UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 3035 |
SOUTHERN
COLORADO PRESTRESS COMPANY, |
|
Respondent. |
|
August 24, 1976
DECISION
BEFORE BARNAKO, Chairman; MORAN and CLEARY,
Commissioners.
BARNAKO, Chairman:
Pursuant to 29 U.S.C. Sec. 661(i) we
review whether Judge John A. Carlson properly allowed a serious citation to be
amended to allege a violation of the standard set forth at 29 C.F.R. Sec.
1926.105(a) and (b),[1] and whether he properly
found that the Respondent had violated that standard. For the reasons that
follow we affirm his decision.
Respondent was engaged in the erection of
a three-story prestressed concrete building. During an inspection, one of the
Secretary’s compliance officers observed an employee of the Respondent standing
on a foot-wide perimeter beam at the third floor level. He was using a pry bar
to seat the end of a floor slab. The employee was about 27 feet above the
ground. Neither safety nets, scaffolds, nor platforms were present or used to
protect the employee. The employee was not wearing a safety belt or utilizing
any other device designed to prevent him from falling. As a result, a serious
citation alleging violation of the standard published at 29 C.F.R.
1926.750(b)(1)(ii)[2]
was issued to the Respondent. Respondent contested the citation.
Some six months later, after an informal
pre-hearing conference before the Judge and about two weeks prior to the
evidentiary hearing in the case, the Secretary filed a motion to amend his citation
and complaint to additionally allege violations of the standards at 29 C.F.R.
1926.28(a) and (b) and 105(a) and (b). On the hearing date, the motion was
argued and granted only insofar as the additional 105(a) and (b) charge was
concerned.
After the close of both the Secretary’s
and the employee representative’s case, the Respondent moved for dismissal of
the 105(a) and (b) charge. It argued that the practicality of safety devices
mentioned in the standard as alternatives to safety nets had been established.
Commission precedent[3] clearly called for the
dismissal of the charge in such cases even if none of the safety devices were
actually utilized as was the case here. Accordingly, the Judge granted the
motion.
Respondent then put in its proofs relative
to the 1926.750(b)(1)(ii) charge made in the original citation. The Judge took
the case under advisement at the conclusion of the hearing. However, before he
issued his decision the U.S. Court of Appeals for the Fifth Circuit issued its
decision in Brennan v. Southern Contractors Service, 492 F.2d 498 (5th
Cir. 1974). The court rejected the Commission’s reasoning as to the
construction of 1926.105(a). It held, essentially, that where the standard is
applicable an employee must be protected either by means of a safety net, if
none of the other safety devices are practical, or by means of one of the other
safety devices if the practicality of any such device is established. The
failure to use any device at all creates the violation, said the Court.
Relying on the Court’s holding, the Judge
issued an order vacating his earlier dismissal of the amended 1926.105(a) and
(b) charge and ordered the hearing reopened to permit the Respondent to present
defenses under that standard. Respondent’s counsel declined, stating there was
no need for expanding the evidentiary record. As a result, the reopened hearing
was cancelled.
We hold that the Judge acted properly in
allowing the amendment. The amendment did not change the factual basis for the
charge (failure to use safety nets); it only changed the standard alleged to
have been violated. The motion to amend was made fourteen days prior to the
evidentiary hearing, and Respondent fully participated in the trial of all
issues relevant to the alleged 1926.105(a) and (b) violations. In fact, it is
apparent that the Respondent felt it had developed the issues adequately
because it subsequently declined to present further evidence when given the
opportunity. Under these circumstances, the amendment was clearly not
prejudicial and, therefore, properly allowed.
We also adopt the Judge’s finding that
1926.105(a) and (b) were violated. The employee was standing on a beam that was
27 feet above the ground surface; fall protection was not provided. A steady
wind of about forty miles per hour was blowing at the time. The record is clear
that safety nets could be and were not rigged to protect the employee. Also,
all parties were in substantial agreement that the use of ladders would not be
helpful and that catch platforms should not be considered. Scaffolds too were
impractical.
Finally, evidence was presented as to the
utility of a ‘clothesline’ cable, running between the building’s vertical
columns, to which safety lines could be attached. The evidence also made it
clear, however, that this arrangement could not have been utilized in the areas
of the building above where floor slabs had been placed. That is because the
vertical columns upon which the cable would have to be strung had not yet been
erected.
We, therefore, adopt the Judge’s decision
as to the 1926.105(a) and (b) violations, as to the areas of the building where
the evidence showed it was impractical to use any of the devices set forth in
the standard as alternatives to safety nets. Judge Carlson also properly
concluded that the portion of the citation alleging a violation of
1926.750(b)(1)(ii) be vacated. The standard requires the use of safety nets,
under certain circumstances, in steel erection work. But Respondent here, of
course, was engaged in prestressed concrete construction.
Accordingly, the Judge’s decision is affirmed. So
ORDERED.
BY THE COMMISSION:
WILLIAM S. McLAUGHLIN
EXECUTIVE SECRETARY
DATE: AUG 24, 1976
CLEARY, Commissioner, CONCURRING:
I concur in the result which is consistent
with the cited Commission precedent. My own view, however, is that the
Administrative Law Judge’s reading of section 1926.105(a) in a manner
consistent with the Fifth Circuit’s decision in Southern Contractors Service
is more sound.
MORAN, Commissioner, Dissenting:
I agree with my colleagues’ conclusion
that 29 C.F.R. § 1926.750(b)(1)(ii), the occupational safety standard under
which respondent was originally charged, is not applicable to the work in which
respondent was engaged. I disagree however with their affirmance of a § 1926.105(a)
and (b) violation on the basis that complainant’s motion to amend the citation
was properly allowed. Since that motion was untimely made, the citation should
be vacated.
The alleged violation was detected during
an inspection by complainant of respondent’s worksite on April 19, 1973. Since
complainant did not move to amend the citation until November 1, 1973, more
than six months after the inspection, the motion was barred by the Act’s
statute of limitations (29 U.S.C. § 658(c)), which provides that:
‘No citation may be issued under this
section after the expiration of six months following the occurrence of any
violation.’
Furthermore, this conclusion is not
altered by the provision in Rule 15(c), Federal Rules of Civil Procedure, which
permits an amendment to relate back to the date of an original pleading when
the claim asserted in an amended pleading arose out of the occurrence set forth
therein.
A citation, unlike traditional pleadings,
is a unique creature of statute to which requirements for particularity have
been attached. The Act states in no uncertain terms:
‘Each citation shall be in writing and
shall describe with particularity the nature of the violation, including a
reference to the provision of the chapter, standard, rule, regulation, or order
alleged to have been violated.’ 29 U.S.C. § 658(a) (emphasis added).
Thus, Congress required that the
complainant inform employers of the fundamental aspects of the charge in the
citation itself. It is imperative that this information be supplied in the
citation so that an employer will know, inter alia, how to accomplish abatement
where appropriate and be able to make an informed judgment about the crucial
and irrevocable decision of whether or not to contest.[4]
The legal significance and statutory
requirements for a citation are therefore in sharp contrast to what is commonly
known as ‘notice pleading’ under Rule 8 of the Federal Rules of Civil
Procedure. When pleading under the Federal Rules, a claimant is not required to
set out in detail the facts upon which he bases his claim (Conley v. Gibson,
355 U.S. 41, 47 (1957)), nor to allege the particular law or theory under which
recovery is sought (Misco Leasing, Inc. v. Keller, 490 F.2d 545, 548
(10th Cir. 1974)). Quite obviously, Congress did not intend for the Secretary
of Labor to have such flexibility when it set forth specific requirements for
citations. Therefore, those requirements are not superseded by the Federal
Rules, and my colleagues err in allowing an amendment to the citation in reliance
on those rules.[5]
Because Judge Carlson’s decision is
necessary for a full understanding of the issues presented in this case, it is
attached hereto as Appendix A.
APPENDIX A
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
|
Complainant, |
|
v. |
OSHRC
DOCKET NO. 3035 |
SOUTHERN
COLORADO PRESTRESS COMPANY, |
|
Respondent. |
|
December 6, 1974
DECISION AND ORDER
Appearances:
Ronald G. Whiting, Esq. of Denver,
Colorado, for the Complainant.
Robert G. Good, Esq. and Kenneth R.
Stettner, Esq. of Denver, Colorado, for the Respondent.
Jonathan Wilderman, Esq. of Denver,
Colorado for the Employees’ Representative.
STATEMENT OF THE CASE
John A. Carlson, Judge, OSAHRC.
This is a proceeding under 29 U.S.C.
659(c) for an adjudication under the Occupational Safety and Health Act of 1970
(29 USC 651, et seq, sometimes hereinafter ‘the Act’) of a contest of an
alleged violation of § 654(a)(2). It arose from a citation issued by
complainant to respondent on April 27, 1973 as the result of the inspection of
a workplace in Colorado Springs, Colorado where respondent was engaged in the
erection of a prestressed concrete building. The citation as issued charged a
breach of the standard set forth at 29 CFR 1926.750(b)(1)(ii). The violation
was described in these words:
‘The employer did not provide scaffolding
or safety nets for an employee who was working at the extreme edge of an open
sided, horizontal prestressed concrete and steel beam which was higher than 25
feet above the ground.’
The cited standard reads:
‘(b) Temporary flooring—skeleton steel
construction in tiered buildings.
(1)(ii) On buildings or structures not
adaptable to temporary floors, and where scaffolds are not used, safety nets
shall be installed and maintained whenever the potential fall distance exceeds
two stories or 25 feet. The nets shall be hung with sufficient clearance to
prevent contacts with the surface of structures below.’
Abatement was called for immediately upon
receipt of the citation. By notification issued the same day as the citation a
civil penalty of $600 was proposed. The citation was timely contested by
respondent and Carpenters Union, Local 362, an authorized employees’
representative, thereafter asserted its right of party status through counsel.
The ensuing procedural history of the
proceeding tends to be somewhat complex and will be reviewed here. Following
the granting of an initial motion for continuance filed by complainant (ex.
J–7) a stipulation was filed by all parties requesting an informal pre-hearing
conference on October 24, 1973, immediately prior to hearing on the merits. The
stipulation embraced an understanding that the formal hearing might not proceed
beyond preliminary matters on that date.
Upon representations made at the
conference it appeared likely that the hearing could not proceed to its conclusion
in the two days set aside for it and in view of the pendency of a written
motion by respondent (ex. J–11) for a postponement in order to secure
additional demonstrative evidence, it was agreed that the record would be
opened briefly on October 24th and the evidentiary portion of the hearing
adjourned over until November 19, 1973 at which time respondent would have the
evidence it lacked and the entire matter could be tried to its conclusion (Tr.
5–8). Certain stipulations were entered upon the record by the parties and, at
the request of the judge, counsel for each briefly stated its theory of the
case pursuant to Commission Rule 66(k). The parties were specifically advised
that amendments to the pleadings, if any, were to be submitted expeditiously
(Tr. 18).
Thereafter, on November 1, 1973
complainant filed a motion received on November 5, 1973 to amend his citation
and complaint (ex. J–17) to additionally allege violation of 29 CFR 1926.28(a)
and (b) and 29 CFR 1926.105(a) and (b). Specifically, complainant sought to add
the following language in description of the violation:
Employer did not assure the wearing of
appropriate personal protective equipment in operations where there was an
exposure to hazardous conditions and where Suppart E indicates a need for using
such equipment, such as safety nets, to reduce the hazards to the employees,
including, but not limited to, 29 C.F.R 1926.105 (a) and (b).’
The pertinent standard provides:
§ 1926.105 Safety nets.
(a) Safety nets shall be provided when workplaces
are more than 25 feet above the ground or water surface, or other surfaces
where the use of ladders, scaffolds, catch platforms, temporary floors, safety
lines, or safety belts is impractical.’
(b) Where safety net protection is
required by this part, operations shall not be undertaken until the net is in
place and has been tested.
Respondent, within the time permitted for
response by Commission Rule 37, filed a motion for judgment on the pleadings
received November 13, 1974 seeking dismissal of the entire action on the
grounds, inter alia, that complainant was attempting to issue a new citation
after more than six months from the occurrence of violation, contrary to
section 9(c) of the Act (29 USC § 658(c)).
Owing to his absence on the trial of other
matters this judge had no opportunity to rule upon either motion in advance of
the adjourned hearing date. The motions were taken up at the outset of the
hearing and after extensive arguments by all parties were here (Tr. 24–51),
respondent’s motion was denied and complainant’s amendment was permitted in a
restricted form, eliminating any direct reference to Subpart E and limiting the
additional charge to 29 CFR 1926.105(a) and (b). (Tr. 47–49)
A voluminous record upon the merits was
then made. After the close of both complainant’s and the employee
representative’s case respondent moved, inter alia, for dismissal of that
portion of the charge based upon alleged violation of 29 CFR 1926.105(a) and
(b) on the grounds that the evidence adduced by complainant and the employees’
representative had affirmately established the ‘practicality’ of the use of the
safety devices or means mentioned as alternatives for nets in such standard.
Under the then precedent of Secretary v. Drake-Willamette Joint Ventures,
2 OSAHRC 1216 and Secretary v. Verne Woodrow Company, OSAHRC Docket No.
1607, the complainant was bound to prove the ‘impracticality’ of the non-net
means, whether or not they were in use, before the standard could be held
applicable. In view of the state of the evidence the motion was granted (Tr.
329–332). Respondent that put on its case relative to the question of violation
of the steel erection standards cited, 29 CFR 1926.750.
Following the hearing the three parties
filed extensive briefs and the case was taken under advisement. Prior to
decision, however, on April 12, 1974 the United States Court of Appeals for the
Fifth Circuit issued its decision in Brennan v. Southern Contractors Service
and Occupational Safety and Health Review Commission, 492 F. 2d 498, which
specifically rejected the Commission’s reasoning as to the construction of 29
CFR 1926.105(a). It was held, in essence, that where the standard is applicable
an employee must use either a safety net or one of the other devices described;
and that failure to use any device creates a violation.
In view of the Court’s holding, this Judge
on April 29, 1974 issued an order (ex. J–28) vacating the dismissal of the
amended 29 CFR 1926.105(a) and (b) charge and ordered the hearing reopened on
May 24, 1974 ‘to permit respondent to present evidence relating to any defenses
or otherwise pertinent’ to such standard. Thereafter, all counsel on May 23,
1974 joined in representing through counsel for respondent that no need existed
for the expanding of the evidentiary record as to the alleged violation 29 CFR
1926.105. The hearing was cancelled and the parties were granted leave to file
supplemental briefs (ex. J–29). The respondent and employees’ representative
did so.
ISSUES
The major issues presented for resolution
are:
(1) Whether respondent violated 29 CFR
1926.750(b)(1)(ii) relating to use of safety nets or scaffolding in steel
erection.
(2) Whether complainant could properly
amend to alternatively charge violation of 29 CFR 1926.105(a) and (b).
(3) Whether, if such amendment were
otherwise proper, the provisions of section 9(c) of the Act (29 USC § 658(c))
prohibiting the issuance of citations more than 6 months after the occurrence
of violation, impose a statutory bar to amendment either in the nature of a
statute of limitations, or otherwise.
(4)
Whether complainant satisfied the requirements of section 9(a) of the Act (29
USC § 658(a)) relating to specificity of citations.
(5) Whether, if respondent violated any
standard properly charged, such violation was ‘serious’ within the meaning of
section 17(k) of the Act (29 USC § 666(j)); and what civil penalty, if any,
would then be appropriate.
FINDINGS OF FACT
The following material facts are found to
be sustained upon the entire record:
(1) Respondent, Southern Colorado
Prestress Company, is a division or Prestress Concrete of Colorado, Inc., which
division has principal offices at Colorado Springs, Colorado and a principal
manufacturing or production facility in Pueblo, Colorado, where it engages in
the production and sale of precast and prestressed concrete (Stip.-Joint Ex.
1).
(2)
Respondent itself employs an average of 62–70 persons and during the average
business year ships approximately $100,000 worth of goods to points outside of
Colorado and purchases goods of the same value from sources outside such state.
Respondent’s net worth for the fiscal year ending December 31, 1972 was
$600,000. It ranks approximately third in size among the five similar
competitive producers within the area which includes the State of Colorado.
(Stip.-Joint Ex. 1).
(3) On April 19, 1973 respondent was
engaged in the erection of a three-story prestressed concrete building at a
location in Colorado Springs, Colorado and was on that date inspected by Mr.
Harry C. Hutton, a compliance officer working for complainant (Tr. 54).
(4) The weight bearing structural members
of the building and the flooring (above the ground-floor level) consisted
entirely of prestressed concrete (photos—entire transcript). Prestressed
structural members are made by pouring concrete over stretched steel cables
(Tr. 325). All those involved in the present case were manufactured off site at
a plant in accordance with engineer’s or architect’s specifications and
transported to the building location for erection and assembly (Tr. 547–552,
entire record).
(5) The basic structural components of the
building here in question consisted of vertical prestressed columns, L-shaped
horizontal perimeter beams, and twin-T floor slabs which are designed to rest
upon the ledge or horizontal leg of the L-beams (Tr. 60, 83, photo—compl’s. ex.
3).
(6) All lifting for the erection process
is done by crane and final positioning of the structural components is done by
an erection crew consisting of from 3 to 6 of respondent’s employees (Tr. 143).
The vertical columns are first lifted into place, plumbed, and bolted to
previously laid bases. These uprights have projecting corbels near the various
floor levels. The perimeter beams are positioned upon and secured to the
corbels. Next in the structural sequence the floor slabs are positioned between
the parallel perimeter beams with their double-T legs resting upon the ledge of
the perimeter beam. (Tr. 73, 83, 148–149, 154–160, 206–207; photos—compl’s.
ex’s. 1–3)
(7) There are many broad similarities,
including a falling hazard to connectors or erection crews, between the process
of skeletal steel erection and the prestressed erection process shown to be
used in the instant case (Tr. 134, 245, 255, 326); but the differences in the
materials and technique are far more significant. Dissimilarities include the
facts that concrete pieces for a given strength are many times more bulky than
steel; that concrete members are uniformly smooth and lack the ‘web’
configuration of the conventional steel beam; that prestressed members can be
altered in size only by chipping, rather than cutting as is possible with
steel; that concrete erection cranes routinely work from outside the structure,
whereas steel erection cranes often work from erection floors from within; and
that ‘pure’ prestress work involves use of a permanent original floor slabbing,
whereas steel frame structures commonly involve use of temporary decking (Tr.
343, 450, 590).
(8) At the time of compliance officer
Hutton’s inspection an employee of respondent, one Stanko, an erection crew
member, was standing on a perimeter beam approximately 12 inches wide, at the
third floor level using a pry bar in an attempt to seat the stem or end of a
double-T floor slab, still attached to the crane, which slab had become lodged
(Tr. 10, 56–60, 348, 365, photos—compl’s. ex’s. 2 and 3). He was there for
approximately 5 to 10 minutes (Tr. 59, 189). A short time earlier, two
unidentified employees were similarly positioned on the beam (Tr. 57,
photo—compl’s. ex. 1).
(9) The place where Stanko was standing
was 27 feet above the ground surface (Tr. 60). No safety nets were present, nor
were scaffolds or catch platforms. Stanko was not wearing a safety belt nor
line nor was there any other device, implement, barrier or surface present or
in use which would prevent or interrupt an outward fall to ground surface
should Stanko have slipped or in some manner have been dislodged from his
position (Tr. 61, 65). A steady wind of about 40 miles per hour was blowing at
the times in question (Tr. 58, 124).
(10) Had Stanko fallen the probable
consequence would have been severe physical injury or death (Tr. 66, 72).
(11)
The particular operation in which Stanko was engaged was the seating of a floor
slab between the perimeter beams on either side of the third floor level. These
beams formed a bay between vertical columns which was approximately 32 feet
long and was designed to accommodate four floor slabs (Tr. 314). The beams in
question were on the shorter side of the rectangular building structure (Tr.
560). The slabs were eight feet in width, 35 feet in length and weighed
somewhere between 6,000 to 11,000 pounds (Tr. 74, 189, 350). They were hoisted
by a crane rigged with a ‘spreader’ whose cable ends were attached to the slab
by four lifting rings cast into the upper surface of the slab (Tr. 154–160,
photos-compl’s. ex’s. 2 and 3).
(12)
The installation technique involved bringing the crane-suspended slabs in
‘sideways’, 90° from their ultimate resting position in order to avoid hitting
the vertical columns (Tr. 206, 360). Erection crew members standing on the
previously laid slab guided each new slab in (Tr. 206–207). Crew members then
aided by hand in shoving and swiveling the slab 90°>> so that it could be
brought to rest on the perimeter beams. On the building here in question it was
also necessary to move the end of the slab out over the edge of the perimeter
beam where Stanko was shown standing and then to swing it back in. This maneuver
was done in order to avoid striking an exterior precast wall which had already
been mounted on the other side of the structure. (Tr. 207, 372)
(13) The ordinary position of the men
seating floor slabs is not on the perimeter beams, but on previously laid slabs
at about 3 feet from the outer edge of the structure (Tr. 362, 369). The slabs
are engineered with a planned tolerance of from 1/2 to 1 inch from the inner
edge of the perimeter beam piece (Tr. 400). Often slabs are positioned without
the necessity of going on to the perimeter beam (Tr. 364). With reasonable
frequency, however, the slabs either lodge as shown in the Stanko photos and
with considerable frequency require use of a pry bar to obtain proper tolerance
or spacing (Tr. 154–160, 403, 536–537).
(14) On rare occasions when slabs are
being positioned they may ‘jerk up’ for small distances (Tr. 221–213, 229).
(15) In addition to the lifting rings cast
into the floor slabs hereinbefore referred to, structural beams have similar
rings serving as a means to lift them out of casting beds and also for erection
purposes. They further have metal welding points and vertical columns may have
integral bolts imbedded to facilitate mounting of additional verticals at their
tops (Tr. 348–352, 591).
(16) In order to afford protection from
falls to the exterior of the structure, nets supported by struts, stiff legs,
or outriggers projecting from the vertical columns can be affixed to such
columns by means of clamped-on strap brackets (Tr. 92, 248–249, 254). The nets
themselves may be raised by a crane and fastened by workers on the structure
without significant exposure to hazards of falling (Tr. 249, 285–288, 292).
Such use of nets is a known safety technique (Tr. 254). Nets need not be
installed at each floor level where the distances between upper levels, as in
the instant case, is 12 feet, in order to prevent falls in excess of 25 feet
(Tr. 253, 29 CFR 1926.105(c)(1)). Erection of nets would require approximately
30 minutes for each bay in the building which was the subject of citation (Tr.
292–310).
(17) To lay floor slabs in the area where
Stanko was working—and assuming ideal conditions with no problems such as a
slab’s lodging—would take about 30 minutes (Tr. 545–555). Problems with lodging
or wedging would obviously require more time than the ideal or optimum. The
process could take as long as four hours (Tr. 314). The time involved in the
erection of nets would increase labor costs and would further increase crane
rental expense (Tr. 385).
(18) No temporary floors were used in the
structure in question. No party contended that ladders or catch platforms were
worthwhile safety devices with respect to the laying of floor slabs (Tr.
318–319, entire record).
OPINION
I
The record herein will not support a
conclusion that the activities of respondent toward which the citation was
directed fell within the reach of 29 CFR 1926.750(b)(1)(ii). Complainant and the
employee’s representative urge that the hazards of falling encountered by steel[6] erection crews are
substantially the same as those demonstrated to exist in prestress concrete
erection and that many of the construction techniques used are similar. Where a
worker is positioned at the edge of an elevated surface without the presence of
some means or device to prevent or limit an accidental fall, the hazard and its
potential consequences are essentially the same irrespective of what the
surface is or why the worker is there. But it surely does not then follow that
any random standard designed to prevent falls from the edges of high places
would be applicable for enforcement purposes under the Act.
If it were not sufficiently obvious
without it, the evidence in this case shows that substantial differences inherent
between both the means and materials of construction used in putting up
prestressed concrete buildings, as opposed to skeletal steel buildings. To cite
but a single example, the bulk and weight to strength ratios of steel and
prestressed concrete differ greatly, as do the necessary sizes of structural
members.
In the interpretation of administrative
rules, as well as statutes, the intent of the drafters, if ascertainable, must
govern. Not a phrase or a word anywhere within Subpart R, ‘Steel Erection’,
suggests that such Subpart was meant to pertain to anything but skeletal steel
structures. Where the drafters, as they did, referred only to ‘steel’ and to
the assembly, decking, and other techniques associated with steel erection,
their words used must be accorded their known and ordinary signification. If we
were to expand the literal terms of the cited portion of the standard to
include a material as different from steel as prestressed concrete, we could as
well conclude that Subpart R was intended to apply where workers are exposed to
falls from upper levels of multi-story structures of wood framing or masonry
construction. The language of the standard is clear and will not permit such a
result.[7]
II
Subsequent to the ruling reopening the
case, owing to the Fifth Circuit holding in Southern Contractors Service,
supra, respondent in its supplemental brief made strenuous objection to
this Judge’s determination permitting complainant to amend to allege violation
of 29 CFR 1926.105(a) and (b). The general question of amendment has proved a
nettlesome one, but appears to me to have been substantially laid to rest by
Commission decisions. The Act itself in section 12(g) (29 USC § 661(f))
provides in pertinent part:
Unless the Commission has adopted a
different rule, its proceedings shall be in accordance with the Federal Rules
of Civil Procedure.
There is no contrary Commission rule. The
Commission has in a number of cases made apparent its inclination to follow the
liberal amendment philosophy embodied in Federal Rule 15. As was said in Secretary
v. W. B. Meredith, II, Inc., OSAHRC Docket No. 810 (June 7, 1974),
The law is clear and Commission precedent
well settled that administrative proceedings under the Act are liberally construed
and very easily amended.
See, also, Secretary v. J. L. Maybry
Grading, Inc., OSAHRC Docket No. 285 (April 27, 1973). The Commission has
thus not chosen to be guided by those common law or code principles of
amendment forbidding ‘substantial changes in causes of action’ and generally
freezing litigants into original pleading postures. Such principles were long
ago repudiated with the adoption of the Federal Rules.[8] Without dwelling upon
whether ‘administrative’ pleadings before the Commission are more easily
amended than those before the Federal District Courts, it is clear that they
are as easily amendable. The second portion of Federal Rule 15(a) is
interpreted by a host of cases to entrust to the discretion of the trial judge
a policy which favors a liberal allowance of amendments, including those at the
commencement of, during, and even after trial.[9]4 The keystone to the
exercise of discretion in determining the propriety of amendment is the extent
to which prejudice may be visited upon the opposing party through permitting
the amendment. United States v. Hougham, 364 U.S. 310 (1960); Hanson
v. Hunt Oil Company, 398 F. 2d 578 (8th Circ. 1968). In the present case,
for reasons which will later be detailed, the amendment is permitted since no
substantial prejudice is apparent.
A brief observation will suffice as to
whether the pleading of the additional standard in this case should be regarded
as alternative in character. Under Federal Rule 8(e)(2) pleading in the
alternative is permitted in absolute terms. Under the facts herein respondent
could not be in violation of both 29 CFR 1926.1750 and 29 CFR 1926.105 since
the former, if applicable, is far more specific than the latter and would hence
prevail to the exclusion of the latter. See 29 CFR 1910.5(c)(1); Secretary
v. Sun Shipbuilding and Drydock Company, OSAHRC Docket No. 161 (October 3,
1973); Secretary v. Ohio Urethane Specialists, OSAHRC Docket No. 1807
(August 21, 1973).
III
Respondent maintains that no amendment was
permissible in this case because of section 9(c) of the Act (29 USC § 658(c))
which provides:
No citation may be issued under the
section after the expiration or 6 months following the occurrence of any
violation.
Respondent’s argument[10]5 must be rejected since
any consideration of 9(c) is essentially subsidiary to the question of whether
amendment was properly allowable. Federal Rule 15(c) provides in explicit terms
that any amendment so long as ‘. . . the claim or defense asserted . . . arose
out of the conduct, transaction or occurrence set forth or attempted to be set
forth in the original pleading relates back to the date of the original
pleading . . ..’ The original conduct described in the present case involved an
employee working without fall protection at a height above 25 feet. The
principle of relation back applies with full force where amendments involve a
change to a statute different from that originally alleged so long as both
relate to the same allegedly wrongful conduct. Tiller v. Atlantic Coast Line
R. R., 323 U. S. 574 (1945); Mach v. Pennsylvania R. R., 198 F.
Supp. 471 (1960). What would be true for statutes is also true for regulations.
IV
An associated question is whether section 9(a) of the
Act (29 USC § 658(a)) as it relates to ‘particularity’ of citations
circumscribes in any way the freedom with which amendment should otherwise be
granted under Federal Rule 15. The pertinent portion of 9(a) provides:
‘Each
citation should be in writing and shall describe with particularity the nature
of the violation, including a reference to the provision of the Act, standard,
rule, regulation or order alleged to have been violated.’
An indirect answer is provided by those Commission
decisions previously referred to which have allowed amendments, absent
prejudice, under either Federal Rule 15(a) or (b). These cases alone show that
the ‘particularity’ requirements does not render the charge as originally cast
in the citation immutable; nor do they limit amendment to such trifling matters
as correction of clerical errors. The purpose of the particularity requirement
of 9(a) is well defined in National Realty and Construction Company, Inc. v.
O.S.A.H.R.C., 489 F.2d 1257, 1264 (n.31)(1973) as follows:
Allowing subsequent amendment of a
citation’s charges will not disturb the central function of the citation, which
is to alert a cited employer that it must contest the Secretary’s allegation or
pay the proposed fine. In the typical case, the more inaccurate or unhappily
drafted is a citation, the more likely an employer will be to contest it. But a
citation also serves to order an employer to correct the cited condition or
practice, and a failure to so correct is a punishable violation. 29 U.S.C. §
666(d). Obviously an employer cannot be penalized for failing to correct a
condition which the citation did not fairly characterize. Thus, before
penalizing a failure to correct a cited violation, the Commission must satisfy
itself that the citation defines the ‘uncorrected’ violation with particularity.
29 U.S.C. § 658(a).
Where a citation is contested as to
violation there can obviously be no ‘penalizing’ until litigation ends and a
final order issues. Abatement is tolled until such time under 29 USC § 659(b).
Where the hazardous occurrence, event,
condition or practice believed to constitute a violation has been initially
identified by complainant, the respondent in a contested case cannot be heard to
complain that prejudice is established by the mere fact that complainant is
allowed, through amendment, to charge either in the alternative or by
substitution a standard which may have the most specific applicability to the
hazardous situation described. In a contested case the ‘particularity’
requirement does not per se circumscribe the ability to amend.
V
In its supplemental brief respondent
strenuously urges that the permission given to complainant to amend was
prejudicial. Much of what respondent contends may be summarized with its
characterization of the offering of the amendment as ‘dirty pool’. The analogy
to games is significant as it serves to underscore what this Judge views as the
weakness of respondent’s position. As has been said by the Supreme Court:
The Federal rules reject the approach that
pleading is a game of skill . . . and accept the principle that the purpose of
pleading is to facilitate a proper decision on the merits.[11]
As previously emphasized, the allowance of
permission to amend is entrusted to the discretion of the trial judge and
should be freely granted in the absence of prejudice. In granting the instant
amendment this judge considered the time which elapsed before the motion to
amend was made, but in balancing this against the rather obvious problem faced
by complainant owing to the then prevailing restrictive interpretations of 29
CFR 1926.105, no basis for inferring bad faith could be found. As to the
overriding issue of prejudice, it is first noteworthy that when the motion seeking
amendment was argued at trial prior to the taking of evidence the only
objection ultimately pressed by respondent went to the statute of limitations
issue (respondent’s supplemental brief at page 3, Tr. 25–51). For reasons
earlier specified herein, that objection was not well founded. At that point in
the proceeding, although respondent had had approximately two weeks’ notice of
the written motion to amend and had filed its own motion in response, counsel
made no specific point as to actual prejudice in terms of case preparation or
availability of evidence which would serve as a basis of delay in the taking of
testimony. The subsequent record bears out that factual considerations
concerning virtually every conceivable facet of the use (or non-use) of
alternative safety devices was explored by all parties in exhaustive detail.
When the supplemental hearing was scheduled on the 29 CFR 1926.105 issue,
occasioned by the Fifth Circuit’s rejection of the commission’s prior
construction of that standard, respondent had every opportunity to bring forth
any additional evidence or matters relating to that issue. This the respondent
affirmatively declined to do, choosing to rest upon the previous record. With
regard to that decision respondent merely states in its supplemental brief:
‘Subsequent to the order to reopen, Respondent
concluded that the record and evidence therein was all that could be developed
at trial and that additional evidence was not available.’
Respondent then proceeded to make in its
supplemental brief extensive protestations of prejudice. In the light of the
record these protestations, while colorfully worded, must be regarded as
generalizations lacking in true substance. It would have been simple for
respondent to identify specific ways in which its ability to defend had been or
was impeded; and to explain why such specific problems could not have been
cured by subsequent hearing. As the record stands the case deserves to be
determined upon the merits based upon the applicability of 29 CFR 1926.105.
VI
We now turn to a consideration upon the
merits as to whether respondent violated 29 CFR 1926.105(a) and (b). I must
conclude that the violation was established. Such determination is based solely
upon the hazards encountered in laying the floor slabs as exemplified by the
activities of Mr. Stanko. No attempt can properly be made here to consider what
measures or standards may or may not have been applicable during other phases
of the erection process, though certain of the background evidence did touch
upon such other phases.
It is undisputed, of course, that Stanko
was working on a perimeter beam without fall protection of any sort. Respondent
contends that the nature of the prestressed erection process is such that
exposure of this type cannot be avoided—at least not by means referred to in 29
CFR 1926.105(a) and (b). Certain of these means are ruled out by the evidence.
All parties are in substantial agreement that no temporary floors are involved;
that the use of ladders would not be helpful; and that catch platforms should
not be considered.
As to nets, safety lines and scaffolds,
respondent, through Mr. Cooper the safety and training director of the parent
company, presented much testimony aimed at establishing the use of nets,
scaffolds, or safety lines would (1) in fact increase the hazard to employees
and (2) effectively preclude the employees from accomplishing their work.[12] In addition, there are
the related suggestions that the state of the art, as it were, in the
prestressed industry does not yet permit the use of safety devices until
uprights, beams and flooring are all in; and that use of nets in particular
would be prohibitively expensive in terms of man hours and equipment time.
All of these contentions have been
carefully considered and were ultimately rejected. The preponderance of the
credible evidence satisfies me that the nature of the floor slab positioning
job frequently requires erection crew members to go on the perimeter beams
where they involve themselves in strenuous maneuvers to seat or space floor
slabs. Respondent maintains that for the spacing tolerance operation crew
members could stand on the floor slab, not the beam, to use a pry (Tr. 575).
Curiously, however, there is no indication that this procedure was ever suggested
to any worker or foreman. Even if the men stood as Mr. Cooper suggested, they
would be close enough to the edge to be exposed to a patent danger of falling.
Apropos of nets, respondent maintains that
workers would be exposed to an equal or greater danger in putting up or taking
down such devices than if they continued to work without them. In this regard I
accept the validity of the views of complainant’s and employees’ representative
witnesses, and particularly Mr. Jerome J. Williams, Area Director of OSHA, that
nets could be set up at either end of the building—the place where the evidence
shows that employees were exposed to falling—without significant exposure to
employees, particularly when contrasted to the exposure existing without nets
(Tr. 317).
The record abounds in competing
calculations by witnesses of the parties as to how long it would take to set up
nets compared to the length of time required to raise and position floor slabs.
Ultimately, however, using the figures most favorable to respondent by assuming
that the two levels of bays were floored in the optimum of 30 minutes each—that
is to say that each slab went in without a hitch—the ratio of slab laying time
to net erection time would be 60/60. This would increase cost in terms of crane
rental fees and labor, but would surely not ‘take approximately twice as long
to erect the building’ as Mr. Cooper somewhat rashly suggested at one point
(Tr. 384). He later retreated rather far from this position (Tr. 555–565). Similarly,
respondent’s expert maintained that the use of bands and clamps around the
uprights in order to support nets would pose a danger because of the close
tolerances within which floor slabs must be placed to uprights. The danger he
foresaw was that the presence of bands or clamps would increase the possibility
of an incoming slab striking a column and imperiling the entire structure. He
later retreated from this position, too (Tr. 405, 539, 541). Logic surely dictated
that he do so, since the steel bands would not be at the floor level where it
was agreed that tolerances between floor slabs and perimeter beams were an inch
or less. If positioning slabs to such close fits posed a genuine threat to the
building’s remaining upright, then the whole erection procedure would arguably
present unacceptable perils.
Also, respondent’s Mr. Cooper asserted
that the presence of nets extending out eight feet beyond the edges of the
building would make the job of lifting slabs up to the desired position more
hazardous because of the greater clearance required. He explained that for
reasons of economy and convenience prestressed pieces are usually unloaded
close to the exterior of the structure (Tr. 375). This is undoubtedly true. But
he acknowledged that because of the swing radius of cranes the presence of nets
would only somewhat complicate the task of hoisting slabs or other members (Tr.
402). Logic dictates that the possible danger of hitting a net in lifting a
slab past it would pose no significantly greater hazard to any structural member
already in place then would lifting the same piece from a resting place close
to the base of the building. It must further be noted that in the particular
building with respect to which this contest arose, floor slabs came in from the
‘long’ side of the structure where erection crews did not work in positioning
of slabs. No net would obstruct that side except, perhaps, to a certain extent
at the corners.
It is thus held that the affirmative
evidence of record convincingly demonstrates that nets could effectively be
used in compliance with 29 CFR 1926.105 to reduce the hazards of falls of
erection crew members whose duties take them to the perimeter of the structure
during the laying of floor slabs without substituting comparable hazard to the
employees and without preventing them from performing their work.8[13] Respondent was in
violation of the standard as its requirements were defined by the Court in Southern
Constractors Service, supra.
It should be noted that the force of
respondent’s safety director’s assertions that no safety devices could be used
was diminished by what this Judge regarded as indications of a less than
profound commitment to safety principles—at least where workers at heights were
concerned. Mr. Cooper’s philosophy was at one point expressed as follows:
As I mentioned before, the employees on
the erection crew are very self-conscious about safety. They’re the ones that
get hurt. So they are the ones that are looking out for a situation like this,
and they are the ones who generally do not put themselves in this position.
(Tr. 373–374).
The same convictions were earlier stated,
though less explicitly (Tr. 364). Further, there is an acknowledgement that no
directives had ever been given to employees on the subject of working at
heights laying floor slabs in high winds, the subject having been left up to
‘their discretion’ (Tr. 531–532).
Doubtless there is a measure of validity
to respondent’s position that erecting nets would be time consuming and would
increase total construction costs. One would go unnecessarily far to suggest
that a situation could never arise where cost considerations alone would not
justify noncompliance with a safety or health standard. Within the context of
the present case, however, the principle enunciated in Secretary v. Divesco
Roofing and Insulation Co., OSAHRC Docket No. 345 (August 13, 1973) to the
effect that increased cost factors, even large ones, do not justify disregard
of essentially rational safety requirements, is controlling. Moreover, the
evidence shows that the prestressed structures of respondent are designed with
considerable ingenuity to be erected quickly at the building site. It shows
that prestressed members are fitted at the time of manufacture with cast-in
rings either for the purpose of lifting them out of molds or lifting them into
position for installation or both. Other cast-in fittings include welding
points and can include bolts in the top of vertical columns to facilitate
mounting of higher uprights. Thus, it seems wholly likely that respondent, with
the same resourcefulness used in the general design of its product, could
manage to devise brackets for net fittings which would considerably decrease
the time and cost of net erection over that required for a clamp and strap
method.
The matter of the possible use of safety
belts and lines or external scaffolds should be touched upon briefly. Under the
evidence efficacy of either of these means was less apparent than for nets.
Hence, the conclusion as to nets is regarded as determinative of the issue of
violation. Witnesses for complainant and the employee’s representative
presented essentially persuasive proof as to the utility of a ‘clothesline’
cable, running between vertical columns, to which safety lines could be
attached. Such a scheme would, despite respondent’s many objections appear
workable at the level where Stanko was located, but could not be employed on
the level above where the photographs show floor (or roof) slabs already in
place, since no verticals are present above that point to which a clothesline
could be attached. External, ground-standing scaffolds pose problems because of
the presence of excavations around the building footings to accommodate
plumbers and other mechanical contractors, and because of the height involved (Tr.
385–387).
VII
29 USC § 666(j) provides:
For purposes of this section, a serious
violation shall be deemed to exist in a place of employment if there is a
substantial probability that death or serious physical harm could result from a
condition which exists, or from one or more practices, means, methods,
operations, or processes which have been adopted or are in use, in such place
of employment unless the employer did not, and could not with the exercise of
reasonable diligence, know of the presence of the violation.
The evidence herein amply demonstrates
that should an employee have fallen 27 feet from near the edge of a floor slab
or from a perimeter beam to the outside of the structure the likely
consequences of the fall would have been serious. This was not disputed by
respondent. As to the knowledge requirement contained in the above cited
section it is clear that persons in authority for respondent, including the
individual responsible for the company’s safety program, were aware of exposure
of employees, but took the fundamental position that no feasible means were
available to protect against such exposure. This position having been rejected
and violation found, it follows that the violation must be classified as
serious.
VIII
We next consider the question of penalty.
Jurisdiction to exact civil monetary penalties lies exclusively with the
Commission. In the case of serious violations 29 USC 666(b) makes mandatory the
assessment of a penalty. Section 666(i) requires that consideration be given to
the size of the employer, the gravity of the violation, the employer’s good
faith and its history of previous violations. This provision has been
extensively construed by the Commission in such cases as Secretary v. Nacirema
Operating Co., Inc., 1 OSAHRC 33 (1972) and Secretary v. Baltz Brothers
Packing Co., 2 OSAHRC 384 (1973). The former case indicates that the
‘gravity’ of the violation will ordinarily be accorded the greatest weight. The
latter indicates that the number of employees exposed; the duration of
exposure; the precautions taken against injury; and the degree of probability
of occurrence of an accident should be considered in gauging gravity.
In his testimony herein complainant’s
compliance officer indicated that in proposing an ultimate penalty of $600 he
gave attention to the statutory criteria as interpreted by his superiors and
used specifically formulated guidelines as incorporated in a ‘penalty
assessment worksheet’ (compl’s. ex. 4; Tr. 66). An unadjusted penalty of $1,000
was reduced by a ‘maximum’ allowable 20% for respondent’s prior good history;
and was further reduced a ‘maximum’ 10% for size based upon the fact that 6
employees were at the site. As to ‘good faith’ 10% of a ‘maximum’ of 20%
allowable under complainant’s guidelines was allowed. The compliance officer
indicated that he did not allow a full 20% because no means of protection of
employees were in evidence, but he allowed 10% because of prompt abatement in
that (presumably) employees were ordered out of the danger area. Under the
criteria adopted by the Commission the lack of any means of protection for
employees would appear to go more to gravity than good faith; but as earlier
mentioned the safety program of respondent, with its apparent heavy reliance on
employees’ instinct for self preservation as a substitute for substantive
safety measures or direction is not of a quality commensurate with respondent’s
size and resources. The safety director had direct responsibility for nine
companies, including respondent, operating in several states (Tr. 338, 424)
with a total of 1,400 employees including plant workers and construction
workers (Tr. 512). His staff consisted of a secretary, a nurse and a night
watchman (Tr. 519). The typical contact with erection crews appears to have been
in the form of machine-reproduced copies of various safety handouts from
insurance companies and the newspaper, mailed to foreman (Tr. 426, 511, 514).
The gravity of the violation must be
regarded as moderately high since the evidence shows that erection crews during
floor slab installation were required to be at the edge of the structure with
reasonable frequency with no significant steps being taken to guard against
falls—even to the extent of forbidding their working in 40 mile an hour winds.
In regard to respondent’s ‘size’ the
reasoning used by the compliance officer appears to be at odds with Secretary
v. Jasper Construction, Inc., OSAHRC Docket No. 119 (August 1, 1973)
wherein it was held that an employer’s size should be determined by consideration
of its gross dollar volume and the total number of persons employed (not simply
those at the cited workplace). Respondent is not a small employer.
On balance, however, it is my independent
judgment that consideration of the evidence in the light of § 666(i) warrants
the imposition of a $600 penalty.
CONCLUSIONS OF LAW
Upon the entire record herein it is
concluded:
1. That at all times material hereto
respondent was an ‘employer’ engaged in a ‘business affecting commerce’ within
the meaning of the Act and was subject to the jurisdiction of this Commission.
2. That the evidence fails to establish
that respondent was in violation of 29 CFR 1926.750(b)(1)(ii) relating to use
of safety devices in steel erection since the proofs disclose that respondent
was not engaged in steel erection.
3. That the citation was properly amended
to alternatively charge violation of 29 CFR 1926.105(a) and (b).
4. That the provisions of 29 USC § 658(c)
did not inhibit such amendment since it properly related back to the time of
the original pleading.
5. That complainant satisfied the
requirements of 29 USC § 658(a) relating to specificity of citations.
6. That on April 19, 1973 respondent was
in violation 29 CFR 1926.105(a) and (b).
7. That such violation was ‘serious’
within the meaning of 29 USC § 666(k).
8. That giving due consideration to the
criteria set forth at 29 USC § 666(i), a civil penalty of $600 is reasonable
and appropriate for the above specified serious violation.
ORDER
In accordance with the foregoing it is
hereby ORDERED:
1. That the citation for serious violation
as amended to alternatively charge violation of 29 CFR 1926.105(a) and (b) is
hereby affirmed.
2. That a civil penalty in the sum of $600
is hereby assessed in connection with such violation.
John A. Carlson
Judge, OSAHRC
DEC 6, 1974
[1] The standard reads:
(a) Safety nets shall be provided when
workplaces are more than 25 feet above the ground or water surface, or other
surfaces where the use of ladders, scaffolds, catch platforms, temporary floors,
safety lines, or safety belts is impractical.
(b) Where safety net protection is
required by this part, operations shall not be undertaken until the net is in
place and has been tested.
[2] The standard reads:
(b) Temporary flooring-skeleton steel construction
in tiered buildings (i)(ii). On buildings or structures not adaptable to
temporary floors, and where scaffolds are not used, safety nets shall be
installed and maintained wherever the potential fall distance exceeds two
stories or 25 feet. The nets shall be hung with sufficient clearance to prevent
contacts with the surface of structures below.
[3] Drake-Willamette
Joint Ventures, 2 OSAHRC 1216, BNA 1 OSHC 1181, CCH OSHD para. 15,655 (1973);
Southern Contractors Service, 3 OSAHRC 234, BNA 1 OSHC 1240, CCH OSHD para.
15,801 (1973).
[4] Employers must decide within 15
working days of receipt of the notification of proposed penalties whether or
not to contest the action. 29 U.S.C. § 659(a). If no notice of contest is filed
within that time, employers are normally precluded from obtaining any hearing
on the matter.
[5] For other cases in which I have
stated additional reasons for this position, see my separate opinions in Secretary
v. Warnel Corp., OSAHRC Docket No. 4537, March 31, 1976, and Secretary
v. California Stevedore and Ballast Company, 16 OSAHRC 800, 806 (1975).
[6] [Placement of this footnote not indicated in original text; it appeared in the range of text starting here, up to where footnote 2 is indicated.] This decision in no way purports to deal with the applicability of the steel erection standards to “hybrid” structures utilizing both prestressed members and steel members. The building in question in this case was wholly prestressed. Neither is it necessary to decide whether, as respondent urges, 29 CFR 1926.750(b)(1)(ii) was intended to apply only to inward falls within the structure.
[7]Extensive
testimony (Tr. 440–502) was given by Mr. Robert D. Gidel, former Director of
Program Operations for OSHA as to the genesis and lineage of complainant’s
construction safety and health standards, with the particular emphasis on
Subpart R. It is to be noted that since this Judge’s decision relative to the
inapplicability of Subpart R is based on the literal meaning of the standard,
the testimony of this witness which was addressed primarily to the ‘legislative
history’, as it were, did not play a part in the determination. Resort to such
history is unnecessary where a regulation is free of ambiguity. General
Electric Co. v. Southern Construction Company, 383 F.2d 135 (5th Cir. 1967,
cert. den. 390 U.S. 955). Beyond that, it is highly questionable whether the
unofficial, non-contemporaneous recitals of an official associated with the compilation
of the standards should be entitled to weight. N. C. Freed Co., Inc. v.
Board of Governors of Federal Reserve System, 473 F.2d 1210, 1217 (2d Cir.
1973); National School of Aeronautics v. United States 142 F. Supp. 933
(1956).
[8] Moore’s Federal Practice,
¶15.08[2].
[9] See Wright & Miller, Federal
Practice and Procedure: Civil §§ 1484, 1488.
[10] Respondent insists that 9(c) is a
statute of limitations. In my view it is more than a mere bar to the bringing
of an action, raisable as an affirmative defense. It is instead a specific
statutory termination of the existence of the right to commence an enforcement
action. See Goodwin v. Townsend, 197 F.2d 970 (3rd Cir. 1952).
[11] United States v.
Hougham, supra,
at 317, citing Conley v. Gibson, 355 U. S. 41.
[12] The validity of such defenses has been recognized by the Commission. See, respectively, Secretary v. Industrial Steel Erectors, Inc., OSAHRC Docket No. 703 (January 10, 1974); Secretary v. Consolidated Engineering Company, Inc., & Otis Elevator Company, OSAHRC Docket Nos. 394 and 471 (October 17, 1944).
[13] In both Industrial Steel Erectors, supra, and Consolidated Engineering Company, supra, the defenses of ‘greater hazard’ or ‘work impossibility’ are affirmative in character with the burden of proof resting upon respondent. No consideration of the question of burden of proof was necessary herein. The preponderant weight of the evidence from all sources compels the conclusion that nets were an appropriate means of fall protection.