by Mr. Erickson and G.S.A. to McCloskey and
Company and John B. Kelly, Incorporated, concerning other construction defects,
no mention of the ‘dangerous’ wall was made in these letters of transmittal and
reports (Tr. 62, 63).
16.
For the purpose of supporting the wall, a wooden frame was placed by the
Respondent’s employees in the position where the mailbox would be inserted.
This frame is shown in blue on Exhibit C–6 with the long dimension running
vertically and the short dimension running horizontally (Tr. 24, 25)s.
17.
The wall referred to in the previous Finding was constructed sometime in August
by John B. Kelly, Incorporated, as a subcontractor to McCloskey and Company
under the Government Contract No. GS–02B–16025, and John B. Kelly’s employees
constructed the wall at that time.
18.
In August of 1971 it was ascertained that the mailbox, which is delineated in
blue on Exhibit C–7, had been placed incorrectly and would have to be turned to
a position as indicated by the red box appearing on Exhibit C–7 (Tr. 25)s.
19.
On September 27, 1971, Eugene [redacted]
and Clement Jefferson, employees of the Respondent, were instructed to perform
alteration work on the aperture which was to accommodate the mailbox. Mr.
William Sutton, an employee and supervisor of the Respondent, instructed [redacted] and Jefferson to physically
turn the wooden frame placed in the mailbox aperture so that the long dimension
would now run horizontally and the short dimension would run vertically (Tr.
26).
20.
William Sutton orally instructed Mr. [redacted]
to brace or shore this vertical wall with two diagonal 4‘ 4‘ beams before [redacted] was to remove the frame that
was in the position as shown by the green line on Exhibit C–8 (Tr. 26).
21.
Exhibit C–7 shows the wall at the time Mr. [redacted]
started the modification job he was assigned to do by Mr. Sutton. The frame for
the mailbox is in the vertical position (Tr. 27).
22. Exhibit C–8 is what was proposed to be done. The
wall would have to be cut out or undercut a distance of 13’ to the right. The
frame would have to be removed and turned with the longest dimension running
horizontally. There would also have to be some cutting of a wall that was
standing adjacent to the mail chute to the left, a 6’ cut in that was necessary
(Tr. 27)s.
23.
Referring to Exhibits C–7 and C–8, Mr. Sutton instructed Mr. [redacted] to place a diagonal brace
against the wall somewhere above the lintel and to ‘tie it into the wall’ so
that the edge of the brace would fit into the wall and run diagonally to the
ground in two dimensions, (Tr. 29)s.
24.
Sometime after Mr. Sutton spoke to Mr. [redacted]
on September 27, 1971, Mr. [redacted]
proceeded to do the job that he had been instructed to do (Tr. 29)s.
25.
Subsequent to Mr. Sutton’s instructions and after Mr. [redacted] had commenced on the job, Mr. Roy J. Erickson,
architectural engineer on the project, had occasion to visit the work site
where Mr. [redacted] was engaged and
told him to get away from the job, that he was jeopardizing his life, and told
Mr. [redacted] that Mr. Erickson
intended to see his supervisor. He told Mr. [redacted]
that the wall was not shored or braced properly and that he should get away
from there because it was dangerous (Tr. 29)s.
26.
When Mr. Erickson observed Mr. [redacted]
working on the wall, he did not observe any diagonal bracings supporting the
wall (Tr. 30)s.
27.
Subsequent to Mr. Erickson’s visitation, Mr. James Butler, the Safety Engineer
for the general contractor, McCloskey and Company, visited the work site and he
observed Mr. [redacted] working on
the wall and that he was just about ready to remove the frame. Butler told [redacted] to get away from there, that
it was dangerous and that the wall was not properly braced. Mr. Butler also did
not observe any diagonal bracings at that time (Tr. 30)s.
28.
Mr. Butler returned about 20 minutes to one-half hour later and observed Mr. [redacted] still working on the wall
without the diagonal bracings and again warned him to get away from the wall,
that the situation was dangerous (Tr. 31)s.
29.
Subsequent to Mr. Butler’s second visit, Mr. William Sutton again returned to
the work site sometime around 10:00 a.m. or 10:15 a.m. and observed Mr. [redacted] working on the wall. There
were still no diagonal bracings in place.
30.
Mr. Sutton observed that Mr. [redacted]
had placed a vertical 4‘ by 4‘ brace vertically in the opening from whence he
had removed the frame as shown on Exhibit C–8. (s)
31.
Mr. Sutton advised [redacted] to
place the diagonal bracings as he had been previously instructed to do, in that
the present condition of the wall was dangerous. Sutton advised that when [redacted] would begin to undercut the
aperture the wooden frame would have to be removed and that the wall might
collapse unless the diagonal bracings were in place. Sutton left sometime
within about two or three minutes after his conversation with Mr. [redacted] (Tr. 31, 32)s.
32.
Subsequent to Mr. Sutton’s leaving the site, Mr. Clement Jefferson testified
that Eugene [redacted] said to him,
‘I wonder what is going to happen when I remove this vertical shore.’ [redacted] did remove the vertical shore
and the wall came down and crushed Mr. [redacted]
sometime around 10:30 a.m. to 10:45 a.m.
33.
The diagonal bracings ordered by Mr. Sutton, the superintendent for the
Respondent, had never been put in place.
34.
Mr. Erickson and Mr. Israel Kremer, also an architectural engineering
representative, testified that the wall, without the wooden frame, would be
dangerous unless it was shored or braced properly. The wall would become more
dangerous as Mr. [redacted] continued
to undercut 13 inches into the base of the wall, which would leave a 5–4‘ wall
resting on a 2–4‘ base (Tr. 32 and Exhibit C–8)s.
35.
The job that had been assigned to [redacted]
to perform involved not only the turning of the box as shown in Exhibit C–8,
but the building of a ‘return’ of cinderblock to the left below the lintel as
it appears on Exhibit C–8. Thus, the opening which appears opened on this
exhibit would now be closed, and the opening above the red line would be filled
in with cinderblock all the way back to the position of the mail chute (Tr. 33)s.
36.
The construction referred to in the previous Finding of Fact would obviously
prevent shoring from being put in the opening in a vertical position since it
would have to be removed from the rebuilding of the return wall and, therefore,
the instructions given by Mr. Sutton about diagonal bracing was necessary to
properly perform the alteration job (Tr. 33)s.
37.
After the wall collapsed the plans were changed so as to provide more lateral
support (Tr. 69–72).
38.
The parties stipulated that a Compliance Officer for the District Office at
Philadelphia, Mr. Elmo Daugherty, made an accident investigation on September
29, 1971, two days after the accident; interviewed a number of these persons
who would have testified; and on the basis of his interviews, prepared a
report. He submitted his report to his supervisor, Mr. Donald Allendorff. Mr.
Allendorff, based on the report submitted by Mr. Daugherty, issued the citation
for the serious violation, for the abatement period, and the proposed penalty.
Mr. Allendorff also issued nonserious violation citations (Tr. 39)s.
39.
In September 1971 the wall was materially changed by two employees, Eugene [redacted] and Clement Jefferson. These
men were employees of John B. Kelly, Incorporated, the Respondent (Tr. 41)s.
40.
Mr. Markegene, witness for the Respondent, testified that shoring instructions
had been given to [redacted] by
William Sutton (Tr. 45)s.
41.
Mr. Roy J. A. Erickson, an engineer who works for Federal Court Architects and
Engineers of Philadelphia, testified at some length to the conditions that
existed prior to and at the time of the accident (Tr. 47–81).
42.
Erickson testified that the wall that was constructed was not tied into the
ceiling and was a free standing vertical wall, roughly about 18 feet high. This
wall was not tied into the ceiling in any way. There was a 9 inch recess that
ran vertically for a distance of about 13 feet from the top. At the base of
this recess or mail chute was an opening in which a mail box would be placed.
When this wall was observed in August 1971 the mail box opening was 4X3 26’.
This mailbox was placed in a vertical position incorrectly and it should have
been in a horizontal position. The mail chute and mailbox were not placed in
the wall at the time it was constructed, because this material was not on the
job site (Tr. 28–50).
43.
Erickson testified that to properly have built the wall, the mailbox and the
chute should have been on the job and installed. The chute itself indicates on
the drawing that it is to be imbedded in the 8-inch concrete masonry unit wall.
Instead of that the Respondent elected to build a chase, an open chase. From
the column to the chase was a masonry wall about 16‘ long and then there was a
chase which was entirely open and then the other section of the wall was about
five feet long (see exhibit C–6) (Tr. 51).
4.
The mail chute was approximately 3 5/8 inches deep and about 8 3/4 inches long,
so that the depth would have received a number of inches of concrete block on
either side of the chute itself and the wall would have all been tied in
together (Tr. 52).
45.
The wall was not tied in and therefore was free standing and stood in this
condition for approximately two months (Tr. 52).
46.
The frame that was placed into the wall where the mailbox would be placed
actually supported the wall at the time the wall was constructed (Tr. 53).
47.
Erickson testified that he observed that the frame had been placed in the wall
incorrectly and would have to be removed. His recommendation was, therefore,
that the wall be torn down completely to the bottom of the frame and that this
procedure was agreed upon by the Respondent (Tr. 53).
48.
Erickson testified that it was Mr. William Sutton who had agreed to tear the
wall down completely to the bottom of the frame (Tr. 53).
49.
On cross examination, Mr. Erickson testified that he did not think it was
proper that the wall should have been built in August 1971 before the mail
chute and mailbox arrived on the job site and incorporated in the constructed
wall (Tr. 72).
50.
Erickson testified that they (the Respondent) assured him that they would not
touch the wall, that it was going to be removed and torn down and built
properly. ‘If they had followed the plans of specification at that time,
everything would have been just fine’ (Tr. 78. See also Tr. 80 and 81).
51.
Erickson answered in the affirmative that it was his opinion that the wall free
standing without the mailbox and chute created a hazard, and that a further
hazard existed because of the fact that the box or frame was in the wall
incorrectly and subsequent work would have to be done (Tr. 81).
52.
Mr. Jefferson, Mr. Sutton, Mr. Butler, Mr. Erickson, Mr. Stevenson, Mr. Kremer,
and Mr. Vallery were all present at the hearing held in this matter on March
28, 1972. Mr. Markegene, witness for the Respondent, acknowledged that the GSA
general order for accident and fire prevention in construction and alteration
work, referred to as document PBSP 5900.3, had been received by the Respondent
and a copy was in their office (Tr. 101).
53.
William Sutton was assigned by Mr. Markegene as supervisor of the entire
masonry construction job at the federal courthouse. Part of this job was the
construction of the wall in question (Tr. 103, 104).
DISCUSSION
The
basic relevant facts in the instant case as detailed above have been stipulated
to by the parties and are not here in dispute.
The
facts indicate that the 17 foot free standing masonry wall, which collapsed and
killed Eugene [redacted] on September
27, 1971, was unsafe at the time of its erection in August of 1971, and on
September 27th at which time the modification of the wall was attempted. The
Complainant has presented testimony that in August of 1971, Mr. Erickson, the
architectural engineer, advised the company that the free standing wall was
unsafe and would have to be torn down to a 2 1/3 foot base. Mr. Erickson
testified that the wall was likely to collapse because the metal mail chute and
mailbox had not been installed in the wall at the time of its construction and
that Mr. William Sutton, Respondent’s supervisor, had agreed on behalf of the
Respondent to tear the wall down.
The
wall was not torn down by the Respondent, and on September 27, 1971, Eugene [redacted], an employee of the
Respondent, together with a co-worker, Mr. Clement Jefferson, were instructed
to perform certain modifications thereon. On the day in question Mr. Sutton
orally instructed Mr. [redacted] to
provide two diagonal 4‘X 4‘ braces to the wall before he attempted the
modification job. Subsequent to Mr. Sutton’s instruction, Mr. [redacted] commenced the work in
contravention of the instructions of his supervisor. Additional testimony of
Mr. Butler, Mr. Erickson, and Mr. Sutton, showed conclusively that these three
men, within a period of two hours, observed the conditions under which Mr. [redacted] was attempting to modify the
wall and together, warned [redacted]
five times, of the dangerous and hazardous condition that existed.
In
summary then, the hazard of a possible collapse of the wall likely to cause
death or serious physical harm to employees was known to William Sutton,
Respondent’s supervisor, assigned by the Respondent as supervisor in charge of
the masonry work in question, and to others who enjoyed no supervisory power over
the employee. Mr. Sutton was at the site of the wall collapse at two different
times on the morning of September 27, 1971, prior to the collapse of the wall.
Both times he warned Mr. [redacted]
to follow the instructions given to him as to the diagonal bracing of the wall
in question.
The
undersigned also notes that Mr. Erickson and Mr. Israel Kremer, the
architectural engineering representative, both testified that the wall which
was sought to be modified would constitute a dangerous condition unless it was
properly braced with diagonal bracings. Further testimony elicited from the
witnesses showed that the rectangular wooden frame that was supporting the wall
would have to be removed from Mr. [redacted]
to complete his modification task. When this frame would be removed by Mr. [redacted], then the 17 foot high free
standing masonry wall which was 56‘ in length would be resting on a 24‘ base
without appropriate or adequate support.
In
September of 1971 the Respondent, who had constructed this wall, undoubtedly
recognized the hazards of the wall collapsing and injuring persons, since
according to the undisputed testimony, William Sutton advised the employee who
was to perform the modification on the wall to diagonally brace the wall. There
can be no question that the diagonal bracing instructed to be placed by Mr.
Sutton would be for no other purpose than to prevent the collapse of the wall.
Subsequently, Erickson and Butler warned [redacted]
of the serious condition. In fact, Erickson testified that he went to various
locations at the work site looking for Sutton to advise Sutton of the imminent
danger occasioned by [redacted]’s
work on the wall. Sutton again returned to observe [redacted] performing his work. At the time of Sutton’s return, the
diagonal braces were still not in place.
The
evidence makes it abundantly clear that with full knowledge of the serious
hazard represented by the free standing wall, Mr. Sutton, the Respondent’s
supervisor, twice observed the deceased employee commencing the wall modification
work without first bracing the said wall with diagonal supports, which
procedure was contrary to Sutton’s instructions.
On
each occasion (and most decidedly on the second occasion) the Respondent, then
standing in the shoes of its supervisor Sutton, and obliged under the Act, to
furnish to its employees a working environment free from recognized hazards as
well as from the viewpoint of practical on-the-job safety principles, had the
duty and obligation to insist and insure that the errant employee comply with
the bracing directives before proceeding further with the precarious
modification. The evidence demonstrates, however, that the Respondent, through
Mr. Sutton, failed to meet either the statutory or the common-sense obligation
noted above, when he merely cautioned the employee of the danger involved in
continuing the modification attempt in disregard of the bracing instructions.
Mr. Sutton at that time had the obligation to remain on the scene in order to
insure that the employee who had twice contravened the instructions, had
properly carried them out.
The
Respondent argues that such a procedure would require the employer to furnish
one supervisor for each employee, an ‘enormous’ burden and one which Congress
did not intend under the Act. It appears clear to the undersigned that on the
facts in this case, as outlined immediately above, the Respondent’s ‘one on
one’ argument is at the very least, misplaced.
The
facts clearly show that had Mr. Sutton simply remained with or periodically
checked the employee on either of the two specific occasions on which he
directed the required diagonal bracing to be set up and thereby insured that
the construction of the bracing had been commenced and completed, the
Respondent’s statutory and non-statutory obligations would have thus been met.
Such a simple ‘one shot’ surveillance or observation designed to insure that
the employee was carrying out safeguards ordered for his welfare, and the
welfare of others at the work site, falls far short of constituting the
‘enormous’ burden which the Respondent perceives as ‘furnishing one supervisor
for each employee’ and a ‘one on one’ basis, and was an obligation which the
Respondent could and should have assumed, in order to render the workplace
hazardless.
In
its proposed conclusions of law and reply memorandum the Respondent in effect
additionally argues that the Secretary’s action was brought against the wrong
Respondent, and that it was the general contractor, the Government Services
Administration, and the Federal Court Architects and Engineers of Philadelphia,
who violated the Act. This contention is based inter alia on the proposition
that the Respondent’s ‘sole responsibility for the construction of the wall
simply was to carry out the orders given by McCloskey and Co.;’ that McCloskey
and Co. and the aforementioned groups ‘allowed’ the obviously unsafe wall to
stand unsupported; that the Respondent having no ‘control or knowledge of the
plans for the wall’ could not have recognized its inherent defects; that the
site of the tragic accident was not a ‘place of employment’ of John B. Kelly,
Inc., the Respondent; that the deceased employee, Mr. [redacted], was contributorily negligent, and Sections 5(a) and 17
of the Act ‘imply’ that contributory negligence is a defense to a citation for
violation of the Act, as is the showing of assumption of risk on the part of
Mr. [redacted] which is demonstrated
in the record.
The
main thrust of the Respondent’s contentions involves the premise ‘that because
the primary contractor was the ultimate employer and was directly responsible
for activities on the building site, the ‘place of employment’ was that of
McCloskey and Co.,’ and not the Respondent.
In
his reply memorandum the Respondent perceives the salient issue in this case as
the ‘placement of responsibility under the Act for the collapse of a wall at
the site of construction of a federal court house . . .’ and infers that the
complainant has obscured this issue, persistently refusing to deal with facts
relating to who was responsible for the construction of the wall in question,
and reasserting its position as noted above that it was the general contractor,
and not the Respondent who had responsibility for the actual construction of
the wall. The Respondent urges that it was ‘actually the employee’ of the
general contractor and ‘as such, was only the innocent instrumentality of
McCloskey and Co. in building the wall.’ The Respondent further argues that
since McCloskey and Co. was the primary contractor responsible for the erection
of the wall, it was also responsible for correcting the wall’s defects; that
the Respondent was not responsible for the wall being without lateral support;
that it was McCloskey and Co. which ordered the alteration or modification work
on the wall; and repeats that the Respondent’s sole function in the
construction and alteration of the wall was to carry out instructions of the
‘ultimate employer on the job site,’ and it exercised reasonable diligence in
doing so.
I do
not agree with the Respondent’s contentions as outlined in its memoranda, and
as referred to above.
The
single issue remaining for determination in this case is whether or not there
was a serious violation by the Respondent under section 5(a)(1) of the
Occupational Safety and Health Act.
As
the Complainant has asserted, section 5(a)(1) ‘is forceful in its brevity.’ It
reads:
Sec. 5. (a) Each employer——
(1) shall furnish to each of his employees
employment and a place of employment which are free from recognized hazards
that are causing or are likely to cause death or serious physical harm to his
employees.
This
is the salient issue under the statute involved and the issue is not, as the
Respondent argues, ‘the placement of responsibility under the Act for the
collapse of a wall. . . .’ We are here concerned with a remedial statute
designed inter alia to assure safe and healthful working conditions for ‘every
working man and woman in the Nation.’ Section 5(a)(1) above, of that statute is
clear and unambiguous in its face, and does not lend itself to being distorted,
perverted or weakened by interpretations of its plain meaning which may spring
from tort, agency or contract law, applicable in other non-statutory contexts.
The
question of the Respondent’s tort liability and its collateral aspects
involving the law of agency and/or contracts is not at issue here, and may not
serve to either diminish or eliminate the Respondent-employer’s general duty
under the Act to furnish to each of his employees employment and a place of
employment free from recognized hazards.
In
view of the above, it would then follow that the employer’s ultimate compliance
responsibility may not be diminished by principles of tort law, including the
principle of contributory negligence.
Responsibility
for compliance with the Act is not transferred from the employer to his
employee. Such a consequence is contrary to the Congressional intent underlying
the Act as stated in Senate Report No. 91–1282, 91st Cong., 2nd Session, 1970,
at page 149, wherein it is stated:
The committee does not intend the
employee’s duty provided in section 5(b) of the Act to diminish in any way the
employer’s compliance responsibilities or his responsibility to assure
compliance by his own employees. Final responsibility for compliance is with
the employer.
In a
strikingly similar case, cited by the Complainant, Review Commission Judge
Joseph L. Chalk, in treating with the employer’s contention that he was
blameless on principles of tort law, asserted, and as to that specific issue I
am in agreement with his views as expressed below:
While other contractors or individuals in
similar factual settings may be responsible under tort law for their actions of
commission or omission that result in death or injury to another’s employee,
such a fact, when established, does not relieve the employer in question of his
unique obligation under the Act to furnish each of his employees a place of
employment free from recognized hazards . . . especially under the
circumstances where the employer perceives the potentiality of a hazard and
initiates measures calculated to avoid it.[1]
In
line with the last portion of the above quotation the Complainant notes that
William Sutton, employed by the Respondent as a supervisor, similarly
‘perceived’ the potentiality of grave harm to employees at the work site which
the modification of the wall presented, and Sutton also ‘initiated’ (but did
not complete) ‘measures calculated to avoid’ the recognized hazard.
There
is no doubt that because of the number and variety of ‘employers’ on a given
construction site at one time, and the contractual pyramid under which such
projects operate, an Occupational Safety and Health Administration compliance
officer may find it difficult in certain situations to determine which of these
‘employers’ violated the general duty clause (see paragraph 13(a)(2)(d) of
Chapter VII of the OSHA Compliance Operations Manual), as such clause pertained
to its employees, but on the facts in the captioned case it appears only too
clear that the dictates of the general duty clause extended uniquely to the
Respondent named herein, and not to the general contractor, McCloskey and Co.
as the Respondent contends.
The
evidence demonstrates that the Respondent on September 27, 1971, when the wall collapsed,
exercised effective control of at least that specific area of the overall
general work environment where the modification work was initiated; that the
only employees there and then affected by the hazard were employees of the
Respondent out of a total of approximately 48 workers which the Respondent
employed at the workplace on that day; that the Respondent recognized the wall
and the modification thereof as a hazard; that the supervisor empowered to
direct the modification work and give orders to the workers involved therein
was an employee of the Respondent; that the employee killed in the wall
collapse was employed by the Respondent; that the last clear chance to rectify
or eliminate the recognized hazardous condition resided in the Respondent,
through its supervisor, Mr. Sutton.
These
facts clearly indicate that it is the Respondent (who conceded it is an
‘employer’ within the meaning of the Act) and not McCloskey and Co., the
general contractor (as the Respondent contends) who breached its general duty
to its employees, by failing to furnish the said employees with a non-hazardous
work site.
The
instant situation is clear on its face and is not susceptible of being
distorted by contentions based upon non-statutory concepts, and principles of torts,
contracts and agency. The prime actor here from the statutory standpoint was
the Respondent. The attempt of the Respondent to stretch section 5(a)(1) of the
statute so that its general duty clause covers McCloskey the general
contractor, who remained comparatively absent and remote from the activities
described above relative to the wall, appears utterly without foundation,
either factual or legal.
In
summary therefor, substantial evidence exists to support the conclusion that
the Respondent in the captioned case, violated section 5(a)(1) of the Act by
failing to furnish to the employees employment and a place of employment free
from recognized hazards causing or likely to cause death or serious physical
harm to said employees. The Respondent’s failure in this regard being
manifested by a lack of adequate supervision in the carrying out of an
undercutting and removal operation of masonry material from a free standing
masonry wall which inadequate supervision resulted in the wall’s collapse and
the unfortunate death of one of the Respondent’s employees.
CONCLUSIONS OF LAW
Based
upon all of the foregoing, the undersigned concludes that:
1.
Jurisdiction of this proceeding is conferred upon the Occupational Safety and
Health Review Commission pursuant to section 10(c) of the Occupational Safety
and Health Act of 1970.
2. At
all times relevant herein, John B. Kelly, Incorporated, the Respondent, was an
employer engaged in a business affecting commerce and employed employees within
the meaning of section 3(5) of the Act and is subject to the requirements of
the Act.
3.
The employer did not furnish to each of its employees, employment and a place
of employment which were free from recognized hazards that were causing or were
likely to cause death or serious physical harm to said employees, in that:
(a) The employer did not take adequate
precaution or provide proper supervision in an operation to undercut and remove
masonry material from a masonry wall, which ultimately resulted in the collapse
of the wall; and
(b) The employer did not temporarily shore
or brace, or cause to be shored or braced, a masonry wall until the designed
lateral strength was reached to prevent collapse due to wind or other forces,
as required by ANSI Standard A 10.9(12.5) as adopted by 29 CFR 1518.700(a), as
adopted by 29 CFR 1910.12.
4. A
recognized hazard, likely to cause death or serious physical harm, exists where
the Respondent fails to insure through adequate supervision, the adequate
diagonal bracing and supporting of a free standing masonry wall, 17 feet in
height, 54‘ in width, prior to undercutting said wall, so that it will stand
only on a 24‘ base.
5.
The Respondent violated section 5(a)(1) of the Act in that it failed to furnish
to each of its employees, employment and a place of employment which were free
from recognized hazards that were causing or were likely to cause death or
serious physical harm to its employees, in the manner and means noted above.
6.
This violation constituted a serious violation of the Occupational Safety and
Health Act of 1970 (29 U.S.C. § 654), and the penalties proposed by the
Philadelphia Area Director of the Occupational Safety and Health Administration
were reasonable, proper, and warranted under the circumstances.
7.
While the Respondent does not dispute the proposed penalty of $550.00 for the
aforesaid violation as being unjust or unreasonable, in view of the gravity of
the hazardous condition which the Respondent permitted to exist, and the
resultant related fatality, the said penalty is concluded to be inappropriate.
8.
The Respondent violated section 5(a)(2) of the Act in his admitted
non-compliance with the following safety standards promulgated thereunder:
(a)
29 CFR 1518.250(a)(3), as adopted and described in Item 1 of the Citation
(nonserious).
(b)
29 CFR 1518.250(b)(5), as adopted and described in Item 2 of the Citation
(nonserious).
(c)
29 CFR 1518.500(b)(8), as adopted and described in Item 3 of the Citation
(nonserious).
9.
The reasonableness of the abatement periods applicable to the aforesaid
violations is not disputed by the Respondent and under the pertinent facts and
circumstances were properly fixed.
10.
The total proposed penalty assessed for the nonserious violations, which
amounted to $44.00, while not opposed by the Respondent is found to be
inappropriate and unsuitable in that the assessment of such penalty in light of
other relevant factors including good faith, fails to serve any useful purpose
in effecting continuing and future compliance on the part of the Respondent
with the letter and spirit of the Act.
ORDER
In
view of all the foregoing, and good cause appearing therefore, it is ORDERED
that:
1.
The applicable proposed penalty of $550.00 relating to the Citation for Serious
Violation is reassessed to $1,000.00.
2.
The Citation alleging the ‘non-serious’ violations, as described in Items 1
through 3 therein, is affirmed in all respects, except that the total proposed
penalty of $44.00 assessed for such violations is hereby vacated.
[1] (See Secretary of Labor v. Thorlief Larsen & Son, Inc., OSHRC Docket No. 370; reported in BNA Occupational Safety and Health Reporter, 57, June 1, 1972, at pages 1255–1256.)