UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 77-1895 |
NORANDA
ALUMINUM, INC., |
|
Respondent. |
|
May 7, 1979
ORDER
Before CLEARY, Chairman; BARNAKO AND COTTINE,
Commissioners.
BY THE COMMISSION:
On
August 16, 1978, Administrative Law Judge Alan M. Wienman issued his decision
and order in this case, affirming a single serious violation of the
Occupational Safety and Health Act of 1970, 29 U.S.C. §§ 651-678 [hereinafter
referred to as ‘the Act’], for respondent’s failure to comply with the standard
published at 29 C.F.R. § 1910.176(b)[1] and assessing a penalty in
the amount of $400, as proposed. The case was not directed for review by the
full Commission pursuant to section 12(j) of the Act. Thereafter, respondent
petitioned for review of the decision of the Judge to the United States Court
of Appeals for the Eighth Circuit. The petition for review was granted.
On
March 8, 1979, the Court of Appeals for the Eighth Circuit issued a decision in
Noranda Aluminum, Inc. v. O.S.H.R.C. and Marshall, No. 78-1861 (8th
Cir., March 8, 1979). In its decision, the court affirmed the finding of the
violation and the assessment of the $400 penalty. The court, however, vacated
the date in the citation by which abatement was to be accomplished because
respondent had changed the methods of stacking and securing that were the
subject of the citation in this case while the administrative proceedings were
pending. Accordingly, the court remanded the part of the case involving the
abatement order for proceedings by the Secretary consistent with the following
instructions:
If upon reexamination the [Secretary]
finds that petitioner is in compliance with applicable requirements, well and
good. Otherwise, in fairness we think that the [Secretary] should advise
petitioner what it needs to do in order to get into compliance and should give
petitioner a reasonable but limited time within which to do so. Should the
dispute between petitioner and [Secretary] persist, the latter can always issue
a new citation and additional proceedings can be had. Id, slip op. at 7.
Although
the court did not, in its opinion, explicitly direct the Commission to take any
action, this order is issued to implement and take action as follows: (1) Commission
retains continuing jurisdiction of this matter until all aspects of the case,
including abatement, are final under section 10(c) of the Act.
Therefore,
it is hereby ORDERED that the Secretary shall examine respondent’s altered
stacking procedures and take action as follows: (1) If the Secretary determines
that the modified procedures are in compliance with the cited standard, the
Commission shall be so notified. Abatement will be considered to be
accomplished and the case will be closed effective the date of receipt of the
Secretary’s notification that the modified stacking methods are acceptable. (2)
If the Secretary determines that the modified stacking procedures are
inadequate, he will issue to respondent abatement instructions and fix a date by
which abatement is to be accomplished. The Commission shall also be given
notice of this action, and, if there is no dispute, shall enter an appropriate
order. (3) In the event a dispute arises under the terms of the cited standard
either over the adequacy of respondent’s modified stacking procedures or over
instructions issued by the Secretary under part (2) of this order, the matter
will be submitted to the Commission for appropriate action.
FOR THE COMMISSION:
RAY H. DARLING, JR.
EXECUTIVE SECRETARY
DATED: MAY 7, 1979
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 77-1895 |
NORANDA
ALUMINUM, INC., |
|
Respondent. |
|
FINAL ORDER DATE: October 5, 1978
DECISION & ORDER
APPEARANCES:
EUGENE F. DESHAZO, Esq., U.S. Department
of Labor, Office of the Solicitor, Kansas City, Missouri, for the Complainant
GERALD TOCKMAN, Esq., 706 Chestnut Street,
St. Louis, Missouri, for the Respondent
WIENMAN, JUDGE, OSHRC:
STATEMENT OF THE CASE
This
is a proceeding pursuant to section 10 of the Occupational Safety and Health
Act of 1970 (29 USC 651 et seq., hereafter called the Act) contesting a
Citation for serious violation issued to Respondent June 1, 1977. The Citation
for alleged violation of occupational safety regulation 29 CFR 1910.176(b)[2] resulted from a fatality
investigation conducted during a period from May 18–20, 1977, at Respondent’s
plant in St. Jude Industrial Park, Marston, Missouri. The alleged violation was
described on the Citation as follows:
The storage of material created a hazard:
a) At the 7 (seven) inch billet pole
storage rack area at north end of bay 2, in the metal services building the
L-Racks, spacers, and retainers did not prevent the billet poles from rolling
off the top of the rack.
Complainant
proposed a $400 penalty in connection with the alleged violation. After Complaint
and Answer were filed, a hearing was held on February 21, 1978, at Cape
Girardeau, Missouri, with both parties present and participating.
THE ISSUES
No
jurisdictional matters remain in issue, the parties having pleaded facts
sufficient to establish that Respondent is subject to the Act and that the
Commission has jurisdiction of the parties and the subject matter.
The
issues for decision are whether Respondent violated occupational safety
regulation 29 CFR 1910.176(b) as alleged in the Citation, and if so, what
penalty is appropriate for said violation.
SUMMARY OF THE EVIDENCE AND DISCUSSION
Five
witnesses testified at the hearing, all appearing on behalf of Complainant.
These included the OSHA Compliance Officer who conducted the inspection, and four
of Respondent’s employees who worked in the cited plant area at various times.
Respondent presented no witnesses, electing to move for dismissal at the
conclusion of Complainant’s case on two grounds: (1) That the cited regulation
is inapposite applying only to completed stacks and storage and not to the
process of stacking and storing; and (2) that the Complainant’s evidence failed
to establish a violation for multiple reasons. The two grounds will be
discussed separately.
Respondent’s
motion to dismiss on the ground that § 1910.176(b) is applicable only to
completed stacking and storing is premised on the theory that the Citation and
Complaint are directed and confined to the fatal accident which led to the OSHA
inspection. This is not the case. Neither the Citation nor Complaint makes any
allegations with respect to the episode on May 13, 1977, when three aluminum
billets rolled off the top row of a rack
(redacted), the metal handler who had made up the stack. Not at issue are
any factual questions concerning the actual manner by which (redacted) assembled the particular
stack, or whether he had completed the stacking process when the billets moved.
The
contest is focused on the charge that billet poles ‘during May 18–20, 1977, and
at times prior thereto’ were stored in violation of § 1910.176(b) which
mandates that materials stored in tiers be ‘stacked, blocked, interlocked and
limited in height so that they are stable and secure against sliding or
collapse.’ The crucial allegation is a failure to secure the stacks to prevent
accidental movement. Construing the standard to apply only to completed tiers
or racks of material does not, in our judgment, render it inapplicable to
Respondent’s workplace. To date the Commission has not defined ‘storage’ in the
context of § 1910.176(b), but the duration or time period that materials must
remain in place in order to constitute ‘storage’ has been a frequent subject of
Commission discussion. In a line of cases dealing with such diverse regulations
as those governing excavations, explosives and blasting agents, and
construction materials handling, the Commission has uniformly ruled that
‘stored’ is synonymous with ‘placed’ or ‘deposited;’ and that temporary
placement of materials constitutes ‘storage.’ See, Secretary v. Perini
Corporation, 5 BNA OSHC 1343, CCH OSHD para. 20,030 (No. 12589, 1977); Secretary
v. Whitcomb Logging Co., 2 BNA OSHC 1419, CCH OSHD para. 19,128 (No. 1323,
1974); Secretary v. Perini Corporation, CCH OSHD para. 22,772 (No.
13029, 1978); Secretary v. Sierra Construction Co., CCH OSHD para.
22,506 (No. 13638, 1978); Secretary v. Gerard Leone & Sons, 6 BNA
OSHC 1512 (No. 14157, 1978). Frequently cited by the Commission in this regard
is the appellate court decision in Brennan v. OSHRC and Dic-Underhill
Construction Corp., 513 F.2d 1032 (2nd Cir., 1975) dealing with regulation
§ 1926.250(b)(1) in re construction material storage.
The
record is not generous in providing a description of Respondent’s production
processes, but witnesses related that billets, stacked in Bay 2 in tiers well
above a man’s head (Ex. C–4), are next either placed on a furnace car or in a
storage area (T. 293). Such deposit or placement is synonymous with ‘storage,’
a contrary interpretation not serving the regulatory purpose. See, Brennan
v. OSHRC & Gerosa, Inc., 491 F.2d 1340, 1343 (2nd Cir., 1974).
We
therefore deny the motion to dismiss based on the ground that the regulation is
inapplicable and consider whether the evidence establishes a violation of §
1910.176(b).
No
witness described in unbroken sequence the manner in which aluminum bars or
billets were processed in the cited area of Respondent’s metal services building,
but composite testimony provides the following general outline:
The
aluminum is melted and cast in molds of various diameters in an area termed the
‘DC pits’ (T. 121). The diameters range from 6‘ to 14‘ (T. 200). The 7‘
diameter bars, cast in ‘drops’ of 40 billets (T. 204), are 300‘ long and weigh
approximately 1100 pounds (T. 35).
After
casting, billets are transported to the inspection area and deposited on the
floor (T. 122). This completes the pit crews’ task, and the inspection area
metal handler assumes responsibility for stacking the billets on L-shaped metal
frames and marking identifying data on the aluminum. This was the function of
Richard Allen on May 13, 1977. Allen was stacking triple tiers of 7‘ billets on
each L-frame, placing eight billets on the lower two tiers and five billets on
the top tier. The completed pattern was three L-frames high with an overall
height of 95‘ (T. 35, 54).
At
various times through the inspection dates Respondent employed other stacking
patterns, but the standard procedure by which the metal handler sought to
secure the racked billets against movement was always a strategic distribution
of devices termed ‘spacer bars’ and ‘retainer clips.’ Whether the procedure was
effective in preventing billets from rolling off the racks is the pivotal issue
in the case.
‘Spacer bars’ are 3‘ x 3‘ blocks of aluminum,
approximately 56‘ to 59‘ in length, inserted at intervals in the billet rows
(T. 33). ‘Retainer clips’ are specially designed devices placed on the end of
the spacer bars to block billet movement (T. 34).
At
the time of inspection the retainers were either of ‘window’ or ‘horseshoe’
(‘U’) design. The rectangular ‘window’ retainers, depicted in Exhibit C–2, are
designed to impede billet movement by tilting and exerting countervailing
frictional force (T. 54). Compliance Officer Robert T. Dwyer constructed a
model in an attempt to demonstrate how this function could be theoretically
defeated if the billet rows were so close as to prevent the retainer from
‘laying over’ (T. 45–53). However, this testimony was considerably impacted by
Dwyer’s admissions that he could not calculate the forces involved (T. 94), and
that he had conducted no tests of the system (T. 80).
The
‘horseshoe’ type retainer presumably functioned in a similar fashion to the
‘window,’ but its physical characteristics were not described by any witness.
It apparently was less frequently used. Dwyer saw none during the inspection
(T. 61), and one employee, George Woollums, testified he saw none prior to (redacted) (T. 141). Another metal
handler, Mike Zoellner, did recall use of the ‘U’ retainers prior to the
accident (T. 277), and one appears in Exhibit C–1, a photograph made by Dwyer.
All
four employee witnesses declared they had observed multiple instances when
retainers failed to keep billets in place (T. 200–201, 207, 220, 270, 278).
Mike Zoellner testified that a 7‘ billet had rolled off on the foot of a relief
man (T. 272). Since Respondent presented no witnesses, the employee testimony
relative to falling retainers and billets stands unrebutted in the record.
Respondent did cross examine in an effort to establish that retainers and
billets did not move without the application of some external force, but
admissions on this point were not elicited from all witnesses (T. 220, 270).
The
employee testimony is persuasive that use of ‘window’ and ‘U’-type retainer
clips did not always result in stable and secure storage of the tiered billets.
Rather, both retainers and heavy billets fell with sufficient frequency to
create a hazard contrary to the mandate of § 1910.176(b). We therefore
conclude that the evidence establishes a prima facie case of violation.
In
concluding that Complainant has succeeded in meeting its burden of proof, we
are mindful of the arguments urged by Respondent in support of a contrary view.
We note, however, that many of Respondent’s contentions are based on a
restricted view of the pleadings and issues which we do not share.
Respondent
contends, inter alia, that there has been a failure of proof because there was
no showing that: (1) That 7‘ aluminum billet stacked eight wide with ‘U’-type
retainers rolled or moved; and (2) that the deceased employee, Richard Allen,
was responsible for his own death, having failed to use retainers on the top
rack and having failed to position L-frames according to company practices.
As
noted earlier in this decision, the resolution of the central issue herein does
not depend on the circumstances of Richard Allen’s death. Complainant made no
allegations in that regard, and the Compliance Officer candidly stated that he
did not know the cause of Allen’s accident (T. 76).
Respondent’s
contention that charge is limited to its procedure while employing one
particular stacking pattern—7‘ billet stacked in rows eight billets wide—has no
support in the pleadings. The Citation identifies ‘the 7 (seven) inch billet
pole storage rack area at the north end of bay 2, in the metal services
building’ as the site of the violation but does not restrict the allegations in
terms of stacking patterns, types of retainer clips, etc. Respondent rather
artfully suggests that the pleadings were narrowed by certain answers
Complainant made in response to interrogatories prior to the hearing. Our
review of the interrogatories and answers reveals no sufficient basis for such
a conclusion.
Also
urged in support of the motion to dismiss are two additional arguments: (1)
That the Citation does not inform the Respondent of what is considered to be a
hazard; and (2) Complainant failed to suggest any means of correcting the
alleged hazard.
Again,
we find neither argument persuasive. The hazard expressly alleged in the
Citation is the manner of storage of material, namely, that ‘the L-Racks,
spacers, and retainers did not prevent the billet poles from rolling off the
top of the rack.’ It is fatuous to insist that the hazard is not clearly
delineated by such express language.
The
contention that Complainant failed to suggest abatement measures is accurate
vis-a-vis the pleadings but does not entirely comport with the testimony.[3] In any event the argument
assumes that the Complainant’s burden in establishing a § 1910.176(b) violation
includes proof of the likely utility of abatement measures. Again, this is not
the case since § 1910.176(b) is a ‘performance standard.’ And the performance
required by the standard is clear enough, namely, storage of material so that
it does not create a hazard but is stable and secure against sliding or
collapse. Section 1910.176(b) therefore may be enforced without proof by the
Secretary of the feasibility and likely utility of abatement measures. Cf., Secretary
v. Hughes Brothers, Inc. (No. 12523, July 27, 1978); Irvington-Moore,
Div. of U.S. Natural Resources v. OSHRC, 556 F.2d 431, 436 (9th Cir.,
1977).
The
violation was serious within the meaning of section 17(k) of the Act in view of
the fact that serious physical harm or death could result from accidental
movement of the heavy billets and the employer could, with the exercise of
reasonable diligence, have ascertained the fact the retainer clips and billets
had often been observed to fall from the racks. Mindful of the gravity of the
violation, the number of employees exposed, and the Respondent’s size, history,
and good faith, we find a civil penalty in the sum of $400 appropriate under
the circumstances.
FINDINGS OF FACT
Having
held a hearing and considered the entire record herein, it is concluded that a
preponderance of the reliable, probative, and substantial evidence supports the
findings of fact set forth in the foregoing summary of evidence.
CONCLUSIONS OF LAW
1. At
all times material hereto Respondent was an employer within the meaning of
section 3 of the Occupational Safety and Health Act of 1970.
2.
Jurisdiction of these proceedings is conferred upon the Occupational Safety and
Health Review Commission by section 10(c) of the Act.
3.
During a period from May 18–20, 1977, and at various times prior thereto in
said month, at Respondent’s workplace in St. Jude Industrial Park, Marston,
Missouri, Respondent violated occupational safety regulation 29 CFR 1910.176(b)
as alleged in the Citation for serious violation issued to Respondent June 1,
1977. There was substantial probability that death or serious physical harm
could result from the violative conditions and Respondent knew or with the
exercise of reasonable diligence should have known of the presence of the
violation. The aforesaid violation was a serious violation within the meaning
of section 17(k) of the Act, and a penalty of $400 is appropriate for said
violation.
ORDER
Based
on the above findings of fact and conclusions of law, it is ORDERED that the
Citation for serious violation issued to Respondent June 1, 1977, is hereby
affirmed and a penalty in the sum of $400 is assessed thereon.
Alan M. Wienman
Judge, OSHRC
Dated: September 5, 1978
[1] The cited
standard reads as follows:
§ 1910.176 Handling materials—general.
(b) Secure storage. Storage of material shall not create a hazard. Bags, containers, bundles, etc., stored in tiers shall be stacked, blocked, interlocked and limited in height so that they are stable and secure against sliding or collapse.
[2] Regulation 29 CFR
1910.176(b) provides:
Storage of material shall not create a hazard. Bags, containers, bundles, etc., stored in tiers shall be stacked, blocked, interlocked and limited in height so that they are stable and secure against sliding or collapse.
[3] Compliance Officer Dwyer (T. 71–72) and George Woollums (T. 142–144, 163) both suggested abatement measures. And curiously enough Respondent, through its cross examination of Mike Zoellner, established that at the time of the hearing it was using newly modified L-frames and retainers. The new retainer is a ‘horse-shoe’ equipped with two teeth on a bar welded to what formerly was the open end of the ‘U.’ The portion of the retainer containing the teeth is bent at angle of some 26° to 27° from the vertical axis. A scale drawing of the new retainer appears in the record as Exhibit R–7.