UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 13068 |
PABST
BREWING COMPANY, |
|
Respondent. |
|
December 23, 1982
ORDER OF REMAND
Before: ROWLAND, Chairman; CLEARY and COTTINE,
Commissioners.
BY THE COMMISSION:
On
December 17, 1982, the Commission issued its decision in Sun Ship, Inc., OSHRC Docket No. 16118. In accordance with the
decision of the U.S. Supreme Court in American
Textile Manufacturing Institute, Inc. v. Donovan, 101 S.Ct. 2478 (1981) (‘ATMI’), the Commission held that
‘feasible’ under the occupational noise standard means achievable. The
Commission overruled the cost-benefit test of feasibility previously set forth
in Continental Can Co., 76 OSAHRC
109/A2, 4 BNA OSHC 1541, 1976–77 CCH OSHD ¶21,009 (No. 3973, 1976), appeal withdrawn, No. 76–3229 (9th Cir.
Apr. 26, 1977), and substituted a test consistent with ATMI.
In
view of this intervening change in law, the judge’s decision with respect to
the alleged violation of section 1910.95(b)(1) is vacated. The case is remanded
for further proceedings, including evidentiary submissions, so that the
interrelated issues of technological and economic feasibility can be
reconsidered in light of the test of feasibility established by Sun Ship, Inc.[1]
SO ORDERED
FOR THE COMMISSION:
Ray H. Darling, Jr.
Executive Secretary
DATED: DEC 23, 1982
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 13068 |
PABST
BREWING COMPANY, |
|
Respondent. |
|
July 25, 1978
DECISION AND ORDER ON REMAND
APPEARANCES:
Stephen J. Simko, Jr., Esquire, Office of
the Solicitor, U. S. Department of Labor, Atlanta, Georgia, on behalf of
complainant.
Mr. J. D. Fleming, Jr., Esquire,
Sutherland, Asbill and Brennan, Atlanta, Georgia, on behalf of respondent.
STATEMENT OF CASE
LARKIN, JUDGE
This
case is on remand from the Occupational Safety and Health Review Commission
(Commission). Respondent (Pabst) operates a brewery at Perry, Georgia. On April
7, 1975, Pabst as cited [2] for a non-serious
violation of section 5(a)(2) of the Occupational Safety and Health Act of 1970
(Act) for failure to conform with 29 C.F.R. § 1910.95(b)(1).[3]
The
areas left in issue are Filling Rooms, I, 2, III East and III West.
In
Filling Room I, cans are filled with beer in two 100-spout fillers, operating
at a rate of approximately 90,000 cans per hour each, for a total filling rate
of approximately 180,000 cans per hour. Two employees operate these fillers. In
Filling Room 2, cans are filled with beer in two 88-spout fillers, each of
which processes approximately 72,000 cans per hour, for a total filling rate of
approximately 144,000 cans per hour. Two employees operate these fillers. After
being filled, the cans from Filling Rooms I and 2 move to a pasteurizer outside
of the filling rooms. Twelve-ounce non-returnable bottles pass from a bottle
sterilizer into Filling Room III East, where they are filled in a 72-spout
filler at a rate of approximately 42,000 bottles per hour. One employee
operates this filler. Returnable and non-returnable bottles, primarily 12-ounce
returnable bottles, pass from the bottle sterilizer into Filling Room III West,
where they are filled in a 100-spout filler at a rate of approximately 36,000
bottles per hour. Two employees, one to operate the filler and one to operate a
soaker-discharger, work in Filling Room III West. After being filled, bottles
pass from Filling Rooms III East and III West into a pasteurizer.
Filling
Rooms I and 2 are approximately 40 feet by 70 feet. Filling Rooms III East and
III West are approximately 40 feet by 60 feet. The rooms have concrete block
walls with plaster ceilings.
The
Packaging Center normally operates on three daily eight-hour shifts. All of the
fillers are operated about 70% of the time during the day shift. As few as two
fillers may be operated on a shift and it is rare that all of the fillers are
run except on the day shift. The operators normally spend between 6.5 and seven
hours per shift in the filling rooms. Other personnel come into the filling
rooms, including maintenance, utility, clean-up, and supervisors but their
exposure time is not in issue.
In
Filling Rooms III East and III West, the operators monitor the filling
operation. They correct bottle jams and feed crowns at the crowner chute. The
operators move along a platform 12 to 14 feet long. If problems occur they
spend 70% to 80% of their time at the crowner, two to four feet away from the
filler. Otherwise, they spend approximately 50% of their time at the crowner.
In
Filling Rooms I and 2, the operators feed lids to the canning machine and
monitor along an 18-foot platform. Approximately 60% of the time is spent
feeding lids to the seamer and 40% is spent at other locations. The operators
feel the cans to detect indentations and remove foreign material in the seamer
causing the problem. The operator must clear jams, sometime to the extent of
using crowbars. The can lines run approximately 70% to 75% of the time.
The
noise measurements on March 12, 1975, and June 23, 1977, in the four filling
rooms were as follows:
Room III
West
|
Location |
98-105 |
platform |
98 |
platform - cap machine |
102 |
platform - filler area |
98-101 |
platform - soaker discharge |
98-100 |
floor - between conveyor and soaker discharge |
Room III
East
|
platform - filler |
98-102 |
platform |
101.5 |
platform - machine running and not filling |
Room 2
|
platform - machine running and not filling |
97-98 |
platform - machine filling |
97.5 |
east machine - cap filling location |
97-98 |
filler area |
97 |
between filling machines |
98 |
behind machine |
Room I
|
west machine - filling platform |
102 |
between machines |
101-103 |
east machine - platform |
101 |
east doorway |
102 |
conveyor line - between machines |
In
areas of possible excessive noise, signs requiring hearing protection are
posted and Pabst employees are required to use personal hearing protectors.
The
workers in Filling Rooms I, 2, III East and III West wear muffs. These muffs
will lower noise at the eardrum by at least 30 dBA or to a level between 68 and
72 dBA.
On
June 23 and 24, 1977, Dr. Thomas H. Melling, Hampshire, England, agreed upon by
the parties as an expert in acoustical engineering and noise control in
breweries, inspected Pabst’s facility to determine the feasibility of
engineering controls to reduce the noise levels. Dr. Melling’s report was
received into evidence by agreement of the parties.
Two
components make up the noise level in a room with machinery running. The first
is the direct noise from the machines. The second is the reverberant level
produced by all of the noise sources in the room. The direct noise level at the
operator’s ear decreases as he moves away from the machine. If the machine is
compact, such as a motor or a pump, the direct noise level decreases by
approximately six dBA with each doubling of the distance from the center of the
machine. For example, if the direct noise level is 102 dBA when the operator is
two feet from a pump, it falls to 96 dBA when he moves to four feet from the
pump. If the machine is elongated rather than compact, such as in the case of a
conveyor line, the direct noise level decreases by approximately three dBA for
each doubling of the distance of the operator from the center of the machine.
For example, if the direct noise level is 102 dBA when the operator is two feet
from a conveyor, it falls to 99 dBA when he moves to a distance of four feet.
The reverberant sound level is constant throughout the room and does not depend
on the location of the operator.
Noise
levels in dBA cannot be added directly. Instead, the total sound power must be
determined by adding the power from each source. The total noise level can then
be calculated from the equation:
L = 10 log (P/C)
where L is the sound level in dBA, P is the sound
power, and C is a constant. As an approximation, a doubling of the sound power
will increase the total noise level by approximately three dBA. If a room
contains two machines, each of which produces a sound level at a given position
of 90 dBA, the total resulting sound level will be 93 dBA. Similarly, if the
direct sound level at an operation’s position is 95 dBA and the reverberant
sound level is 95 dBA, the total sound level at that position will be
approximately 98 dBA.
The
foregoing considerations indicate that the sound level at the operator’s
position in a room containing machinery will be made up of the reverberant
sound level and the direct sound level produced by the machines. If either
noise component greatly exceeds the other, that component will be the major
contributor to the total sound level and efforts to reduce the total sound
level will depend on taking steps to reduce the predominating component. If
both components are of comparable magnitude, reduction of the overall noise
will require reduction of both components.
The direct
noise level may be reduced by a properly designed shield or enclosure which
separates the operator from the sound source. In some cases, it may also be
possible to redesign or modify the equipment in order to decrease the direct
sound power which is emitted. The reverberant level may be decreased by
installing sound absorbing materials in the room in order to absorb a portion
of the reverberant sound energy.
Dr. Melling concluded:
The filling rooms would require treatment
to reduce both the reverberant noise level and the direct noise level. For each
filling room, absorptive treatment is necessary to reduce the reverberant noise
level. The absorbent material specified was a textured vinyl coated tile
manufactured by Owens Corning, Inc., having an absorption coefficient of 0.6.
For the bottle filling rooms, Filling Rooms III East and III West, the direct
noise level could be reduced by enclosing the bottle conveyors with ‘Clear
& Quiet’ panels produced by Body Guard, Inc. The Body Guard panels are made
of corrugated clear plastic, with wedges of plastic-capped foam in the
corrugations. The direct noise from the crowner could be decreased by
installing a shield made of plastic material similar to that used in the Body
Guard screens and the Holstein and Kappert crowner could be modified to reduce
the direct noise level by rebuilding the crown injection system. For the can
filling rooms, Filling Rooms I and II, the direct noise level from the seamer
could be decreased by covering the seamer opening with a plastic material
similar to that used in the Body Guard shields. Also, the direct noise level
could be reduced by enclosing in metal enclosures hydraulic power packs, used
to operate the fillers.
The
engineering controls were itemized and the cost estimated by Dr. Melling as
follows:
AREA |
RECOMMENDED TREATMENT |
COST ESTIMATE |
Filler Room I |
1130 ft2 absorptive
treatment to walls/ceilings |
$ 720 |
|
Screens over seamer open
areas |
$ 800 |
|
Enclosures for hydraulic
power packs |
$2,000 |
Filler Room 2 |
1130 ft2 absorptive
treatment to walls/ceilings |
$ 750 |
|
Screens over seamer open
areas |
$ 800 |
|
Enclosures for hydraulic
power packs |
$2,000 |
Filler Room III East |
2200 ft2 absorptive
treatment to walls/ ceilings |
$1,500 |
|
Bottle conveyor covers |
$1,200 |
|
Conveyor screens at
filler/crowner |
$1,000 |
Filler Room III West |
2600 ft2 absorptive
treatment to walls/ ceilings |
$1,500 |
|
Modifications to H & K
Crowner |
$3,000 |
|
Conveyor screens at
filler/crowner |
$1,000 |
|
TOTAL |
$16,270 |
The
cost estimate was obtained by Dr. Melling by talking with proposed suppliers by
phone.
As an
experiment to test Dr. Melling’s proposals, Pabst installed the above
recommended applications for Filler Room III East adding an additional 100
square feet of absorptive tile. The installation cost Pabst $9,815. Based upon
the difference between Dr. Melling’s cost estimate and Pabst’s actual cost
experience, the total cost of application of the four rooms would be $43,160 in
lieu of Dr. Melling’s estimate of $16,270. This would indicate a cost of the
controls per employee of $1,570 per employee for Filling Room I; $1,556 per
employee for Filling Room 2; $3,272 per employee for Filling Room III East; and
$2,432 per employee per employee for Filling Room III West.
During
the period from 1974 through October, 1977, Pabst spent a total of $6,100.90 to
provide 266 employees with personal hearing protectors at an average annual
cost per employee of $6.12.
Engineering
predictions are made by either theoretical predictions, empirical predictions
or a combination of both. A theoretical prediction is based on a fundamental
analysis of physical phenomena. An example of a theoretical prediction is the
knowledge that the amount of force necessary to accelerate a mass at a given
rate is equal to the product of mass and acceleration. Because theoretical
predictions are based on physical phenomena fully explained, they tend to be
very accurate. In many practical situations, the controlling factors are too
complex to permit theoretical analysis. In such a case, it is necessary to make
an empirical prediction based on experimental data correlated in an orderly
fashion. With empirical predictions, it is not unusual to find errors of 20%.
If theoretical predictions are used without all of the conditions known
accurately or if empirical predictions are used, an error must be anticipated
in the prediction. The techniques which Dr. Melling used in his study were
based on theoretical equations interpreted and applied by using empirical predictions.
This prediction makes heavy use of experience and calls for the application of
judgment. Because judgment is involved, predictions would vary some between
consultants. Dr. Melling anticipated his predictions could error as much as 2
dBA in sould level and 60% in sound power.
Dr.
Melling predicted that the engineering controls which he specified could reduce
the noise level in all four filling rooms to 91.5 dBA. With Dr. Melling’s
estimate of as much as 2 dBA error in his predictions, the actual noise level
resulting from implementation of the controls could be as high as 93.5 dBA.
If
the noise level in the filling rooms could be reduced to 91.5 dBA by
implementing the controls specified by Dr. Melling, the allowable exposure time
without personal hearing protectors would be 6.5 hours. Theoretically, a worker
exposed to 91.5 dBA for 6.5 hours would not need to wear personal hearing
protectors. The normal work day at Pabst consists of eight hours with a lunch
break of 30 minutes and two 15-minute coffee breaks. On days with no equipment
malfunctions, the workers are exposed for seven hours. Because of the
possibility of error in Dr. Melling’s calculations and an exposure on some days
of seven hours instead of 6.5 hours used by Dr. Melling, the filling room
employees would need to continue wearing personal hearing protectors.
In
assessing the effect of a change in sound level, the term ‘doubling rate’ is
used to indicate the sound level decrease, in dBA, which decreases the effect
by one half. A doubling rate of three dBA is internationally recognized as the
proper doubling rate to be used in assessing the effects of a change in sound
level on hearing damage. Under this criterion, hearing damage is a direct
function of the sound power level or the sound energy level.
Using
a doubling rate of three dBA, the percent change in sound power or sound energy
which results from a change in sound level from L1 dBA to L2 dBA is given by
Delta P = 100(10.IL2/10.IL1-1)
To evaluate the effectiveness of a particular noise
control, a cost-benefit ratio, in dollars per percent of sound energy
reduction, may be calculated by dividing the cost of the control of each
protected worker by the percent of sound energy reduction. A high ratio
indicates that the control is costly compared with its benefits.
Pabst
administers pre-employment audiometric tests to all new employees and annual
audiometric examination to employees who are employed in high noise areas. If
any hearing problems are detected, the company refers the employees to the
company physician. Pabst has invested over $5,000 in equipment used in the
hearing conservation program and spends over $3,000 annually on audiometric
tests. The annual cost of the audiometric examination program is $7.58 per
employee tested.
Pabst
has experienced no difficulty in insuring that its employees use personal
hearing protectors. No workmen’s compensation claims for hearing impairment
have been made.
The
Secretary has never adopted any regulations, rules, interpretations, guidelines
or standards to define the meaning of the term ‘feasible’ administrative or
engineering controls.
It is
the Secretary’s practice not to give employers any guidelines or information
which identify feasible controls when a citation is issued. That practice was
followed in this case.
Neither
the citation nor the complaint specified the noise levels alleged to exist at
the cited locations, the amount of reduction in noise levels which complainant
expected Pabst to accomplish, nor any method of noise control which Pabst could
implement in order to abate the alleged violations.
An
abatement period cannot be specified until a specific control is identified, a
supplier is located, and the delivery and installation times have been
determined. The one-year abatement period proposed in this case was not based
on any analysis of these factors.
The
abatement period of one year in this case was selected because it was customary
to set a one-year period since such a period did not require the approval of
the OSHA regional office.
ECONOMIC FEASIBILITY
The
ultimate decision in the case rests upon whether the government has carried its
burden of proving that the proposed engineering controls are ‘economically and
technologically feasible.’ It is concluded that the Secretary has not carried
that burden.
Although
bound by Commission precedent[4] it is difficult to ignore
without comment the validity of respondent’s argument that the term ‘economic
feasibility’ is so vague that it violates the due process clause of the Fifth
Amendment. Respondent argues:
In order for the Commission to hold that
the term ‘feasible’ is sufficiently definite, the meaning of the included term
‘economic feasibility’ must be sufficiently clear that it need not be defined
by statute or regulation in order to inform an employer what he must do to
avoid a violation.
The relevant criteria were stated by the
Tenth Circuit, in the specific context of OSHA standards, in Brennan v. Occupational Safety and Health
Review Commission, 505 F.2d 869 (10th Cir. 1974). The basic rule is:
‘A statute which is so vague that men of
common intelligence must necessarily guess at its meaning and differ as to its
application violates due process. This rule applies to regulations.’ 505 F.2d
at 872 (citations omitted).
The
decision as to whether or not a standard meets this test is ‘governed by the
‘reasonable man’ concept.’ Id at 873.
The noise standard is not impermissibly vague if a reasonable person could
decide whether or not a noise control measure is ‘economically feasible.’
Respondent respectfully submits that neither complainant, respondent nor even
the Commission can reasonably make that decision.
‘.
. . it should be noted that complainant has never promulgated any regulation,
rule, interpretation, guideline, or standard in order to advise the public what
‘feasible’ means. . . .
‘Respondent respectfully submits that the
noise standard does not ‘delineate its reach in words of common understanding.’
Brennan v. Occupational Safety and Health
Review Commission, 505 F.2d 869, 872 (10th Cir. 1974). When a panel of
experts selected by complainant cannot agree on what ‘feasible’ means, and when
complainant’s own industrial hygienist states that ‘it’s a vague term’ which he
cannot evaluate, it would be ludicrous to hold that ‘feasible’ is a word of
common understanding. No reasonable man, no employer, and not even a reasonable
expert can be held at his peril to know what he is commanded to do by a
standard which directs him to employ ‘feasible’ noise controls.’
The
Commission has stated its position in Turner
Co., supra, by quoting the following except from the case of Union Camp Corporation, supra:
‘Any standard given the necessary
specificity, as respondent suggests, to meet the objection of one employer
would be necessity contain variable factors which would call for different
conclusions by different employers under different or even the same
circumstances. It is manifest that engineering or administrative controls can
not be specified to meet the varying noise levels of every employer. Yet all
must be subject to regulation if the objective of the Act is to be achieved.
How does one accomplish this objective? Requiring specifications as to how to
reduce noise levels for every known sound in excess of the permissible limits
would be an insurmountable obstacle to the enforcement of the Act. The
objective of the Act would be totally frustrated insofar as noise exposure is
concerned. Thus the standard must necessarily be expressed in general terms and
depend for its application upon the circumstances of each case. The employer is
required to think and use his expertise gained in the operation of his business
in order to comply with the standard. This is not grounds for declaring a
standard vague and unenforceable. Due process does not require that an employer
be informed as to every course of action he is to take.’
It is
difficult to understand how the compounding of mass confusion furthers the
purposes of the Act. Failure to force the government to establish guidelines in
the noise field will result in many years of useless litigation with the
ultimate cost passed on to the American consumers and especially the American
worker already being destroyed in an economy out of control.
Respondent
correctly points out that what is meant by the term ‘economic feasibility’ will
be as varied as the number of people questioned. To compound such mass
confusion by failing to force the government to set forth guidelines in the
noise field is especially devastating to the small employer fighting for
survival in an attempt to comply with the regulations of a myriad of government
agencies.[5]
How
is the small employer to handle the situation? How is the small employer going
to know how to proceed as to his noise problem? To be exact, to find out what
is required under the present regulation and Commission position, ultimately
requires litigation because each employer, of necessity, cannot know what
‘economic feasibility’ means as to his individual operation. His first recourse
must be an appeal to the Commission. There as is obvious in the Turner case,
supra, his problem is only compounded. The Secretary contends that ‘economic
feasibility’ is limited to whether the costs of the controls would result in
putting the employer out of business. See
Castle & Cooke Foods, A Division of Castle & Cooke, Inc. supra.
Each Commissioner has his own ideas. Then, as in Turner, the case is reversed by the Court for the Commission to
define the term ‘economic feasibility’ as to the specific facts in issue and
the whirlwind begins again. By then the complexity of the Commission has
changed with a new member who probably has his own concept of what is meant by
‘economic feasibility.’ In the interim litigation costs mount and emphasize to
an attorney properly representing large or small employer that his client may
never know what the term ‘economic feasibility’ means as applicable to his
business because he does not have the financial resources to find out—and this
is due process under the Constitution . . . to put the situation in the
vernacular ‘Thomas Jefferson would turn over in his grave.’
Again,
it is mere folly to say that the government cannot tell its citizenry what is
expected of them in the noise field. The Secretary in this case has brought an internationally
recognized expert in the noise field from England at a probable fantastic cost
to defend against the vagueness of the regulation. This witness has joined the
horde of other persons in expressing his understanding of what is meant by the
term ‘economic feasibility.’ If this witness can establish criteria in this
case, then the government could use him to establish published regulations
applicable to the industry. Rather than expend vast sums of money in expert
witness fees and litigation costs, wouldn’t the purposes of the Act be far
greater served by recognizing that the regulation ‘. . . is so vague that men
of common intelligence must necessarily guess at its meaning’ and violates due
process?
Guidelines
must be established. If not done on an administrative level, it will have to be
done by the Courts. The Commission rather than fulfilling its statutory role as
a quasi-judicial body has attempted to establish guidelines as the alter ego of
the Secretary. This function instead was placed by Congress with the Secretary
who has statutory authority to make law by issuing regulations that must muster
due process.
The
ultimate effect of the regulation is that government is saying to its citizenry
‘you tell government what is meant’ rather than the government telling its
citizenry. For the citizenry to find out what ‘economic feasibility’ means
legally it must litigate. This is not government by and for the people, this is
people subservient to and for government.
The
Commission attempts to soften the impact of its position by stating to the
employer, you spend what may amount to thousands of dollars to apply controls
and if your efforts are unacceptable to a government inspector, your good faith
attempt will be rewarded by the Commission as the proposed penalty which can
not exceed $1,000 under section 17(c) of the Act will be adjusted. See footnote
12 of the Commission’s decision in Turner
Co., supra.
Due
process ultimately means fairness. There is no way that fairness can be found
regarding this regulation whether applicable to the Secretary, the Commission,
the worker or the employer. Instead, ridiculous position after ridiculous
position will be justified on the grounds it is a public act involving safety
and health. Does such purpose justify that the basic concepts of a democracy as
protected by the Constitution should be ignored? The purposes of the Act can
not be furthered by attempting to uphold such a vague and indefinite
regulation.
However,
being bound by Commission precedent, an attempt will be made to determine
whether the proposed controls in this case are ‘economically feasible.’ The
Commission has expressed ‘economic feasibility’ in terms of a ‘cost benefit’
concept. More specifically the Commission stated in Continental Can Co., Inc., supra:
. . . any significant reduction in ambient
noise levels which are above G–16 limits will tend to provide some protection
to the hearing of employees. But we cannot overlook the fact that protection
against most of the detrimental effects of excessive noise can be achieved
through the use of a relatively reliable and convenient type of personal
protective equipment. Additionally, the effects of excessive noise are gradual
rather than sudden, and a certain amount of exposure to continuous noise levels
as high as 115 dBA is permitted by the standard itself.
Other factors to be considered in the
benefits which noise reduction will achieve include the number of employees
exposed to excessive noise, and the net reduction in their exposure which engineering
or administrative controls can reasonably be expected to produce. As to the
last noted factor we would emphasize that the benefits to be obtained will vary
according to the magnitude of the noise levels existing prior to the imposition
of controls. Cost factors which must be considered include both the direct
costs of installing and maintaining controls, and indirect costs due to any
loss of productivity or efficiency resulting from their implementation. This
list is not meant to be all-inclusive. We cannot here establish specific
guidelines which will be applicable to all cases. The ultimate determination in
each individual case must be made by weighing all the relevant factors in light
of the objectives of the Act.’
As to the merits, the Secretary contends:
1.
Pabst exposed its employees to noise levels in excess of those listed in Table
G–16.
2.
Pabst failed to utilize feasible administrative or engineering controls to
reduce noise levels and 21 employees were exposed to levels two to four times
those listed in Table G–16.
3.
The government does not have to prove that administrative or engineering
controls are economically or technologically feasible, but even assuming that
it does, it has carried that burden, and
4.
The controls recommended by the government’s expert were available at the time
of the initial inspection.
In
response to the Secretary’s first and second arguments, Pabst concedes that the
noise levels in the areas in issue exceed the levels listed in Table G–16.
Instead, Pabst points to the protection afforded by personal hearing protectors
and the fact such protectors lower the sound levels at least 22 dBAs below the
engineering controls proposed by the expert.[6]
The
parties are in substantial disagreement as to the Secretary’s third argument
and it will be considered in conjunction with Pabst’s contentions.
Pabst
does not pursue the argument on brief that the proposed controls were not
available at the time of the inspection. With exception of the H & K
crowner, Dr. Melling testified that similar materials were being used in Europe
prior to the inspection date.
There
are other areas of controversy as to the facts that must be reconciled. Most
crucial to the case is whether the proposed controls will eliminate the need
for personal hearing protectors. The Secretary assumes this fact on brief and
it is concluded it is not supported by the weight of the facts of record. Pabst
contends that even accepting the expert’s findings, personal protectors must
still be worn. Pabst’s position is supported by admissions of Dr. Melling and
testimony of Pabst’s safety director. The expert’s findings were based upon a
6.5 hour day and a conclusion that the controls would lower the sound levels to
91.5 dBA. The 91.5–dBA level is the maximum permissible exposure time for 6.5
hours under Table G–16. The expert admitted a margin of error and obviously
there would have to be some margin of error in speculating as to the ultimate
sound reduction of untested controls. This possible error was estimated by Dr.
Melling at 1% to 2% in sound level or 60% in sound power (Tr. 211). Also, on
some days the employees are exposed for at least seven hours. For these reasons
the expert conceded:
‘Q So if in fact your prediction is off as
much as 2 DB’s and this is what is found when the controls are tested, then
this is the allowable time. This is the average time, so that on the average
they’re overexposed one and a half hours, and on maximum days they’re
overexposed for two hours?
‘A Yes.
‘Q Now, based on all of that, if you’re
responsible for the safety program at this plant, surely you’re not going to
let the employees discontinue the use of hearing protectors? That’s fair to
say, isn’t it?
‘A That’s fair to say.
‘Q And in fact, unless you could have a very
convincing safety factor in here you probably would not want [to] risk the
health of your employees enough to discontinue the use of hearing protectors,
is that right?
‘A That’s right.’ (Tr. 219)
The
parties are in disagreement as to the estimated costs of the proposed controls.
Dr. Melling obtained his estimated costs by telephoning proposed suppliers.
Pabst installed the proposed controls in Filling Room III East. The actual
experience of Pabst would be entitled to greater weight than cost estimates
obtained by phone due to the possibility of misunderstandings and
misconceptions that are likely to occur during phone conversations.[7] Pabst’s actual cost for
Filling Room III East are more reliable to use as a basis for arriving at
ultimate estimated costs.
In
support of his contention that the proposed controls are ‘economically
feasible,’ the Secretary relies heavily upon the maintenance cost of $5,000,000
expended by Pabst annually and the original equipment costs of approximately
$1,800,000 to $2,000,000. The Secretary argues that one percent of capital
costs of the equipment is convincing that the costs of proposed controls are
‘economically feasible.’
Pabst
argues that the ‘cost-benefit’ concept should be applied by comparing the cost
per dBA reduction per employee provided by personal hearing protectors against
the cost per dBA reduction per employee pr vided by the proposed controls.
Pabst points out that the ‘cost-benefit’ concept must be considered in the
light of whether the proposed controls will eliminate the wearing of the
personal hearing protectors. Pabst emphasizes that personal hearing protectors
reduce the sound levels 22 dBA below the threshold limits at a cost of $6.12
per employee, while even the Secretary’s most optimistic cost figures show $592
per employee and will not eliminate the wearing of the personal hearing
protectors.
The
Secretary’s argument that the costs of the controls are reasonable when
considered in the light of Pabst’s annual maintenance costs and the capital costs
of the equipment adds little to a ‘cost-benefit’ concept. Sizeable capital and
maintenance costs are at most indicative that an employer can afford the
controls. Pabst does not challenge this fact and the Commission majority has
rejected the Secretary’s argument that ‘economic feasibility’ is limited solely
to ability to afford the controls. See
Continental Can Co., Inc., supra.
Pabst’s
approach does add significance to a ‘cost-benefit’ concept. If cost per dBA of
reduction is considered in the light of benefit to each employee, some
guideline is established that could be applicable to all employers irrespective
of the size of the employer or the number of employees involved. Actually, the
benefits to the individual employee in the light of the cost to the employer of
the control for each employee is the crux of what a cost-benefit concept should
be all about. There is no better way to ultimately determine cost-benefit than
by weighing the cost of the control by the amount of sound reduction measured in
terms of dBA. This approach relates directly to Table G–16 and the reality of
whether the control eliminates the wearing of personal hearing protectors.
Although the Commission has held that controls may be required to reduce noise
levels even though the levels specified in Table G–16 are not reached, the fact
that personal hearing protectors are not eliminated is a very important fact to
consider as to the benefit of the control to the employee. Actually from a
‘cost-benefit’ concept the fact that the personal hearing protectors are not
eliminated should be one of the more important considerations. If personal
protectors are not eliminated, the benefit of the proposed control to the
employee is at best minimal. This fact was recognized by the Commission in the
following quote from Continental Can Co.,
Inc., supra, that ‘. . . we cannot overlook the fact that protection
against most of the detrimental effects of excessive noise can be achieved
through the use of a relatively reliable and convenient type of personal
protective equipment.’
As
stated, unless the cost-benefit concept is applied on the basis of cost per dBA
of reduction in the light of benefit to each employee, the concept can not be
made consistently applicable to all employers. By this approach, a definite
guideline is established and there is better possibility of equal and fair
application of the regulation to all employers, irrespective of size or the
number of employees affected.
The
higher the ratio between the costs of the proposed controls and the costs of
personal hearing protectors in situations where the protectors are not
eliminated, the greater the indication that the costs are excessive and the
benefit minimal. The facts in the instant case emphasize the importance of the
recognition of inexpensive personal hearing protectors especially where the
controls fail to eliminate their use. The facts of record show that the
personal hearing protectors cost $6.12 per employee. The Secretary’s most
optimistic cost shows $592 per employee. The personal hearing protector will
reduce the noise conservatively to 68 dBA or 23.5 dBA lower than the
Secretary’s most optimistic assumed results. Pabst breaks down its comparative
cost-benefit argument even further by comparing costs on the basis of percentage
of sound removed by hearing protectors as against the proposed controls. This
comparison indicates a cost-benefit ratio for hearing protectors of six cents
versus $6.50 to $13.89 depending on the filling room involved. The results
become of even greater magnitude when the reduction of percentage of sound
between the protectors and proposed controls are compared.
The
expert testified:
‘Q. Looking at it strictly from the
standpoint of economic feasibility, though, if I can get down to 68 dBA at a
cost of $6.12, you agree with me that purely on an economic basis, given the
choice of these two, the economic choice, of course, must be hearing
protectors?
‘A Yes.
‘Q And I think you said earlier that
really, hearing protectors, anytime this is an allowable choice, is bound to be
the better economic choice?
‘A Yes.
‘Q On an economic basis, there’s no
question in your mind that hearing protectors are economically the preferable
choice?
‘A In this instance, yes.’ (Tr. 301).
The
facts indicate in the instant case an extremely high costs ratio and the
protectors must still be worn. When these facts are weighed in the light of the
admissions of the government’s expert witness as to cost-benefit concepts, the
only logical legal conclusion remaining is that the Secretary has failed to
carry his burden of proving that the proposed engineering controls are
‘economically feasible.’
ENGINEERING FEASIBILITY
Pabst
questions whether the acoustical tile and the Body Guard shield can be used in
its plant because of sanitation problems. It relies upon Great Falls Tribune, supra, holding that the Secretary’s burden
includes proof that the proposed controls can be used in the employer’s
workplace.
Dr.
Melling testified that the Body Guard could be designed without the acoustical
material. Although this testimony is an ultimate conclusion of fact, in view of
his expertise, the statement is accepted as sufficient to carry the Secretary’s
burden.
However,
a different conclusion must be drawn regarding the acoustical tile.
Dr.
Melling did not determine the working environment in the filling rooms. He did
not determine the hazard involved from movement of cartons, ladders or other
devices that might damage the tile. Although he testified that tile was
intended to be placed higher than the workmen, this does not assure that
cartons and the necessity to use ladders would not damage the tile. Obviously,
a vinyl coating no thicker than one thousandth of an inch would be very
susceptible to sharp edges or an object exerting even slight pressure. Dr.
Melling’s statement that the tile had been used in breweries in Europe or on
offshore platforms is not sufficient to shift the burden back to Pabst to go
forward with the evidence, much less sufficient to carry the Secretary’s burden
of persuasion. The reason, of course, is that the Secretary failed to lay
foundation that Dr. Melling knew the working conditions at Pabst or that the
breweries in Europe were the same in design as Pabst’s facility and, of course,
there was no foundation laid that the operation at Pabst has any bearing to
offshore platforms. To emphasize the problem with the Secretary’s failure of
proof, Dr. Melling’s pertinent testimony was as follows:
‘Q All right. Now, again, in answer to my
question, just so we’ll have it on the record, you don’t know of any breweries
using the H & K Crowner in America - - - I’m sorry, modification of the H
& K Crowner?
‘A No I don’t.
Q How many breweries, what fraction of
breweries in America use the acoustical tile that you suggest of your own knowledge?
‘A I don’t know.
‘Q How many breweries in America have
enclosed hydraulic power packs to your knowledge, what fraction of them?
‘A I don’t know.
‘Q Now, I’m leaving something out, Dr.
Melling, what is it? Oh, Body Guard, how many breweries in America to your
knowledge are using Body Guard on the conveyors?
‘A I don’t know.
‘Q Do you know how many breweries in
America have shielded, covered the bottom of the seamer in America?
‘A No.
‘Q So that with regard to Pabst, in terms
of these specific modifications, you’re not able to evaluate how widely any of
these are used in America in breweries?
‘A Given time I could find out, yes.
‘Q Right, but I mean here today?
‘A Here today, no.’ (Tr. 229, 230)
‘Q If the - - - let’s be sure the Court
understands what we’re talking about with the tile now. Acoustical tile
normally is very porous and very absorbant, right?
‘A Yes.
‘Q As it needs to be to be a good sound
absorber?
‘A Right.
‘Q So that this material up here, if I put
it in a bucket of paint would soak that paint up rapidly, right?
‘A Yes.
‘Q It would be kind of like the television
commercial that one of the flouride (sic) toothpastes puts on where they take a
piece of chalk and they put it in a dye and very, very quickly you get a
colored ring, right?
‘A Yes.
‘Q Now, the only way that you can put this
tile in the Pabst Brewery is by preventing that kind of thing, right?
‘A Yes.
‘Q Because if material starts sopping up
in there you’d have a terrible sanitation problem, right?
‘A Yes.
‘Q And the FDA would be on your neck,
true?
‘A I believe so.
‘Q So what’s been done here it to coat
this tile with an impervious vinyl film, correct?
‘A Yes.
‘Q How thick is that film?
‘A It’s of the order of thousands of an
inch.
‘Q A couple of mils, maybe?
‘A Umh.
‘Q Two thousandths of an inch thick?
‘A Yes.
‘Q And if you make it a thick film, of
course, then the tile would no longer function as an acoustical absorbant?
‘A Correct.
‘Q So we have here a vinyl film maybe .001
to .002 inches thich (sic)?
‘A Yes.
‘Q Now, I can take my thumb nail and
scrape it across this film and destroy it very easily?
‘A Yes.
‘Q So that if someone comes into the
bottling plant with a stack of beer bottles and happens to rub across the
surface of that film it would damage it, wouldn’t it?
‘A It would indeed, but let’s get this
into perspective. That treatment is quite high up, it deliberately placed above
head height, etcetera so it will be reasonably free from damage.
‘Q And how many times do people bring
ladders, big stacks of cartons in there that would go up above the level of the
tile?
‘A In the case of Pabst, I have no idea.
‘Q But you wouldn’t be surprised it does
occur from time to time?
‘A I wouldn’t be surprised.
‘Q But from what you know of this
material, you wouldn’t disagree with me that it may or may not prove
structurally satisfactory at the Pabst plant? You know it will absorb noise,
but you don’t know whether its’s going to prove that it’s too easily damaged to
stay up, isn’t that true, Dr. Melling?
‘A I would agree with you, yes.’ (Tr.
231–234)
‘Q. No, how long would you expect the
material to last in place?
‘A Well, again I can call on my experience
back in the United Kingdon (sic) where we have used similar materials not only
in breweries, but offshore platforms, which I’m sure you will accept as being a
more rugged environment than a brewery. It’s been very satisfactory and very
little damage.’ (Tr. 314).
On
the basis of the overall record, it must be concluded that the Secretary has
failed to carry his burden of persuasion that the acoustical tile is a feasible
engineering control adaptable to Pabst’s operation.
ULTIMATE CONCLUSIONS OF FACT, LAW, DECISION
AND ORDER
1.
Respondent is engaged in a business affecting commerce within the meaning of
section 3(5) of the Act.
2.
The Commission has jurisdiction over the parties and the proceeding.
3. On
March 12, 1975, the noise levels in Filling Rooms 1, 2, III East and III West
of Respondent’s packaging center exceeded the limits of Table G–16 of 29 C.F.R.
§ 1910.95(b)(1).
4.
The employees exposed to the noise levels in Filling Rooms 1, 2, III East and
III West were protected by personal protective equipment.
5.
Due to the high cost ratio between the engineering controls proposed by the
Secretary and the personal hearing protectors where the controls will not
eliminate the wearing of the protectors, the Secretary has failed to prove that
the costs of the proposed controls are feasible when weighed in the light of
the benefits to the employee.
6.
The Secretary has failed to prove that on March 12, 1975, and January 10, 1978,
that economically feasible engineering controls existed for use in Filling Rooms
I, 2, III East and III West of respondent’s packaging center at Perry, Georgia.
7.
The Secretary has failed to prove that acoustical tile was technologically
feasible for installation on March 10, 1975, and January 10, 1978, in Filling
Rooms I, 2, III East and III West of respondent’s packaging center at Perry,
Georgia.
8.
The respondent was not in violation of section 5(a)(2) of the Act for failure
to conform with 29 C.F.R. § 1910.95(b)(1).
DECISION AND ORDER
Wherefore it is ORDERED:
The
citation issued on April 7, 1975, is vacated and no penalty is assessed.
Dated this 25th day of July, 1978.
JOHN J. LARKIN
Judge
[1] Chairman Rowland
dissents. He would not remand the case for further proceedings. Consistent with
his dissenting opinion in Sun Ship,
he concludes that the requirement in section 1910.95(b)(1) that feasible
administrative or engineering controls be utilized is invalid.
[2] The citation
described the violation of 29 C.F.R. § 1910.95(b)(1) as follows:
Failure
to use feasible engineering or administrative controls to protect employees
from exposure to hazardous noise levels exceeding those specified in 1910.95
Table G–16. Violations occurred in the Filling Room # III—West, Filling Room
No. III, East, No. 2 Filling Room, No. 1 Filling Room, Machine Operators in Can
Packaging Area, Uncaser and Rinser Operator, Label Machine Operators, H & K
Packer Machine Operator, SK Glue Machine Operator, 3 West Uncaser & Rinser
Operator and Bottle Pasteurizer Operator.
Long
Range Abatement: April 9, 1976
An
Abatement Plan shall be submitted by: July 5, 1975’
[3] The standard at
29 C.F.R. § 1910.95(b)(1) provides:
When
employees are subjected to sound exceeding those listed in Table G–16, feasible
administrative or engineering controls shall be utilized. If such controls fail
to reduce sound levels within the levels of Table G–16, personal protective
equipment shall be provided and used to reduce sound levels within the levels
of the table.
TABLE
G–16—PERMISSIBLE NOISE EXPOSURES1 |
|
Duration per
day, hours |
Sound level dBA
slow response |
8 |
90 |
6 |
92 |
4 |
95 |
3 |
97 |
2 |
100 |
1 ½ |
102 |
1 |
105 |
½ |
110 |
[4] Continental Can Co., Inc., 76 OSAHRC
109/A2, 4 BNA OSHC 1541, 76–77 CCH OSHD ¶21,009 (Docket No. 3973, August 24,
1976), pet. for rev. withdrawn; Turner Co., 76 OSAHRC 108/A2, 4 BNA OSHC
1554, 76–77 CCH OSHD ¶21,023 (Docket No. 3635, August 24, 1976) rev. CA 7; Castle & Cooke Foods, A Division of
Castle & Cooke, Inc., 77 OSAHRC 87/A2, 5 BNA OSHC 1435, 77–78 CCH OSHD
¶21,854 (Docket No. 10925, May 19, 1977); Union
Camp Corp., 74 COSHRC 25/C5 (8/31), 1 BNA OSHC 3385, 73–74 CCH OSHD ¶17,576
(Docket No. 3905, May 1, 1974); Great Falls Tribune Co., 77 OSAHRC
86/B7, 5 BNA OSHC 1443, 1977–78 CCH OSHD ¶21,844 (Docket No. 6632, May 19,
1977).
[5] Respondent points
to the requirements of the Food and Drug Administration and Internal Revenue
Service as two of the agencies directly involved in this case in addition to
OSHA. Very little imagination is required to recognize the many other agencies
with voluminous regulations affecting respondent’s operation.
[6] Although the
Secretary refers to administrative controls in his brief, no facts were offered
that administrative controls were applicable or feasible and it has not been
considered as an issue.
[7] The witness recognized he was working under a time limitation and the difficulty dealing with suppliers (Tr. 198, 203). Also, the rising costs of materials due to inflation are a matter of common knowledge.