United
States of America
OCCUPATIONAL SAFETY AND HEALTH
REVIEW COMMISSION
1120
20th Street, N.W., Ninth Floor
Washington,
DC 20036-3457
SECRETARY OF LABOR, |
|
Complainant, |
|
v. |
OSHRC Docket Nos. 13-0644 & 13-0791 |
WYNNEWOOD REFINING CO., LLC, and its successors, |
|
Respondent. |
|
ON BRIEFS:
Ronald
J. Gottlieb, Attorney; Charles F. James, Counsel for Appellate Litigation; Ann
Rosenthal, Associate Solicitor of Labor for Occupational Safety and Health; M.
Patricia Smith, Solicitor of Labor; U.S. Department of Labor, Washington, DC
For the Complainant
Nicole
A. Smith, Esq.; Benjamin E. Stockman, Esq.; Venable LLP, Washington, DC, and
New York, NY
For the Respondent
Richard
Moskowitz, General Counsel, American Fuel & Petrochemical Manufacturers;
Peter Tolsdorf, Senior Counsel, American Petroleum Institute; Eric J. Conn,
Esq.; Conn Maciel Carey PLLC, Washington, DC
For
Amici Curiae American Fuel & Petrochemical Manufacturers and American
Petroleum Institute
DECISION
Before: MacDOUGALL,
Chairman; ATTWOOD and SULLIVAN, Commissioners.
BY THE COMMISSION:
The
Occupational Safety and Health Administration cited Wynnewood Refining Company,
LLC, for—as relevant here—twelve violations of various provisions of OSHA’s Process
Safety Management standard, 29 C.F.R. § 1910.119. Eleven of these violations involve the “Wickes”
steam boiler at the company’s oil refinery in Wynnewood, Oklahoma, and four of
those violations are characterized as repeat. The twelfth citation item alleges an additional repeat PSM violation
related to the company’s alleged failure to develop and implement safe work
practices for contractors. Following
a hearing, Administrative Law Judge Brian A. Duncan affirmed all twelve violations
as serious and assessed a total penalty of $58,000 for them.
Both parties petitioned
for review of the judge’s decision. Wynnewood
LLC contends that the Wickes boiler-related items should be vacated because the
PSM standard does not apply to the boiler.[1] The Secretary contends that the judge erred
in rejecting his repeat characterization of five of the PSM items because, although the predicate violations were
committed by a different corporate entity when it was owned by a different
parent corporation, substantial continuity existed between Wynnewood LLC and
the prior entity. For
the following reasons, we affirm the judge’s decision.[2]
BACKGROUND
Wynnewood
LLC’s refinery in Oklahoma processes crude oil and on a daily basis produces 70,000 barrels of gasoline, propane, propylene, butane, fuel
oils, and solvents. Prior to December
2011, the refinery was owned and operated by Wynnewood Refining Company, a
subsidiary of Gary-Williams Energy Corporation.
On December 15, 2011, CVR Energy, Inc., acquired all the stock of
Gary-Williams Energy Corporation and its subsidiaries, including Wynnewood
Inc., which then registered with the State of Delaware as a limited liability
corporation—Wynnewood LLC, the respondent here—on February 21, 2012.[3]
The Wickes boiler, located about 100
feet from the reactor column in the refinery’s Fluid Catalytic Cracking Unit
(FCCU), is one of four boilers in the refinery providing steam to the 225‑pound
“steam header,” which then routes steam for use in various processes throughout
the facility. In hearing testimony, the
Wickes boiler was described as “a major contributor into that steam header,”
and “by far the workhorse of the plant for steam,” as it provides steam for,
among other things, powering turbines and pumps, putting out small fires, “stripping”
crude oil of certain substances during the refining process, and clearing the “FCCU
riser” of hydrocarbons during emergency shutdowns.
The Wickes boiler is powered by two types of fuel—natural
gas, which the refinery purchases, and refinery fuel gas (RFG), which is made
from non-condensable, unsaleable, and flammable gas byproducts of the refining
process. Natural gas and RFG are mixed
in a fuel gas drum and the resulting fuel is then routed through a
4.1-mile-long pipeline network, including through a trunk line to the Wickes
boiler. During times when no RFG is
produced—such as when the refinery is shut down for maintenance, a period known
as a “turnaround”—only natural gas is provided to the drum. On September 28, 2012, the refinery was in
the middle of a turnaround, so the Wickes boiler was to be started up using
only natural gas. During this start-up, however,
too much natural gas was allowed into the boiler’s “firebox”—where fuel is
burned to produce a flame—and shortly thereafter the boiler exploded, immediately
killing one Wynnewood LLC employee and critically injuring another, who died
twenty-eight days later.
The day after the explosion, OSHA began
an inspection of the refinery, which resulted in the issuance of three
citations to Wynnewood LLC (Docket No. 13-0791), with all items relating to the
Wickes boiler—twelve of these citation items allege violations of the PSM
standard; five of which are alleged as repeat violations.
One month after the start of this
first inspection, OSHA initiated a second inspection of the refinery, which
resulted in the issuance of three more citations to Wynnewood LLC (Docket No.
13-0644), addressing various conditions in the refinery; one of the citation
items is alleged as a repeat violation of the PSM standard.
Under Docket No. 13-0791, as relevant here, the judge affirmed eleven of
the twelve citation items alleging violations of the PSM standard; four of
which he characterized as serious instead of repeat.[4] Under Docket No. 13-0644, as relevant here, the
judge affirmed the one citation item alleging a violation of the PSM standard but
characterized it as serious instead of repeat.[5] In rejecting the Secretary’s repeat
characterization of these affirmed items, the judge concluded that, because the
predicate PSM violations were committed by Wynnewood Inc. while it was a
subsidiary of Gary-Williams Energy Corporation, those violations could not be
attributed to Wynnewood LLC.
For the following reasons, we agree with the judge that the
PSM standard applies to the Wickes boiler and therefore affirm the eleven items
at issue on review that allege PSM violations relating to the boiler. We also agree that a repeat characterization
is unwarranted for the five items on review.
DISCUSSION
I. Applicability of the PSM Standard
The PSM standard “applies to . . . [a] process which involves a Category 1 flammable gas . . . or
a flammable liquid with a flashpoint below 100 °F . . . on site in one location, in a quantity of 10,000 pounds . . . or
more.” 29 C.F.R. § 1910.119(a)(1)(ii). “Process” is defined as “any activity
involving a highly hazardous chemical including any use, storage,
manufacturing, handling, or the on-site movement of such chemicals, or
combination of these activities,” and “[f]or purposes of this definition, any
group of vessels which are interconnected and separate vessels which are
located such that a highly hazardous chemical could be involved in a potential
release shall be considered a single process.”
29 C.F.R. § 1910.119(b). As such,
the definition of “process” has two prongs—a vessel may be part of a covered
“process” via interconnection or location.
The Secretary asserts that the Wickes boiler fits both
prongs, alleging that the FCCU is a covered process and the boiler is both interconnected
with it and located such that a catastrophic event could affect it. The judge agreed, finding that the Wickes
boiler is interconnected with the Alkylation Unit and FCCU through the RFG
pipeline, as well as interconnected with virtually all the refinery’s processes
through the steam header, and concluding that the
boiler was centrally located in the FCCU such that an event like the explosion
in this case could result in a catastrophic release of a highly hazardous
chemical (HHC). The judge also rejected
Wynnewood LLC’s contention that the Wickes boiler qualifies for the PSM
standard’s workplace fuel exemption, which provides that “[h]ydrocarbon fuels used solely for workplace consumption as a
fuel” are exempted from coverage “if such fuels are not a part of a process
containing another [HHC] covered by this standard.” 29 C.F.R. § 1910.119(a)(1)(ii)(A).
Wynnewood LLC asserts that the judge erred in several ways,
arguing that: (1) a mere physical connection between vessels is insufficient to
make them a single process absent evidence that the cited vessel could cause a
catastrophic HHC release—a showing the company contends the Secretary failed to
make; (2) in any event, the Wickes boiler was not in fact “interconnected” to a
PSM-covered process because neither the RFG pipeline nor the steam header are
sufficient connections under the standard; (3) the Wickes boiler was not
situated such that it could cause a catastrophic release from nearby covered
processes; and (4) the Wickes boiler’s use of RFG falls within the workplace
fuel exemption because the only HHC or flammable gas that contacts the boiler
is a small quantity of refinery and/or natural gas, all of which the boiler
uses only as a fuel. We begin with the
company’s first contention, which raises an interpretation issue.
“Interconnected”
Vessels and Proof of Risk of Catastrophic Release
Wynnewood LLC contends that interconnected vessels do not
form a single “process” unless each vessel is shown to pose a risk of
catastrophic HHC release. The company
argues that because there are no commas on either side of the following phrase
in the standard’s definition of “process”—“and separate vessels which are
located such that a highly hazardous chemical could be involved in a potential
release”—the “such that” phrase in the definition modifies “interconnected” as well as “located.” 29 C.F.R. § 1910.119(b) (defining “process”
as “any group of vessels which are interconnected and separate vessels which
are located such that a highly hazardous chemical could be involved in a
potential release shall be considered a single process”). The company therefore asserts that to prove interconnection,
the Secretary must show that the cited vessel is connected to a covered process
and could cause or contribute to a
catastrophic release of HHCs.
Even without the commas, the definition’s
repeated use of the word “which” sets up a parallel structure that on its face
indicates two separate and complete conditions.
This meaning is reinforced by the fact that while the phrase “which are
located” cannot stand alone as a complete concept—to be meaningful, it needs
the modifying phrase “such that a highly hazardous chemical could be involved
in a potential release”—the phrase “which are interconnected” can stand alone. Accordingly, we find that the plain meaning of
the definition is that a single process consists of either “any group of
vessels which are interconnected” or “separate vessels which are located such
that a highly hazardous chemical could be involved in a potential release.”[6] See,
e.g., Cent. Fla. Equip. Rentals, Inc., 25 BNA OSHC 2147, 2150 (No. 08-1656,
2016) (“Most OSHA standards regulate a particular condition and, therefore,
presume the existence of a hazard.”); Oberdorfer
Indus., Inc., 20 BNA OSHC 1321, 1330 (No. 97-0469, 2003) (consolidated) (29
C.F.R. § 1910.219(c)(2)(i) “presumes a hazard” where “horizontal shafting
[is] no more than 7 feet . . . from the floor,” so “the
Secretary is not obligated to show that the conditions in question are
themselves hazardous in order to prove a violation”).[7]
Interconnection
of Vessels
We turn next
to whether the Secretary has shown that the Wickes boiler is interconnected
with other vessels such that it is part of a PSM-covered process. It is undisputed that the FCCU and Alkylation
Unit are PSM-covered processes by virtue of the flammables contained in each
and as the judge found, the Wickes boiler is physically connected to both units
through the RFG pipeline and to virtually all the refinery’s processes via the
steam header. Indeed, Wynnewood LLC acknowledges
that the Wickes boiler was, at least indirectly, physically connected to the
FCCU and Alkylation Unit. Nevertheless, the
company argues that interconnection may be established only where multiple vessels are involved, and that the
Secretary has failed to show that the boiler’s firebox is a “vessel” covered by
the standard because it does not contain an amount of HHCs that exceeds the
threshold quantity specified in § 1910.119(a)(1)(ii).
Wynnewood LLC is correct that there
is no evidence in the record that RFG—the only hydrocarbon handled by the
Wickes boiler—exists anywhere in the refinery in an amount that exceeds
the PSM standard’s threshold quantity, but the company’s focus on the boiler’s
firebox and fuel is misplaced. The PSM
standard does not require that an interconnected vessel itself contain the
threshold quantity of HHCs—indeed, it does not even require that each vessel in
an interconnected group contain HHCs at all.
See 29 C.F.R. § 1910.119(b)
(defining “process” as “any activity involving a highly hazardous
chemical”). Thus, because the record
shows that the Wickes boiler held water, it constitutes a “vessel,” and the
status of the firebox has no bearing on the issue here. See
Webster’s Third New International
Dictionary of the English Language, Unabridged 2547 (3d ed. 1986)
(defining “vessel” as “a hollow and usu[ally] cylindrical or concave utensil . . . for holding something and
esp[ecially] a liquid”); United States v.
Sherburne, 249 F.3d 1121, 1126 (9th Cir. 2001) (“turn[ing] to the
dictionary for guidance” in absence of statutory definition).
Wynnewood LLC also argues that the two, indirect connections
between the Wickes boiler and the FCCU and Alkylation Unit—namely, the RFG and
steam systems—are insufficient to constitute interconnection under the standard
because neither played a direct role in these processes. The judge, citing the Commission’s decision
in Delek Refining, Ltd., 25 BNA OSHC
1365 (No. 08-1386, 2015), aff’d in relevant part, 845 F.3d 170
(5th Cir. 2016), rejected this argument, concluding that the link between the
Wickes boiler and the FCCU is even more concrete than the equipment found to be
part of the single process in Delek. The company contends that the judge’s
reliance on Delek was error, and we
agree—Delek is inapposite to the
“interconnection” issue here. In Delek, the issue was whether the
positive pressurization unit, which kept hazardous vapors from entering the
FCCU control room at Delek’s refinery, was “process equipment” under §
1910.119(j)(4)(i). Delek Refining, 25 BNA OSHC at 1370. Thus, while Delek did address the PSM standard’s “process” definition, it
focused on the first sentence and whether the positive pressurization unit was
involved in the “manufacturing, handling [and] on-site movement” of HHCs, id. at 1371, not whether vessels were
interconnected pursuant to the definition’s second sentence.
We find, however, that the indirect,
physical link between the Wickes boiler and the FCCU and Alkylation unit is sufficient for PSM coverage.
“Interconnect,” which the standard does not define, commonly means “to
connect mutually or with one another,” and “interconnection” means “connection
between two or more.” Webster’s Third New International Dictionary
of the English Language, Unabridged 1177 (3d ed. 1986); see Crawford v. Metro. Gov’t of Nashville
& Davidson Cty., 555 U.S. 271, 276 (2009) (undefined term “carries its
ordinary meaning”). These definitions
contemplate the linking together of multiple objects, which necessarily
includes an indirect link between some of them.
This is in contrast with the word “connect,” a
term the standard does not use, which describes a direct link—“to join, fasten,
or link together usu[ally] by means of something intervening,” for example, “a
bus line connects the two towns,” or “connect a garden hose to the
faucet.” Webster’s Third New International Dictionary of the English
Language, Unabridged 480 (3d ed. 1986). In short, the PSM standard’s use of the term
“interconnected” makes it irrelevant whether the Wickes boiler is directly
connected to, or involved with, the processes of the FCCU and Alkylation Unit. The main point is that RFG generated by the
FCCU and the Alkylation Unit is piped to the Wickes boiler, and steam from the
boiler is piped to the FCCU and Alkylation Unit; the Wickes boiler is therefore
one of a “group of vessels which are interconnected,” 29 C.F.R. § 1910.119(b),
and therefore covered as part of a “process” by the PSM standard. 29 C.F.R. § 1910.119(a)(1)(ii).
Location
of Wickes Boiler
Alternatively, the Secretary asserts that the Wickes boiler
was covered by the PSM standard because it was “located such that a highly
hazardous chemical could be involved in a potential release.” 29 C.F.R. § 1910.119(b). Before the judge, Wynnewood LLC argued that
the Secretary failed to make this showing because the Wickes boiler’s 100-foot
distance from the FCCU reactor column, the closest part of the process
containing HHCs, has not been shown to have been close enough to cause a catastrophic
release of HHCs. In this regard the
company asserted that there was no damage to any process equipment as a result
of the explosion in this case, the nearby exhaust line carrying combustion
byproducts does not contain any HHCs, and the testimony of the compliance
officer and the Secretary’s expert is speculative regarding the explosion
hazard. The judge rejected the company’s
arguments as too heavily based on the particular explosion here and found that
the boiler’s central location in the FCCU, coupled with the fact that debris
from the boiler (such as a ladder, a platform, and pieces of the boiler’s
brick-like lining) was propelled across the street toward an operator shelter,
was sufficient to establish that the boiler’s location made it such that an HHC
could be involved in a potential release.
On review, the company contends that the judge’s ruling is based on
speculation. We disagree.
Wynnewood LLC asserts that to establish the location prong
of the definition, the Secretary must prove that the potential for a
catastrophic release was probable, but this is not the test. The standard itself states that vessels must
be “located such that a highly hazardous chemical could be involved in a potential release.” 29 C.F.R. § 1910.119(b). The record here shows that the Wickes boiler
was located centrally in the FCCU and confirms that the explosion in this case was
strong enough to propel a ladder and platform forty feet into an operator
shelter.[8] Also, the Secretary’s expert testified that
the explosion could have been worse—“if they would have been producing steam
[at that time], and if that boiler would have been under pressure, not only
would you have had the firebox explode, as we saw, with shrapnel and walkways
and all sorts of stuff flying all over the place, but you would have had a
steam boiler explosion.” As such, the
explosion here was not the worst-case scenario, and in the expert’s opinion,
“an incident here at the boiler could definitely cause damage to other
equipment, whether it be pipes or vessels in that facility.” Wynnewood LLC points out that the Secretary did
not proffer evidence concerning the construction specifications of the FCCU,
but the FCCU’s structural integrity is of no relevance, especially in light of testimony from Wynnewood’s own expert that he
was “surprised maybe that the [fuel] lines [to the Wickes boiler] weren’t on
fire” after the explosion. This acknowledgement
that a fire hazard was present, along with the evidence discussed above, is sufficient to show that the Wickes boiler was “located such
that a highly hazardous chemical could be involved in a potential release.” 29 C.F.R. § 1910.119(b).
Workplace
Fuel Consumption Exemption
The final issue with
regard to applicability of the PSM standard to the Wickes boiler
concerns Wynnewood LLC’s contention that the boiler qualifies for the
standard’s workplace fuel consumption exemption. The PSM standard does not apply to
“[h]ydrocarbon fuels used solely for workplace consumption as a fuel (e.g.,
propane used for comfort heating, gasoline for vehicle refueling), if such
fuels are not a part of a process containing another highly hazardous chemical
covered by this standard.” 29 C.F.R. §
1910.119(a)(1)(ii)(A). The company argues
that the Wickes boiler qualifies for this exemption because the only
HHC that contacts the boiler is RFG produced at the refinery, which is
used solely for fueling purposes. In
rejecting this argument, the judge concluded that the exemption has a very
limited scope and was not intended to cover process-related applications such
as the Wickes boiler.[9] We agree.
The plain language of the exemption makes clear that fuels
used for non-process-related uses—like “comfort heating” and for “vehicle[s]”—are
not covered by the PSM standard. 29
C.F.R. § 1910.119(a)(1)(ii)(A). Put
another way, the Secretary cannot base PSM coverage on the mere presence of
such a fuel in a workplace. Here, however,
the PSM standard’s applicability is not based on either the RFG or the natural
gas that is used to fuel the boiler; rather, it is based on the boiler itself,
and its interconnection and location, as discussed above. Therefore, whether the RFG and natural gas
used to fire the boiler could independently serve as a basis for applying the
PSM standard—that is, whether this fuel is “used solely for workplace
consumption”—is irrelevant in this case.[10] For these reasons, we conclude that the PSM
standard applies to the Wickes boiler.
II. Repeat Characterization
The Secretary contends that the
judge erred in rejecting his repeat characterization of five items—Docket No.
13-0791, Citation 2, Items 2 through 5, and Docket No. 13-0644, Citation 2,
Item 1. The citations
for the prior violations underlying these repeat items were issued to Wynnewood
Inc.; they became final orders of the Commission in the fall of 2008, when the refinery
was owned and operated by Wynnewood Inc., then a subsidiary of Gary-Williams
Energy Corporation. The judge rejected
the Secretary’s repeat characterization based on his finding that “holding
[Wynnewood LLC], a separate and distinct . . . entity,
responsible for what [Wynnewood Inc.] did in the past . . . expands
repeat liability beyond what the Commission envisioned in” Sharon & Walter Construction, Inc., 23 BNA OSHC 1286 (No.
00-1402, 2010). We agree.[11]
In Sharon & Walter,
the Commission concluded that “in appropriate circumstances, [the Secretary may
apply] a ‘repeat’ characterization to cases where the cited employer has
altered its legal identity from that of the predecessor employer whose citation
history forms the basis of that characterization.” Id.
at 1293. In “consider[ing] . . . the circumstances under which a
predecessor’s citation history may be attributed to a cited successor
employer,” the “focus is on whether there is ‘substantial continuity’ between
the two enterprises,” which depends on factors falling into three categories:
(1) the nature of the business, because “continuity in the type of business,
products/services offered and customers served indicates that there has been no
substantive change in the enterprise”; (2) the jobs and working conditions,
because these have a “close correlation with particular safety and health
hazards”; and (3) continuity of the personnel who specifically control
decisions related to safety and health,” because “the decisions of such
personnel relate directly to the extent to which the employer complies with the
statute’s requirements.” Id. at 1294-95.
As the judge found, the issue here
comes down to the third category given that the refinery’s business, products,
jobs, and working conditions were the same under both entities. Indeed, the Commission recognized in Sharon & Walter the particular
importance of continuity of personnel, stating that the same “control over
decision-making in both companies . . . weighs
heavily in favor of attributing . . . [the
prior employer’s] citation history to [the cited employer].”[12] Id.
at 1295-96. Here, several of the
day-to-day managers were in the same positions under Wynnewood Inc. and
Wynnewood LLC, including the refinery’s vice president of refining, safety
manager, PSM manager, operations manager, and two supervisors in Zone 2, where
the Wickes boiler is located. The record
also shows, however, that high-level executives of Wynnewood LLC’s current parent
company, CVR Energy—such as the executive vice president for operations and the
vice president of environmental health and safety—took an increased role in
day-to-day operations at the refinery, and they were present frequently to
oversee the transition from Wynnewood Inc. under Gary-Williams Energy
Corporation to Wynnewood LLC under CVR Energy.
This new management focused on improving safety, health, and the proper
implementation of PSM at the refinery. Moreover,
as the judge noted: the number of refinery safety personnel was nearly doubled,
including four new assistant operations supervisors responsible for
occupational safety compliance; $130 million of equipment upgrades were made;
more formalized training programs were developed and implemented; and there was
a renewed emphasis on management of change procedures. These leadership changes resulted in a safety
culture shift at the refinery.[13]
In light of the foregoing, we find these are
not the appropriate circumstances to affirm a repeat characterization. This is not a case where “the cited employer
has altered its legal identity from that of the predecessor employer . . . [simply
to] avoid a repeat characterization.” Id. at 1293. On the contrary, the record does not support
the Secretary’s contention that there was sufficient continuity
in the safety personnel at the cited entity such that “there was a Commission final
order against the same employer for a
substantially similar violation.”[14]
Hackensack
Steel Corp., 20 BNA OSHC 1387, 1392 (No. 97-0755, 2003) (emphasis added). Accordingly, we find that a repeat
characterization is not warranted here.[15]
CONCLUSION
For all the foregoing
reasons, we affirm, under
Docket No. 13-0791, Citation 1, Items 1, 2a, 2b, 2c, 3a, 3b, and 4, and
Citation 2, Items 2, 3, 4, and 5, as serious violations. We also affirm, under Docket No. 13-0644,
Citation 2, Item 1, as a serious violation.
Given
that Wynnewood LLC does not contest the penalty amounts on review, we assess
the penalties for these items that the judge assessed—for Docket No. 13-0791,
Citation 1, Item 1, a penalty of $7,000; for Items 2a, 2b, and 2c, a grouped
penalty of $7,000; for Items 3a and 3b, a grouped penalty of $7,000; for Item
4, a penalty of $7,000; for Citation 2, Items 2, 3, 4, and 5, a penalty of
$7,000 each; and for Docket No. 13-0644, Citation 2, Item 1, a penalty of $2,000—for
a total penalty of $58,000. See KS Energy Servs., Inc., 22 BNA OSHC
1261, 1268 n.11 (No. 06-1416, 2008) (assessing proposed penalty where penalty
not in dispute).
SO ORDERED.
/s/
Heather
L. MacDougall
Chairman
/s/
Dated: March 28, 2019 James
J. Sullivan, Jr.
Commissioner
ATTWOOD, Commissioner, concurring and dissenting in part:
I agree with my colleagues’
conclusions in Part I of their opinion, in which they find that the PSM
standard applies to the Wickes boiler under both “interconnect[ion]” and “locat[ion],” 29 C.F.R. § 1910.119(b), and that Wynnewood
LLC has failed to show that the standard’s workplace fuel consumption exemption
applies, see 29 C.F.R. §
1910.119(a)(1)(ii)(A). Accordingly, I
join my colleagues in affirming the Wickes boiler-related items at issue. I do not, however, join Part II of their
opinion, which rejects the Secretary’s repeat characterization of five of the
violations we affirm.
Longstanding Commission precedent holds that a “violation is repeated
under section 17(a) of the [Occupational Safety and Health] Act if, at the time
of the alleged repeated violation, there was a Commission final order against
the same employer for a substantially similar violation.” Potlatch
Corp., 7 BNA OSHC 1061, 1063 (No. 16183, 1979). For the reasons that
follow, I would conclude that under this precedent: (1) Wynnewood Inc. (the
recipient of the prior citations) and Wynnewood LLC (the respondent here) are
the same employer for purposes of a repeat characterization; and (2) the prior
and instant violations are substantially similar and therefore must be
characterized as repeat. Accordingly, I
would affirm Docket No. 13-0791, Citation 2, Items 2 through 5, and Docket No.
13-0644, Citation 2, Item 1 as repeat violations.
I. Substantial
Continuity of Corporate Entities
The Commission held in Sharon
& Walter Construction, Inc., 23 BNA OSHC 1286 (No. 00-1402, 2010), that
a repeat characterization may be appropriate “where the cited employer has
altered its legal identity from that of the predecessor employer whose citation
history forms the basis of that characterization.” Id.
at 1293. In deciding whether “a
predecessor’s citation history may be attributed to a cited successor
employer,” the Commission must determine “whether there is ‘substantial
continuity’ between the two enterprises,” which requires the consideration of
“factors that essentially fall into three categories”—(1) the nature of the
business; (2) the jobs and working conditions; and (3) the continuity of
personnel who “specifically control decisions related to safety and
health.” Id. at 1294-95. It is
undisputed that the facts relevant to the first two categories of factors weigh
in favor of substantial continuity of the two entities. My colleagues’ analysis of the
third category of factors, however, is problematic.
The majority decision concedes that “several of the day-to-day
managers were in the same positions under Wynnewood Inc. and Wynnewood
LLC.” Nevertheless, my colleagues
decline to find substantial continuity between these entities because two
executives of Wynnewood LLC’s new parent company— CVR Energy, Inc.—“took an increased role in day-to-day operations at the
refinery.” This focus on high-level
executives (here, CVR Energy’s executive vice president for operations and vice
president of environmental health and safety) of a different corporate entity than the cited employer is
misplaced. As noted, the issue is
whether there is substantial continuity of safety and health personnel “between the two enterprises”—the entity
that was issued the prior citation and the entity that was issued the instant one. See id.
at 1294 (emphasis added). The
executives for CVR Energy would only be relevant to this inquiry if the record
established that the entity cited here (Wynnewood LLC)
and CVR Energy were a “single employer,” an issue that was neither alleged by
either party nor litigated. See N.L.R.B.
v. Greater Kansas City Roofing, 2 F.3d 1047, 1051 (10th Cir. 1993) (“[T]he
corporate form will be disregarded” only “[i]n
extreme circumstances,” and “the corporate veil should be pierced only
reluctantly and cautiously.”); see also
Advance Specialty Co., 3 BNA OSHC
2072, 2076 (No. 2279, 1976) (“[W]hen . . . two companies
share a common worksite such that the employees of both have access to the same
hazardous conditions, have interrelated and integrated operations, and share a
common president, management, supervision or ownership, the purposes of the
[OSH] Act are best effectuated by the two being treated as one.”); C.T. Taylor Co., 20 BNA OSHC 1083 (No.
94-3241, 2003) (consolidated) (prohibiting Secretary from citing employers
separately for willful violations where both companies were owned by the same
individual, and one company was “fully in charge of [the other’s] operations”
and “assumed the responsibility for employee safety on the [combined]
job[site]”). The issue in this case,
therefore, turns on the extent of the continuity of personnel between Wynnewood
LLC and Wynnewood Inc.
The record shows that most of Wynnewood LLC’s supervisors, PSM
managers, and safety officials responsible for OSH Act compliance held the same
or similar positions for Wynnewood Inc.:
§
Wayne Leiker was
Vice President of Refining for both Wynnewood Inc. and Wynnewood LLC.
§
Dan Looney was the refinery’s safety manager
for both Wynnewood Inc. and Wynnewood LLC.
§
Dick Jackson was the refinery’s process safety
manager for both Wynnewood Inc. and Wynnewood LLC.
§
Darin Rains was operations manager for both
Wynnewood Inc. and Wynnewood LLC.
§
Mitch Underwood and Troy Stephenson were
supervisors in Zone 2 of the refinery (where the Wickes boiler was located) under
both Wynnewood Inc. and Wynnewood LLC.
§
Kyle McCurtain was a technician in Zone 2 for
Wynnewood Inc., and he was promoted to supervisor by Wynnewood LLC.
§
Paul Howard was a technician in Zone 2 and a
member of the refinery’s supervision for both Wynnewood Inc. and Wynnewood LLC.
§
David Johnson, a safety specialist, worked for
the two entities for a total of eighteen years.
Given this extensive
overlap in supervisory personnel, I would find that substantial continuity has
been established under Sharon &
Walter. Cf. 23 BNA OSHC at 1296 (“[C]ontinuity of
nonsupervisory employees among the two companies is not significant . . . because
those employees are not responsible for OSH Act compliance and would not have
supervised its implementation.”).
Indeed, the supervisors working for both Wynnewood Inc. and Wynnewood
LLC were officials responsible for OSH Act and PSM compliance. Leiker and Looney
headed, for both Wynnewood Inc. and Wynnewood LLC, the certification of
abatement efforts in connection with prior settlements with OSHA. And Jackson managed the PSM program for both
entities, in particular relating to process hazard
analyses, pre-startup safety reviews, and management of change. See 29
C.F.R. § 1910.119(e) (“Process hazard analysis”), (i)
(“Pre-startup safety review”), (l) (“Management of change”). In
addition, Rains was responsible for the entirety of the operations department
for both Wynnewood Inc. and Wynnewood LLC, and Underwood was responsible for
reviewing and updating standard operating procedures for various pieces of
refinery equipment, including the Wickes boiler. See 29
C.F.R. § 1910.119(f) (“Operating procedures”).
Finally, Howard assisted Stephenson in implementing PSM requirements for
the FCCU. Thus, while parent company
executives may have changed, the personnel who, as a practical matter, actually controlled refinery safety on a daily basis for the pertinent entities remained the
same under both Wynnewood Inc. and Wynnewood LLC. As such, I would attribute the prior
Wynnewood Inc. violations to Wynnewood LLC for purposes of a repeat
characterization.
II. Substantial
Similarity of Violations
To establish a repeat
violation, the Secretary must also show that “at the time of the alleged
repeated violation, there was a Commission final order . . . for a
substantially similar violation.” Potlatch Corp., 7 BNA OSHC at 1063. “[P]roof that an employer has committed a
prior violation of the same standard constitutes a prima
facie showing by the Secretary of substantially similar
violations.” FMC Corp., 7 BNA OSHC 1419, 1421 (No. 12311, 1979). Here, the Secretary has made such a
showing—the repeat characterization of each of the five violations at issue is
based on a prior violation of the very same standard. The Commission has recently stated, however,
that “[t]his prima facie showing . . . may be rebutted by evidence of the
disparate conditions and hazards associated with these violations,” and “[a]lthough the principle factor in assessing repeat liability
is whether the two violations resulted in substantially similar hazards, this assessment may also take
into consideration other factors that bear on the similarity of the two
violations.” Angelica Textile Servs., Inc., 27 BNA OSHC 1246, 1255 (No. 08-1774,
2018) (emphasis in original) (citations omitted), appeal docketed, No. 18-2831 (2d Cir. Sept. 21, 2018).
In Angelica,
a Commission majority concluded that the Secretary’s prima facie showing was
rebutted by evidence demonstrating that the cited violations were minor
compared with the prior ones.
Specifically, the majority found that the prior violations involved
deficiencies in the employer’s confined space and lockout/tagout procedures
“that were significant enough to render [them] substantially ineffective,”
while “the Secretary established only minimal deficiencies” with regard to the
cited violations, “reflecting that after those prior violations, Angelica took
affirmative steps to achieve compliance and avoid similar violations in the
future.” Id. at 1256, 1257. In short,
given that the cited provisions were “performance-oriented, which means that
employers have flexibility in meeting their requirements,” the Commission held
that Angelica’s efforts and resulting substantial compliance rendered the cited
violations “stark[ly] differen[t]”
from the prior ones. Id. at 1258.
I dissented on the characterization issue in Angelica in part because the majority’s
focus on compliance efforts between the prior and instant violations injected
into the repeat analysis “an element of good faith or state of mind [that]
blurs the statutory distinction between a willful and repeated violation.” Id.
at 1262 (Attwood, Comm’r, concurring and dissenting in part). I reiterate my view here that Angelica was wrongly decided in this
regard. In any event, Angelica is distinguishable from the
present case. Wynnewood LLC frames its
rebuttal argument in the context of the successor liability issue and claims
that “upon Wynnewood’s acquisition by CVR Energy in 2011, safety, health, and
PSM protections greatly improved.” In my
view, this general assertion regarding Wynnewood LLC’s “overall safety culture”
falls short of proving that it made the type of specific improvements, relevant
to the specific standards that were cited, that the Commission deemed sufficient to rebut the Secretary’s prima facie showing in Angelica. Even the improvements the majority cites here
in the context of its successorship analysis—additional refinery safety
personnel, equipment upgrades, more formalized training programs, and a
“renewed emphasis” at the facility on management of change—are vague
generalizations that are not specific to the particular
standards cited.
Wynnewood LLC further argues that the prior
citations addressed equipment and processes clearly covered by the PSM
standard, which the company views as distinct from the Wickes boiler. While it is true that the prior citations
addressed different equipment than that at issue here, the Commission has
declined to “distinguish between various subcategories of . . . equipment
on the basis of its function and location” in affirming a repeat
characterization—“[t]hat the equipment which was the
subject of the present citation is of a different type than that previously
cited is of little moment.” Potlatch Corp., 7 BNA OSHC at 1065; see also Willamette Iron & Steel Co.,
9 BNA OSHC 1128, 1131 (No. 15317, 1980) (finding substantial similarity where
“the same hazard—a tripping hazard—is the subject of both violations,” despite
the fact that “the present violation also includes additional materials in the
clutter” that caused the hazard); FMC
Corp., 7 BNA OSHC at 1421 (finding “that a difference in the location of
violations at the same worksite is not a relevant consideration” in deciding
whether the violations are substantially similar).
Finally, Wynnewood LLC argues that the hazards
at issue in the prior citations were different from the hazard posed by the
Wickes boiler in this case, such that the violations are not substantially
similar. More specifically, the company
asserts that the prior citations addressed equipment and vessels involving HHCs
and/or flammables above threshold quantities, and so the hazards there included
toxic fire and explosions, self-contained hazardous vapor clouds, and employee
exposure to toxic chemicals. Wynnewood
LLC contends that the Wickes boiler does not handle any HHCs or flammables in a
threshold quantity, so the only potential hazards here are struck-by/crushing
hazards as a result of a boiler explosion.
A closer look at the prior and instant violations, however, shows the
following substantial similarities:
§ Docket No. 13-0791, Citation 2, Item 2, alleges a violation of
§ 1910.119(f)(1)(ii),[16]
based on Wynnewood LLC’s failure to “ensure the
written operating procedures addressed the operating limits of the process such
as . . . Minimum/Maximum gas
pressure to the boiler burner gas train [and] Minimum and maximum pressure . . . at the fuel gas inlet to
the Wickes,” which “exposed [employees] to fire and explosion hazards from
potential releases of fuel gas and other flammable liquids or gases.” The
prior violation also related to operating procedures that address excessive
pressure posing an explosion hazard; it was based on a failure to “develop and
implement a high limit for the Depropanizer
Accumulator pressure,” given that the “operations manual for the unit stated
the high limit was not applicable.”
§ Docket No. 13-0791, Citation 2, Item 3, alleges a violation of
§ 1910.119(g)(2),[17]
based on Wynnewood LLC’s failure to “ensure refresher training was provided . . . to each employee involved
in operating the Wickes.” The prior
violation also involved a lack of refresher training for operators,
specifically a failure to “ensure that refresher training [was] provided to
process operators.”
§ Docket No. 13-0791, Citation 2, Item 4, alleges a violation of
§ 1910.119(j)(2),[18]
based on Wynnewood LLC’s failure to “ensure that written procedures were
established and implemented for the testing and inspection of the Low
Combustion Air Flow Fuel Gas Shut-Off system safeguard.” The prior violation also dealt with written
procedures for a shutdown system; it was based on a failure to “develop written
procedures to maintain the ongoing integrity of controls, pumps, and emergency
shutdown systems in the HF Alkylation Unit.”
§ Docket No. 13-0791, Citation 2, Item 5, alleges a violation of
§ 1910.119(l)(1),[19]
based on Wynnewood LLC’s failure to “ensure management of change procedures
were implemented [for] . . . [t]he
amount of time the firebox is purged prior to attempting to light the pilot[,] . . . [t]he amount that the gas
control valve bypass valve is to be opened[,] . . . [and]
the addition of temporary power to operate the Wickes.” The prior violation also related to the
implementation of management of change procedures; it was based on the
company’s failure to “follow its own written procedures for management of
change regarding changes to procedures, piping and drains in the [alkylation]
unit.”
§ Docket No. 13-0644, Citation 2, Item 1, alleges a violation of
§ 1910.119(h)(2)(iv),[20]
based on Wynnewood LLC’s failure to “develop and implement safe work practices . . . to control the entrance,
presence and exit of contract employers and employees . . . [in]
the FCCU [and] . . . Alkylation
Unit.” Specifically, the Secretary
asserted in his post-hearing brief that while “WRC developed a sign[-]in sign[-]out process,” there were “numerous sign-out
logs where employees failed to sign out of various areas,” and the
sign-in/sign-out “rule was not being consistently enforced.” The prior violation also related to keeping
track of onsite contractor employees who were present in the same areas of
WRC’s facility; it was based on a failure to “ensure that individual contractor
employees are accounted for . . . in
the event of an emergency . . . at
the FCC and Alkylation Units.”
In short, each of these items addresses the same type of condition
involved in the prior violation, and the hazards addressed in the prior
citations were, generally, fire and explosion risks caused by a failure to
comply with the same PSM standards cited here.
More to the point, there is no support in the record for the company’s
contention that the only potential hazards associated with the Wickes boiler
were struck-by and crushing hazards, particularly in light of
testimony from the company’s own expert acknowledging that there was a fire
risk associated with the boiler.
Accordingly, I would find that Wynnewood LLC has failed to rebut the
Secretary’s prima facie case of substantial similarity, and I would
characterize the violations noted above as repeat.[21]
/s/
Dated: March
28, 2019 Cynthia L. Attwood
Commissioner
UNITED STATES OF
AMERICA
OCCUPATIONAL SAFETY
AND HEALTH REVIEW COMMISSION
SECRETARY
OF LABOR, |
Complainant, |
v. |
WYNNEWOOD
REFINING CO., LLC and
its successors, |
Respondent. |
DOCKET NOS. 13-0644
13-0791
Appearances:
Joshua Bernstein, Esq., Mia Terrell, Esq.,
Office of the Solicitor, U.S. Dept. of Labor, Dallas, Texas
For
Complainant
Nicole
Smith, Esq., Nicholas Hankey, Esq., DLA Piper LLP (US), Washington, D.C.
Lee
M. Smithyman, Esq., Smithyman
& Zakoura, Overland Park, Kansas
Edmund
S. Gross, Esq., CVR Energy, Inc., Kansas City, Kansas
For
Respondent
Before: Administrative Law Judge Brian A. Duncan
DECISION AND ORDER
I.
Procedural History
This matter
is before the United States Occupational Safety and Health Review Commission
(“Commission”) pursuant to Section 10(c) of the Occupational Safety and Health
Act of 1970, 29 U.S.C. § 651 et seq.
(“the Act”). On September 28, 2012, a
boiler exploded during a turnaround at the Wynnewood Refinery in Wynnewood,
Oklahoma, killing two employees. In
response, the Occupational Safety and Health Administration (“OSHA”) initiated
an inspection of the Wynnewood Refinery on September 29, 2012. (Tr. 1379; Ex. R-1). On October 29, 2012, Complainant initiated a second,
simultaneous inspection of the worksite in response to complaints about the
conditions in the refinery warehouse.
(Tr. 1381; Ex. R-19). As a result
of the inspections, OSHA issued two separate Citations and Notifications of Penalty (“Citations”) to Respondent.
(Ex. R-1, R-2). The Citation for
Inspection No. 663538 alleges one other-than-serious, eleven serious, and five
repeat violations of the Act, with a total proposed penalty of $234,500.00. The Citation for Inspection No. 778042 alleges
one repeat, one other-than-serious, and eleven serious violations of the Act,
with a total proposed penalty of $46,600.00.[22] Both Citations were issued on March 27, 2013.
(Ex. R-1, R-2). Respondent timely
contested the Citations. A trial was
conducted in Oklahoma City, Oklahoma beginning on September 16–23, 2014 and
concluding February 10–12, 2015. The
parties each submitted post-trial briefs for consideration.
Twenty-one
witnesses testified at trial: (1) John Koesler, operator for Respondent; (2) Greg Kellerhall, operator for Respondent; (3) Jeff Sutton,
console technician (“CT”) for Respondent; (4) James Willson,
former CT for Respondent; (5) Wesley Walker, CT for Respondent; (6) Justin
Sutton, operator for Respondent; (7) Kyle McCurtain, shift supervisor for
Respondent; (8) Mitch Underwood, unit supervisor for Respondent; (9) Troy
Stephenson, unit supervisor for Respondent; (10) Paul Howard, DCS technician
for Respondent; (11) James Johnstone, Complainant’s expert; (12) Casey Perkins,
Assistant Director for OSHA’s Austin, Texas Area Office; (13) Richard Hartung,
Compliance Safety and Health Officer (“CSHO”); (14) David Armstrong, warehouse
technician for Respondent; (15) Marcus Rambo, CSHO; (16) Dick Jackson, Process
Safety Management (“PSM”) Manager for Respondent; (17) Darin Rains, current
VP/GM of Respondent’s Coffeyville refinery and former operations manager at
Wynnewood; (18) Janet Barker, current Voluntary Protection Plan coordinator and
former Assistant Area Director for Complainant; (19) James Stanley,
Respondent’s expert; (20) Steve Arendt, Respondent’s expert; and (21) David
Johnson, former safety specialist for Respondent.
II.
Jurisdiction
The parties
stipulated that the Commission has jurisdiction over this proceeding pursuant
to Section 10(c) of the Act. (Tr. 51). The parties also stipulated that, at all times relevant to this proceeding, Respondent was an
employer engaged in a business and industry affecting interstate commerce within
the meaning of Sections 3(3) and 3(5) of the Act, 29 U.S.C. § 652(5). (Tr. 51). See Slingluff v. OSHRC, 425 F.3d 861 (10th Cir. 2005).
III.
Factual Background
This section
constitutes an overview of the operations of the Wynnewood refinery; its
history of ownership; the events that occurred on September 28, 2012; and the
subsequent inspections. To the extent that certain findings of fact are not
included in this Section III, any additional factual findings necessary to find
(or not find) that a violation has been established will be found in Section
IV.C.
A.
The Wynnewood Refinery
The
Wynnewood refinery is a 70,000 barrel-per-day (bpd) crude oil refinery, which
produces gasoline, propane, propylene, butane, fuel oils, and solvents. (Tr. 802–803;
Ex. C-5, C-16). The refinery is broken
into separate zones, each of which performs a different function in the
refining process. The citation items in Docket No. 13-0791 (Inspection No. 663538)
focus on Zone 2. Zone 2 contains the
Alkylation Unit, the Fluid Catalytic Cracking Unit (FCCU), and the Wickes
boiler, which caused the explosion and prompted the inspections leading to this
litigation. (Tr. 92–93). The citation
items in Docket No. 13-0644 (Inspection No. 778042) focus on alleged violations
in the warehouse, as well as general safety items identified throughout the
refinery.
The refinery
is owned and operated by Wynnewood Refining Co., LLC, which, at the time of the
2012 explosion, was a subsidiary of CVR Energy, Inc. (CVR). (Tr. 1700). CVR acquired Wynnewood from a subsidiary of
The Gary-Williams Energy Company, Inc. (GWE) in a stock purchase in December
2011. (Tr. 1700). According to the
evidence, there was no prior connection or affiliation between CVR and GWE. (Tr.
1701). They are completely
separate, unrelated companies.
B.
History of Wynnewood’s Ownership
i.
Gary-Williams Energy
During
Complainant’s presentation of the evidence, the Court heard from a number of employees and supervisors that worked at the
Wynnewood refinery prior to and after its purchase by CVR. The more notable
examples include: (1) Dick Jackson, who
served as the refinery’s PSM manager starting in 2010; (2) Troy Stephenson, who
became a roving shift supervisor in 2006 and was promoted to Zone 2 supervisor
in 2012, after the purchase;[23] (3)
Mitch Underwood, who served as the Alky Unit supervisor before and after the
purchase, and (4) Darin Rains, who served as operations manager prior to and
after the purchase, and is now the Vice President and General Manager of the
Coffeyville refinery, which is also owned by CVR. (Tr. 571, 618, 1578,
1699–1700). With a few exceptions, such as Rains and Jackson, all of the individuals that testified worked in a particular
unit of the refinery.
During GWE’s
tenure as the owner of Wynnewood, the refinery was inspected and cited for
violations of the Process Safety Management (PSM) standard, which, as is
relevant to this case, form the basis of the repeat violations alleged by
Complainant. Those violations, as well
as prior boiler explosions, including incidents involving the specific boiler
at issue in this case, will be discussed in further detail in the succeeding
sections of this Decision. See Section III.C, infra.
In 2006,
there was a fire in the refinery’s alkylation unit (Alky Unit), which prompted
an inspection and the issuance of citations by Complainant. (Ex. C-27). In that case, Respondent conceded
that the equipment involved in the Alky Unit fire “involve[d] the use of HHCs
[highly hazardous chemicals] and/or flammables in amounts that [met] the
threshold quantity for PSM coverage . . . .” Resp’t Br. at 5. The parties executed a partial settlement agreement,
which became a final order of the Commission around April of 2007.[24]
(Tr. C-28 at 11–12 n.1).
Around the
same time that the partial settlement agreement became a final order of the
Commission, Respondent’s employees were attempting to manually light the H-4
boiler, which is located in the refinery’s boiler
house. (Ex. R-46 at 1–2). During the
lighting process, there was an explosion in the H-4 boiler, which injured two
employees. (Id.). The explosion prompted another OSHA inspection,
which resulted in the issuance of two citation items, each alleging violations
of the general duty clause. (Ex. R-45). Respondent
points out that, notwithstanding the similarity between the explosion in April
2007 and the explosion of the boiler in this case, Complainant did not issue
citations pursuant to the PSM standard in 2007. The matter was settled when
Complainant agreed to withdraw one of the citation items. (Ex. R-47).
Shortly
after the H-4 boiler explosion, Complainant initiated an inspection pursuant to
the National Emphasis Program on PSM. (Tr. 2004–2006). The focus of this particular
inspection was the Fluid Catalytic Cracking Unit (“FCCU”), which
introduces catalysts into crude oil to “strip” the product and create high
octane fuels.[25]
(Tr. 256–57). The inspection lasted
until March 24, 2008, at which time Complainant issued multiple citation items,
alleging violations of the PSM standard. (Ex. C-25). The parties executed a settlement agreement
on September 15, 2008, which became a final order of the Commission on November
10, 2008. (Ex. C-26). Respondent points
out that, notwithstanding the H-4 boiler explosion just months before, there
was no apparent attempt to inspect the boilers pursuant to the PSM standard.
(Tr. 2010–2012)
ii.
CVR Energy (Respondent)
As noted
above, CVR purchased Wynnewood from GWE in December of 2011. According to Darin Rains, this was done via
stock purchase. (Tr. 1700). In contrast
with the relatively scant evidence regarding GWE’s involvement at Wynnewood,
Rains testified that the refinery “went through some pretty drastic changes as
a result of the purchase by CVR Energy.” (Tr. 1701).
Some
examples of the changes noted by Rains include access to previously unavailable
capital, an increase in the number of safety and supervisory operations
personnel, and the regular presence of CVR corporate management. (Tr.
1701–1703). The increase in capital led
to improvements in equipment—CVR spent roughly $130 million on improvements to
the refinery in the Fall 2012 Turnaround. (Tr. 1706; Ex. C-16). Rains noted, though, that the most
significant changes were in the personnel arena. (Tr. 1701). Once CVR purchased the refinery, Wynnewood
“substantially increased the number of people working at the facility”,
including two new safety technicians and four assistant operations supervisors,
whose primary role was to focus on procedure development, training, management
of change (MOC) compliance, and other issues touching on PSM and occupational
safety. (Tr. 1702). In addition to
changes at the ground level, Rains also testified that members of CVR’s
corporate management, including the executive vice president for operations,
Robert Haugen, and the vice president for safety, health, and environment,
Chris Swanberg, made regular visits to the refinery.
(Tr. 1703). There is no evidence to
suggest that similarly situated GWE corporate managers were so involved.
This
perception of wholesale change to the organization and management of Wynnewood
was shared by a number of Respondent’s employees and
managers. For example, Stephenson noted,
“[P]rior to CVR buying us, things were not as formal . . . . We did our
best but since CVR has taken over, we’ve formalized everything and the
expectations are a lot higher in regards to safety,
MOCs, procedures. Things are a lot more strict and a lot more disciplined.” (Tr. 674–75). These sentiments were echoed by Paul Howard
and Dick Jackson, who stated, “The new company has raised the level of the
safety programs since they’ve taken over, and their involvement in the safety
program included process safety.” (Tr. 749, 1612).
C.
The Wickes Boiler
The
explosion that killed two employees on September 28, 2012, originated at the
Wickes boiler, which is part of the FCCU located in Zone 2. (Tr. 92–93; Ex. C-7,
C-11). The Wickes, as described by many
of Respondent’s employees, “was by far the workhorse of the plant for steam.”
(Tr. 360). It is one of four boilers
that provide steam to the 225-pound steam header, which, in turn, routes steam
for use in various processes throughout the plant. (Tr. 2057–58; Ex. C-8 to
C-13). Some of those processes include
providing emergency steam to the riser, which clears it of HHCs; injecting
steam into the FCCU process to drive high-end products out of the crude oil,
also known as steam-stripping; purging low-lying gases in the firebox of the
Alky Unit heater during start-up; powering turbines to pump product; and
serving as a back-up to the electric pumps. (Tr. 162–63, 236–37).
The Wickes
itself is fueled by two separate fuel streams within the refinery—the refinery
fuel gas (RFG) system and a natural gas fuel line. (Tr. 134–40; Ex. C-10). The RFG system, which is the primary source of
fuel for the Wickes, is a fuel recycling system of sorts. Various processes
throughout the plant, such as the FCCU, refine crude oil to a saleable product.
As a result of these processes, a certain amount of non-condensable flammable gas
remains. (Tr. 138). Though this gas
cannot be converted into a saleable product, the refinery still uses it to fuel
various processes throughout the plant. (Tr. 139). These “off-gases” that are produced
throughout the plant are directed via pipeline to a fuel drum, where the
refinery fuel gas is treated. (Tr. 1602–1603).
The resulting gas mixture is then piped out of the drum into a 4.1-mile
pipeline network that leads to different processes throughout the refinery,
including the Wickes. (Tr. 1710–11). Such is the process for normal operations;
however, in some instances, such as during a turnaround, the Wickes can be
powered by natural gas alone. (Tr. 134–35).
In order to start
the Wickes boiler, Respondent had to go through a fairly
detailed process, which involved no fewer than three employees. (Tr. 98).
The first step requires the CT to purge HHCs from the boiler’s firebox for 30
minutes by blowing air into it. (Tr. 111, 421; Ex. C-34). Once the firebox has
been adequately purged, the pilot light has to be lit.
(Tr. 335). After the pilot is lit, an
operator is directed to open the fuel gas bypass valve, which introduces the
RFG mixture into the firebox. (Tr. 335).
Each operator that testified gave a slightly different description as to
how this part of the process is carried out.
Koesler, for example, stated that he was told
to turn the bypass valve “one-quarter of a spoke” and to leave it open for 5–10
seconds, though he admitted there was not a set amount of time to keep the
valve open. (Tr. 113, 116–17). McCurtain
testified that he was trained to open the valve “slightly” or “just a little
bit” and to close the valve if he did not achieve ignition “quickly” or “shortly”.
(Tr. 518, 528). During this process,
another operator positions himself at the sight glass, which allows him to
determine whether there has been a successful ignition.[26] Once ignition is achieved, control over fuel
management is handed over to the CT in the control room. (Tr. 335).
With the exception of a shutdown because of a turnaround or annual boiler
inspection by the State of Oklahoma, the Wickes was operated constantly. (Tr. 376).
As such, there were limited
opportunities for operators and CTs to light the boiler.[27] (Tr.
376). According to McCurtain, however,
it was “not uncommon” for operators to experience a “hard start” when
attempting to light the Wickes. (Tr. 516).
A hard start is best characterized as a mini-explosion occurring within
the firebox, typically a result of allowing too much fuel into the system. (Tr.
102–103). Koesler
stated that, instead of lighting smooth, a hard start causes the boiler to
“woof” or “huff” as a result of a sudden pressure increase within the firebox.
(Tr. 104). In some cases, this merely
caused the boiler to spew dust and smoke; in others, the structure of the
boiler actually bowed outward as a result of the
explosion. (Tr. 106–107, 213; Ex. C-31).
In one instance, Willson, who was manning the
sight glass, was actually struck by the boiler, which
had bowed outward during a hard start. (Tr. 357–58; Ex. C-31).
D.
The Turnaround
On September
28, 2012, Respondent was in the middle of a refinery turnaround.[28]
(Tr. 108–109). During the turnaround,
the refinery was shut down and was not refining petroleum. Instead, Respondent
hired multiple subcontractors to come to the refinery to repair, replace, or
maintain various pieces of equipment throughout the refinery. (Tr. 1704–1706). According to David Johnson, there could be as
many as 1500 contractors working on a shift, which drastically increased the
number of people present at the refinery. (Tr. 2104).
In order to
facilitate repairs and maintenance, Respondent needed to produce steam to purge
HHCs from various lines and equipment. (Tr. 369). This required starting up the Wickes boiler.
Because the refinery was off-line and not producing fuel products, Respondent
had to use natural gas to light the Wickes. (Tr. 346). According to Willson,
the Wickes had been taken off-line earlier that day to make a switch of the
electrical supply circuits. (Tr. 347). Due
to power supply problems, the crew implemented a temporary solution by running
an extension cord to a small generator, which powered the controls and
interlocks of the Wickes. (Tr. 347).
According to Jeff Sutton, the previous CT reported that the temporary
power supply was causing the vanes, which control air flow, to malfunction.
(Tr. 278–79). Eventually the problem was
fixed, and Sutton began to increase the airflow to purge the Wickes firebox of
any remaining HHCs. (Tr. 279).
At the
conclusion of the purge, which lasted about five minutes, Sutton reduced the
airflow to 15,000 cubic feet per minute (cfm) to light the pilot. (Tr.
281). While Sutton was working in the
control room, Lead Operators Koesler and Willson; “A” Operators Russell Mann, Billy Smith, and
Justin Sutton; and “B” Operator Steve Graves were located at or around the
boiler. (Ex. R-110 at 4). Lead Operators
Koesler and Willson were
located at the northwest corner of the Wickes and were overseeing the lighting
attempt. (Tr. 98). Mann was positioned
at the fuel bypass valve, and Smith was positioned at the sight glass to verify
ignition. (Ex. R-110 at 4). Justin
Sutton and Graves did not have specific responsibilities related to the
lighting process.
After the
firebox had been purged, Mann opened the fuel gas bypass valve to introduce
natural gas into the firebox. (Tr. 112).
At some point in the process, Koesler
instructed Mann to close the valve because they had not achieved ignition. (Tr.
126). Mann did not comply with this
instruction. (Tr. 191). When Koesler confronted him, Mann informed Koesler
that he was taking instructions from Willson, who was
standing nearby. (Tr. 191). After a
brief interaction between Willson and Koesler, Koesler moved to the
north side of the boiler to check water levels. (Tr. 125). Willson continued
to oversee Mann, who kept the bypass valve open.
As fuel was
being introduced into the firebox, the other CT in the control room, Wesley
Walker, looked at Sutton’s console and noticed that the firebox was flooded
with too much natural gas. (Tr. 401–402).
Walker immediately radioed the operators to inform them that they should
close the bypass valve. (Tr. 402).
Shortly after Mann closed the valve, the boiler exploded. Smith, who was manning the sight glass, was
pronounced dead at the scene, and Mann, who was critically injured in the
explosion, died twenty-eight days later. (R-110).
Subsequent
investigations by Respondent revealed shrapnel in the area surrounding the
Wickes, and a ladder, which was attached to the west end of the boiler, that
had been blown completely across the street.
Additionally, investigators found that the valve was opened
approximately one-and-a-half spokes and that fuel had been flowing into the
firebox for approximately 5 minutes. (Ex. R-110 at 8). Many of the operators and CTs involved in the
lighting were disciplined, and one of the Lead Operators, Willson,
was discharged. (Tr. 95, 369; Ex. C-89).
IV.
Discussion
Prior to answering
the question of whether any particular standard was
violated, the Court must resolve two important issues. First, the Court must determine whether the
PSM standards cited by Complainant apply to the Wickes boiler. Respondent contends that, by including the
boiler within the ambit of the PSM standard, Complainant has improperly
expanded the scope of the standard beyond its intended purpose, which is to “prevent[] or minimiz[e] the
consequences of catastrophic releases of toxic, reactive, flammable, or
explosive chemicals”. 29 C.F.R. § 1910.119. Consistent with that assertion, Respondent
argues that although the boiler is physically connected to a PSM-covered
process, the boiler itself is not subject to the PSM standards because it
cannot contribute to, cause, or interfere in the mitigation of a catastrophic
release of HHCs. See Delek
Refining Co., Ltd., 25 BNA OSHC 1365 (No. 08-1386, 2015). In response, Complainant has asserted
multiple theories of coverage to suggest that the boiler would have just such
an impact.
Second, the
Court shall also address the issue of successor liability in the context of the
repeat violations issued to Respondent. As
previously discussed, Wynnewood Refinery changed ownership in 2011. The purchase occurred after the underlying
citations were issued but before the issuance of the citations that are
currently under discussion. Complainant
submits that the citations were properly characterized as repeat and bases that
conclusion on the substantial continuity test for successor liability, which was
adopted by the Commission in Sharon &
Walter, 23 BNA OSHC 1286 (No. 00-1402, 2010). Respondent, on the other hand, contends that
the changeover in ownership resulted in changes in management practices,
procedures, and culture significant enough to break the chain of liability
stemming from GWE’s previous actions.
Ultimately,
based on what follows, the Court finds that the PSM standards did apply to the
Wickes boiler. Complainant’s application
of the standard under this set of facts comports with its plain language and is
consistent with its historical interpretation of the standard. The Court also finds, however, that
Complainant failed to show the requisite nexus between Wynnewood under the
ownership of GWE and Wynnewood under the ownership of CVR such that liability
for repeat violations survived the transfer of ownership.
A.
PSM Coverage
i.
The Standard – 29 C.F.R. § 1910.119
The stated
purpose of the PSM standard is to “prevent[] or minimiz[e] the consequences of catastrophic releases of
toxic, reactive, flammable, or explosive chemicals.” 29 C.F.R. § 1910.119. A
catastrophic release, according to the standard, is “a major uncontrolled
emission, fire, or explosion, involving one or more highly hazardous chemicals,
that presents serious danger to employees in the workplace.” Id.
§ 1910.119(b). The standard sets a
threshold quantity for various hazardous chemicals—that threshold quantity (TQ)
represents the point at which a particular chemical is
considered capable of producing a catastrophic release. See id.
§ 1910.119(a)(1). In this case, the operative
question is whether the Wickes boiler is a part of a “process which involves a
Category 1 flammable gas (as defined in 1910.1200(c)) or a flammable liquid
with a flashpoint below 100 °F (37.8 °C) on site in one location, in a quantity
of 10,000 pounds (4535.9 kg) or more” such that the standard applies.[29] Id. § 1910.119(a)(1)(ii). Such a determination would establish a prima facie case for coverage; however, the
Court must also decide whether the exception for HHCs “used solely for
workplace consumption of fuel” applies. See
id. § 1910.119(a)(1)(ii)(A).
As the title
implies, the focus of this standard are processes
involving highly hazardous chemicals.
Insofar as a process involves a threshold quantity of HHCs, it is
covered, subject to certain exceptions. A process, according to the standard,
is:
[A]ny
activity involving a highly hazardous chemical including any use, storage,
manufacturing, handling, or the on-site movement of such chemicals, or
combination of these activities. For purposes of this definition, any group of
vessels which are interconnected and separate vessels which are located such
that a highly hazardous chemical could be involved in a potential release shall
be considered a single process.
Id. § 1910.119(b). This definition indicates (1) the basic
understanding of a “process” and (2) the potential boundaries for that
process. This was explained in more
detail in the preamble to the standard, which states:
The term “process” when used in
conjunction with the application statement of the standard establishes the
intent of the standard. The intent of the standard is to cover a “process”
where the use, storage, manufacturing, handling or the on-site movement of a
highly hazardous chemical exceeds the threshold quantity at any time. The
boundaries of a “process” would extend to quantities in storage, use,
manufacturing, handling or on-site movement which are interconnected and would
include separate vessels located such that there is a reasonable probability
that an event such as an explosion would affect interconnected and nearby unconnected
vessels which contain quantities of the chemical that when added together would
exceed the threshold quantity and provide a potential for a catastrophic
release. In order to clarify this intent, a new sentence has been added to
clarify the fact that interconnected and nearby vessels containing a highly
hazardous chemical would be considered part of a single process and the
quantities of the chemical would be aggregated to determine if the threshold
quantity of the chemical is exceeded.
Process Safety Management of Highly
Hazardous Chemicals, 57 Fed. Reg. 6356, 6372 (Feb. 24, 1992).
ii.
Complainant’s Theories of
PSM-Coverage
Complainant
asserts multiple bases upon which the Wickes boiler should be considered a
PSM-covered process. Specifically, Complainant asserts that (1) the Wickes is
interconnected to a covered process through the refinery fuel gas system and
steam header; (2) the Wickes is located such that a HHC could be involved in a
potential release involving other PSM-covered equipment; (3) the exception for
workplace fuel consumption does not apply; and (4) Respondent treated the
Wickes in its own internal documentation as a PSM-covered process. In response,
Respondent contends that (1) Complainant’s interpretation of the standard
improperly expands the scope of what is considered a “process”; (2) the Wickes
is not sufficiently close to PSM-covered equipment such that it could be
involved in a potential release; (3) the workplace fuel exception clearly
applies; and (4) the fact that it applied PSM-related practices to the Wickes
is only reflective of “best practices” and not an admission of coverage.
1.
Interconnection
The Wickes
boiler, viewed in isolation, is not a PSM-covered process. There is no single
point in time where it processes, uses, or holds a threshold quantity of HHC.
Thus, the determination of whether it is covered necessarily depends on its
connection or location relative to other covered processes. The dispute over
interconnection stems from the second sentence of the definition of the term
“process”, which states that “any
group of vessels which are interconnected and separate vessels which are
located such that a highly hazardous chemical could be involved in a potential
release shall be considered a single process.”
29 C.F.R. § 1910.119(b) (emphasis added). Complainant asserts that the definition
establishes two separate bases upon which coverage can be established: (1)
interconnected vessels; and (2) separate vessels located such that a HHC could be involved in a potential release. Respondent
contends, however, that the modifier “such that a highly hazardous chemical
could be involved in a potential release” is applicable to both separate and
interconnected vessels, thereby grafting an additional burden of proof for
establishing PSM coverage under a theory of interconnection. The Court
disagrees.
This dispute
stems from what is known as the Motiva Response, which was a formal
interpretation issued by Complainant in response to Motiva Enterprises., LLC, 21 BNA OSHC 1696 (No. 02-2160,
2006). (Ex. C-3). See
also Interpretation of OSHA’s Standard for Process Safety Management of
Highly Hazardous Chemicals, 72 Fed. Reg. 31453 (June 7, 2007). In Motiva,
the Commission grappled with what it believed to be an undefined term within
the PSM standard’s TQ requirements for flammables; namely, what constituted “on
site in one location”. Motiva, 21 BNA OSHC 1696. Due to the lack of clarity within the
application paragraph, and less than convincing evidence, the Commission
vacated the citation and placed the onus on the OSHA to offer an “authoritative
interpretation” that would be reviewed in future cases under “standard
deference principles.” Id. at *4.
In response,
OSHA issued a formal interpretive document in the Federal Register. First, OSHA agreed that the language “on site
in one location” in the application paragraph has considerable overlap with the
definition of process. (Ex. C-3 at 1524).
This was due, in part, to the fact that the definition of “process” was
revised in the final rule to clarify that a single process includes both
interconnected and co-located vessels, depending on proximity. (Id.).
Due to this change, OSHA noted that “the limitation placed on
application of the standard to flammable liquids and gases denoted by the
related phrase ‘on site in one location’ no longer carries the independent
weight it had before OSHA clarified the intended meaning of ‘process.’” (Id.).
However, its import was not entirely diminished, as “it continues to
serve a separate purpose by operating to exclude coverage where the HHC
threshold would only be met only if all amounts in interconnected or co-located
vessels were aggregated but some of the amounts needed to meet the threshold
quantity are outside the perimeter of the employer’s facility.”
Second, and
more pertinent to this case, OSHA clarified the burden of proof relative to
interconnected versus co-located processes by stating that the PSM standard
“presumes that all aspects of a physically connected process can be expected to
participate in a catastrophic release.” (Id.). With respect to co-located processes,
however, OSHA must prove that they are located such that a hazardous chemical
could be involved in a potential release. (Id.). Respondent takes issue with this formulation
because it believes that such an interpretation is “in direct contradiction”
with the plain terms of the standard. Resp’t Br. at
27.
Respondent’s
primary argument in this regard is that “[t]he absence of punctuation between
the term “interconnected” and “separate” establishes that the requirement that
an HHC could potentially be involved in a release applies to both
interconnected and co-located equipment.” First, it is not clear what sort of
punctuation Respondent is referring to. Second, the basic structure of the
sentence belies Respondent’s argument regarding plain meaning. The sentence
describes two configurations on either side of the conjunction “and” and
concludes that either configuration constitutes a “process” for the purposes of
the PSM standard. The first configuration
is “any group of vessels which are interconnected”. The second configuration is “separate vessels
which are located such that a highly hazardous chemical could be involved in a
potential release.” In both cases, the
noun is described through the use of a dependent
clause, indicated by the term “which”.
In other words, there is a basic, parallel structure on either side of
the “and”, which can be diagrammed as follows: “For the purposes of this definition,
[A’s] which are [x] and [B’s] which are [y] shall be considered [C].” See 29
C.F.R. § 1910.119(b). When analyzed in
this way, the Court finds that Complainant’s interpretation, as expressed
through the Motiva response, comports
with the plain meaning of the definition.
Let us
assume, however, that Respondent is correct to the extent that the definition
of process is ambiguous. If a
determination cannot be reached based on the text and structure of the
regulation, courts then turn to “contemporaneous legislative histories of that
text.” Unarco Comm. Prods., 16 BNA OSHC 1499 (No.
89-1555, 1993). On such contemporaneous
legislative history is the preamble to the final rule. See generally 57 Fed. Reg. at 6356; see also 72 Fed. Reg. 31453.
The preamble provides a clear distinction between interconnected and
separate vessels: “The boundaries of a
‘process’ would extend to quantities in storage, use, manufacturing, handling
or on-site movement which are interconnected and would include separate vessels
located such that there is a reasonable probability that an event such as an
explosion would affect interconnected and nearby unconnected vessels which
contain quantities of the chemical that when added together would exceed the
threshold quantity and provide a potential for a catastrophic release.” 57 Fed. Reg. at 6372. This discussion, which provides contour to
the definition of process, makes clear that the term “process” extends to interconnected vessels and includes separate vessels, insofar as
such vessels could reasonably be expected to participate in a catastrophic
release. Given this explanation, the Court still finds that the standard
presumes the potential for a catastrophic release when vessels are physically
connected.
Finally,
even if the preamble is somehow considered deficient in its clarification, the
Court finds that the interpretation espoused by Complainant is both reasonable
and consistent with its longstanding interpretation of the issue. See Simpson,
Gumpertz & Heger, Inc.,
15 BNA OSHC 1851 (No. 89-1300, 1992) (“The weight of such [an interpretation]
in a particular case will depend on the thoroughness evident in its
consideration, the validity of its reasoning, its consistency with earlier and
later pronouncements, and all those factors which give it power to persuade, if
lacking the power to control.”) (citing General
Elec. Co. v. Gilbert, 429 U.S. 125, 142 (1976) (quoting Skidmore v. Swift & Co., 323 U.S.
134, 140 (1944))). There is nothing patently
unusual or unreasonable about considering vessels that are physically connected
by pipeline to be part of the same process, nor is it unreasonable to presume
that vessels connected in such a way could be involved in a potential release
of HHCs. This has been Complainant’s
interpretation of the standard since its inception. (Ex. C-4). Accordingly, the Court finds that
Complainant’s interpretation of the standard is reasonable and, therefore,
entitled to deference. See Martin v. OSHRC (CF&I Steel), 499
U.S. 144, 145–46 (1991) (Secretary’s interpretation of a standard, even when
embodied in a citation, is entitled to deference so long as it is reasonable).
According to
the P&IDs involving the Wickes boiler, it is physically interconnected to
otherwise-covered PSM processes in two ways.
First, the Wickes boiler is connected to both the Alky Unit and the FCCU
through the RFG pipeline. (Tr. 655, 911). It is undisputed that the Alky and the FCCU
are PSM-covered processes by virtue of the quantity of flammables contained in
each.[30]
(Ex. C-5). Second, the Wickes is
connected to virtually all of the refinery’s processes
through the 225-lb. steam header. (Ex. C-7). As such, Complainant has, at the very least,
established a prima facie case for
PSM coverage, because interconnected processes are presumed to have the
potential to participate in a catastrophic release. However, such a presumption
could be rebutted by a showing that the interconnected processes at issue could
not participate in or contribute to a catastrophic release.
Perhaps anticipating
the potential failure of its argument regarding the presumption associated with
interconnected processes, Respondent also argues that the Wickes should not be
considered interconnected to a covered process under the terms of the standard. First, Respondent suggests that the Wickes is
not a “vessel” because it does not store or contain any measureable
quantity of HHC. Second, Respondent
argues that the concept of interconnection, as espoused by Complainant, does
not merely equate to a physical connection between equipment; rather:
[T]he concept
of interconnectivity is merely intended to address a situation in which
connected vessels within a single process that contain quantities of HHC, such
as flammable gas storage tanks, will be deemed to satisfy the threshold
requirement even though the amount of flammables in each individual vessel is
less than 10,000 pounds. This theory
does not operate to extend coverage to any structure, regardless of its form or
contents, that is physically connected to a PSM-covered process.
Resp’t Br. at 29 (internal citations
omitted). The Court disagrees.
The
Commission dealt with a similar attempt to narrow the scope of the standard in Delek Refining Co., Ltd., 25 BNA OSHC 1365
(No. 08-1386, 2015).[31] In that case, OSHA alleged that the employer
violated a portion of the PSM standard by failing to inspect and test its
positive pressurization unit (PPU) in the control room of its own FCCU. Delek, 25 BNA
OSHC 1365 at *6. The PPU was designed to
pressurize the control room to prevent hazardous vapors, which are a byproduct
of the FCC process, from entering the control room and poisoning the employees
inside or causing an explosion hazard due to the presence of wiring, which
could serve as an ignition source. Id. Delek contended
that the PPU was not “process” equipment, because it was not directly involved
(physically connected) in the process of converting crude oil to usable fuel.
Although
the specific subsection of the PSM standard at issue in that decision was
different, the Commission still had to address the question of what constitutes
the boundaries of a process. The
Commission made it clear that the focus of the standard—the process—was not as
narrow as suggested by Respondent.
According to the Commission:
[T]he PSM standard does not require
that every part of a ‘process’ come into contact with
hazardous materials. 29 C.F.R. §
1910.119(b) (defining ‘process’ as ‘any activity involving a highly hazardous chemical”) (emphasis added). Here viewing the ‘activity’ involving the FCC
unit in its entirety, the PPU is part of a ‘process’ covered by the PSM
standard because it is an integral part of the ‘manufacturing, handling [and]
onsite movement of [highly hazardous chemicals].”
Delek, 25 BNA OSHC 1365 at *7.
Citing favorably to an OSHA Interpretation Letter from Richard Fairfax
to Howard J. Feldman, the Commission noted that machinery not containing HHCs
can nonetheless be a part of a process insofar as such machinery is used to
control, prevent, or mitigate catastrophic releases. Id. at *8–9.
The
Court finds that Respondent places undue emphasis on individual terms such as
“vessel” and “interconnected” at the expense of the focus of the standard as a
whole—the process. As noted by the
Commission, the definition of “process” is broad—it is any activity involving a HHC, including any use,
storage, manufacturing, handling, or on-site movement. See 29
C.F.R. § 1910.119 (emphasis added). So
broad, in fact, that the Commission held that the PPU in Delek’s
FCC control room, although not a vessel, was part of the FCC process because it
could affect or cause a release. Id.
In
this case, the connection between the Wickes and the FCCU is more
concrete: the off-gases produced by the
FCCU are directed via pipeline to a fuel drum, which mixes the off-gases treats
them, and directs the resulting product to the Wickes. (Tr. 857, 918). The Wickes is clearly an activity that involves a HHC,
because it uses the treated off-gases
from various processes around the refinery. It is, in fact, a downstream
endpoint of the RFG process. (Tr. 838). During
normal operations,[32]
there are multiple processes that feed the RFG system, including the FCCU and
the Alky Unit. (Tr. 920, 1098). These
processes, with the exception of a turnaround, are
basically running all the time. (Tr. 1706).
As the Court observed during the trial, the bypass valve that controls
the flow of RFG can apparently be left open indefinitely without an alarm—it
was not until CT Walker happened to look over the shoulder of CT Sutton and
noticed a large amount of fuel in the firebox that the order was given to shut
it down.[33]
(Tr. 293, 402). Further, the Wickes,
which all witnesses testified is almost always running, requires a constant
stream of fuel. Thus, even if the Court
accepts Respondent’s assessment of the RFG pipeline’s capacity, which it
determined to be 860 pounds of fuel, that assessment disregards the source of
the fuel, such as the FCCU and the Alky, which feed the RFG system and are
directly connected to the Wickes.[34] (Tr.
1598; R-124). The Court cannot find any
basis in the regulatory history or the language of the standard itself that
would suggest such an arbitrary determination of what is interconnected. Accordingly, the Court finds that the Wickes
was interconnected to a covered process, and, as such, should be considered a
single process. See 29 C.F.R. § 1910.119(b).
Respondent
further contends that even if the foregoing is true, the Wickes should still be
exempt from coverage. According to
section 1910.119(a)(1)(ii)(A), the following are exempted from PSM
coverage: “Hydrocarbon fuels used solely
for workplace consumption as a fuel (e.g., propane used for comfort heating,
gasoline for vehicle refueling), if such fuels are not a part of a process
containing another highly hazardous chemical covered by the standard.” Id.
§ 1910.119(a)(1)(ii)(A). The intended
scope of this rule was described in the preamble to the standard, wherein the
American Petroleum Institute noted that
OSHA’s intention in providing
exemption (b)(1)(ii)(A) was to exclude the enormous number of small business
locations across the nation which would not be covered by the proposed rule,
except for their on-site storage of hydrocarbon fuels for low-risk applications
such as heating, drying, and the like. Such activities are not the subject of
this rule, and this exclusion is entirely appropriate.
On the other hand, interpreting this
exclusion to apply to hydrocarbon fuels used for process-related applications
such as furnaces, process heaters, and the like at facilities covered by the
rule was not intended.
57 Fed. Reg. 6356, 6367. At the very outset, this exception had a very
limited scope: small businesses that
used on-site hydrocarbon fuels “for low-risk
applications such as heating, drying, and the like.” Id.
(emphasis added). The exception was not,
however, intended to cover process-related applications such as process heaters
and furnaces. Id. It is significant that this
was recognized by API, which promulgates consensus standards covering the
petroleum industry. See, e.g., 72 Fed. Reg. 31453, 31454 (citing API 750 as basis for
definition of “process”). Thus, the
issue is, again, one of degree: Is the
Wickes, as compared to process heaters and furnaces, which are explicitly not
covered under the exception, properly considered a part of a process involving
another highly hazardous chemical covered by the standard?[35] Respondent
contends that furnaces and heaters are more directly linked to a process than a
boiler, because furnaces and heaters typically apply heat directly to a
product, whereas a boiler merely supplies steam to a header, which directs that
steam to various processes around the refinery.
The
Court is not convinced by the furnace versus boiler distinction urged by
Respondent, nor is it convinced that the workplace fuel exception applies. Though the preamble mentions furnaces and
process heaters as specific process-related applications, the list is not
exhaustive, but exemplary. See 57
Fed. Reg. 6356, 6367 (exception does not cover “furnaces, process heaters, and the like”) (emphasis added). To the extent that process heaters, furnaces,
“and the like” are the examples of what is not covered by the exception, and
considering Respondent’s argument that there is a qualitative difference
between the manner in which a furnace is connected to a process, as opposed to
a boiler, the Court will address the manner in which the Wickes is connected to
other PSM-covered processes and determine whether that connection is sufficient
to establish PSM coverage.
While
the Wickes is the downstream endpoint for the RFG system, it is also a starting
point for many other process-related applications. The Wickes’ core function is to produce
steam. That steam is used in multiple process-related applications throughout
the refinery. For example: (1) When the FCC emergency shut down (ESD)
system is activated, steam is directed to the riser, where it knocks down gases
to prevent further catalyzing of crude oil; (2) Steam is used as a catalyst in
certain reactions, driving high-end products from crude oil, also known as
steam-stripping; (3) In normal operations and emergencies, steam was used as a
primary source to drive turbines that pumped product and as a back-up to
electric pumps; (4) In the Alky, steam is used to snuff out low-lying gases and
purge fugitive HHCs from the heater prior to lighting it (in much the same way
that air is used to snuff gases in the Wickes); (5) Steam is used as a heat
medium in an exchanger, which transfers heat to a process; and (6) Steam hoses
are used to put out small fires on a process pipe. (Tr. 162–63, 236, 239, 1716–17; Ex. C-8). On the face of it, all of
these applications are a process-related to some degree. Nonetheless, Respondent contends that the
steam producing system is a mere utility and that it has specifically
determined that “the boiler could not cause or interfere in mitigating the
consequences of a catastrophic release.” Resp’t Br. at 31 (citing Ex. R-84).
Respondent,
much like the employer in Delek, urges a narrow view of the concept of process-relatedness. In Delek, the employer cited an OSHA Interpretation Letter,
which contained language stating that “‘[t]he boundaries of the covered process
are based on the equipment which contain [highly hazardous chemicals].’” Delek, 25 BNA OSHC 1365 at *7. The Commission disagreed with such a narrow
reading, focusing on the following language:
OSHA does not agree that utility systems are categorically outside
the scope and application of the PSM standard. It is OSHA’s long-standing
position that utility systems are part of the PSM-covered process when
employers use them to control/prevent and mitigate catastrophic releases . . . .
* * *
[T]he proper safe
functioning of all aspects of a process, whether they contain [highly hazardous
chemicals] or not, are important for the prevention and mitigation of
catastrophic releases of [highly hazardous chemicals], due to their direct
involvement in the overall functioning of the process.
As a result, it is
OSHA’s position that if an employer determines that a utility system or any
aspect or part of a process which does not contain a [highly hazardous
chemical] but can affect or cause a release . . . then, relevant elements of
PSM could apply to these aspects. OSHA’s position is that any engineering
control, including utility systems, which meets the above criteria must be . .
. inspected/tested/maintained per OSHA PSM requirements.
Id. at *8–9. Here, Respondent cites the same letter, in
addition to another interpretive document, for the essentially the same
proposition. (Ex. R-83, R-84).
Specifically,
Respondent contends that, notwithstanding the numerous ways in which the Wickes
is connected to various covered processes, it has analyzed those connections
and specifically determined that the failure of the Wickes would not “cause a
HHC release or interfere with the consequences of a HHC release . . . .” (Ex.
R-84). Like the employer in Delek, Respondent
places significant emphasis on the “if an employer determines” language to
argue that the determination of the boundaries of a PSM-covered process “is the
responsibility of the employer, not Complainant.” Resp’t Br. at 30. While there is
no doubt that the PSM standard is a performance standard, which allows an
employer some discretion as to how a particular hazard should be addressed,
“there is no indication in the language of the PSM standard or its regulatory
history that OSHA meant to give to employers, at their sole discretion, the
option of excluding equipment from the standard’s coverage.” Delek, 25 BNA OSHC 1365 at *9. Thus, the interpretive letter states that if
an employer makes a determination that a component
failure in the utility system cannot affect, cause, or interfere in the
mitigation of a potential release, the employer must be able to proactively
demonstrate why the utility system is no longer a part of a covered process.
(Ex. R-83). In other words, the determination must be reasonable. See, e.g., Siemens Energy & Automation, Inc., 20 BNA OSHC 2196 at *1 (No.
00-1052, 2005) (performance standard give a “certain
degree” of discretion but meaning of standard interpreted in light of what is
reasonable).
Respondent
argues that it conducted the analysis of the Wickes as described above and
concluded that the boiler could not cause or interfere in mitigating the
consequences of a catastrophic release.
Specifically, Respondent points to the testimony of Jackson, the PSM
Manager, who states that he considered the failure of the Wickes and other
aspects of the 225-pound steam system as part of his analysis of a loss of heat
to a covered process. (Tr. 1606–1610).
Jackson and Rains concluded that a failure of the Wickes would not have
such an effect because the other boilers that sourced the steam system could
produce sufficient steam to continue operations at the
refinery and that any temporary effects would only impact product quality. (Tr.
1671–72, 1718–1725). Respondent’s expert
testified similarly. (Tr. 2066–2067).
This
determination, Respondent contends, was reinforced by the record evidence,
including: (1)
the Wickes was taken offline once per year for an annual inspection; (2) the
refinery had redundancies in place such that only two of the four utility
boilers were needed to contribute steam to the header. (Tr. 1719–1720). Further, Respondent also argues that the
snuffing steam system, as used in the Alky heater firebox, was only for small
fires and that no evidence was presented to show that such a fire could cause a
catastrophic release of HHC.
The
Court has a different perspective on the record evidence, as well as the
sufficiency of Respondent’s determinations regarding the impact of a loss of
steam on PSM-covered processes. First,
the PHA/Hazop analysis performed by Jackson was,
according to his testimony, focused on the impact of too little or too much
heat being supplied by the Wickes and how that could cause a loss of
containment. (Tr. 1606–1607). In
response to a question regarding whether he was confident that he considered a
loss of steam in all PHAs for covered processes, Jackson stated, “I’m
confident in that based on the questions you have to ask
yourself in a HAZOP of too much heat or too little
heat. And steam provides heat to our processes.” (Tr. 1607; Ex. R-93, R-94). The problem, however, is that the functions
described above are not limited to supplying heat to a particular
process. It is also used to snuff out fires, remove HHCs from the FCC
riser in emergencies, and purge HHCs from furnace fireboxes during the lighting
process. Based on the Court’s review of the PHAs, there is no indication that
the impact on these safety functions was considered.
Second,
in an attempt to downplay the significance of the
Wickes, Raines noted that it is one of four boilers on location at the refinery
and that there is a redundancy system built in to reduce the refinery’s
reliance on any one boiler. (Tr. 1719). While this may be the case, there was no
independent evidence, by way of PHAs or SOPs, to indicate that the system was
designed this way. (Tr. 1764). Further,
Respondent’s employees testified that the Wickes was the workhorse of and a main
contributor to the plant’s steam system. (Tr. 171, 242–43). Respondent lent credence to that
characterization by choosing the Wickes as the boiler of choice for the
turnaround. Respondent recognized that
problems with the Wickes and connected steam system could lead to process
upsets. While those upsets likely had
the most direct impact on product quality, there was also testimony that such
upsets may also impact the use of certain safety measures associated with the
steam system. (Tr. 238, 360, 1037, 1761, 1765).
That the safety measures associated with a covered process could be
affected by a boiler system upset is alone sufficient
to warrant finding a connection sufficient to establish the inapplicability of
the exception. See Delek,
25 BNA OSHC 1365 at *8 (citing favorably to OSHA Interpretation Letter stating
“proper safe functioning of all aspects of a process, whether they contain
[HHC] or not, are important for the prevention and mitigation of catastrophic
releases”). Just because a redundancy
system is built in does not remove a particular boiler
from the ambit of the standard. See id. (“OSHA’s position is that any engineering control, including
utility systems, which meets the above criteria must be . . .
inspected/tested/maintained per OSHA PSM requirements.”). The key is the connection to the process, and
whether a failure in that connection could have an impact on a potential
catastrophic release of HHCs. As testified
to by Rains, certain process upsets, if left alone for a long enough, can cause
a catastrophic release. (Tr. 1761). For
example, what if the emergency shutdown system in the FCC Riser cannot be
activated because the purported steam redundancy system failed? Under such a set of circumstances, surely it
would be reasonable to conclude that a failure at the Wickes would have an
impact on the system’s ability to control, prevent, and/or mitigate a
catastrophic release.
As
noted above, the Commission in Delek determined that the PPU in the control room was
governed by the PSM standard. The PPU
did not have a direct connection to the process; rather, it was a control to
prevent the spread of harmful gases that were a result of the FCC process,
which could, in turn, prevent the control room from managing the refining
process. Delek,
25 BNA OSHC 1365 at *8. The connection
of the Wickes to various processes throughout the plant was not nearly so
attenuated. The Wickes provided steam,
which was used directly on the various PSM-covered processes throughout the
plant in both a production- and safety-related capacity. In its safety-related
capacity, the steam provided by the Wickes served to control, prevent, and/or
mitigate catastrophic releases through its use as a snuffing and purging agent.
While such uses may not be a complete or sufficient
control in and of themselves, the Court finds that such a connection is
sufficient to bring the Wickes under the umbrella of the PSM standard.
At a very
basic level, the Wickes connected to PSM-covered processes on the front and
back end: It is fueled by off-gases from
the FCCU and Alky, and, in turn, it supplies steam to those same processes. The explosion in this case provides a clear
example of how physical connections between processes can lead to a
catastrophic release. There was no
independent, automatic control that could stop the flow of fuel to the Wickes
during the lighting process; the explosion that resulted from flooding the
firebox was only mitigated by the fact that CT Walker happened to notice the
overflow of fuel. Independent of that,
there was nothing to impede the flow of fuel to the system (although it was
natural gas, the same event could have occurred with RFG). Further, to suggest,
as Respondent has, that this was a worst case scenario
disregards the fact that, but for CT Walker intervening, gas would have
continued to flow to the firebox even after the explosion. In fact, Stephenson,
the unit supervisor, testified that gas was released into the atmosphere as a
result of the explosion, noting a smell of gas in the air. (Tr. 667).
In light of the foregoing, the Court finds that the Wickes boiler is a
critical aspect of multiple PSM-covered processes, is not subject to the
workplace fuels exception, and, therefore, was properly cited under the PSM
standard under a theory of interconnection.
2.
Proximity to a Covered Process
An
additional basis for coverage urged by Complainant is that the Wickes,
independent of its connections to covered processes, was “located such that a
highly hazardous chemical could be involved in a potential release”. 29 C.F.R.
§ 1910.119(b). As a result of the
explosion, there was significant damage to surrounding equipment, including
piping and valves; and the ladder and platform, which were attached to the
Wickes, were blown across the street and hit the operator shelter. (Tr. 152,
156–57, 364, 367; Ex. C-62 at 3, 4, R-110 at 19–20). Complainant contends that, in addition to the
damage described above, parts of the FCCU process lines, including the Intercat loader and process pipe racks, could have been
impacted by flying shrapnel. (Tr. 204–206; Ex. C-62 at 15). Based on its location relative to other
aspects of the FCCU process, as reflected in the FCCU Equipment Location Plot
Plan, Complainant’s expert, Johnstone, concluded that the Wickes’ location was
such that it should be considered part of the FCCU process. (Tr. 830; Ex.
C-11). See 29 C.F.R. § 1910.119(b).
Respondent contends that the Wickes is not close enough to any covered process
such that a highly hazardous chemical could be involved in potential release
and, therefore, should not be considered a single process with any adjacent
PSM-covered processes, such as the FCCU. See
id.
Respondent
places significant emphasis on the way this particular
explosion occurred to support its argument that the Wickes was not
sufficiently close to a covered process to be considered a part of that process
and therefore covered under the PSM standard. In particular,
Respondent points out that the closest aspects of a process that
contains any HHC is the FCCU reactor column, which is approximately 100 feet
away. (Tr. 1214). Noting that there was
no damage to equipment beyond a 10–15 foot radius, and
that no release of HHC occurred, Respondent contends that this “worst-case
scenario” shows that the Wickes could not participate in a catastrophic
release. (Tr. 1726).
The Court
disagrees. As noted by Complainant, the
Wickes was centrally located in the FCCU Equipment Location Plot Plan. (Tr.
829–830, Ex. C-11). Thus, before any
discussion of distance, the Court finds that the Wickes is at least situated
such that it could impact co-located, covered processes, i.e., not in some
remote location. As to distance, it is
true that many of the covered processes are not located within the apparent
radius of the blast zone (10–15 feet) as determined by Respondent; however,
that assessment disregards one very large piece of shrapnel that traveled much
further: the ladder and platform, which were previously attached to the Wickes.
As a result of the explosion, the ladder and platform attached to the east side
of the Wickes were propelled across the street and hit the operator shelter. (Tr.
152, 156–57, 364, 367; Ex. C-62 at 3, 4).
Arendt estimated the distance from the boiler to the shelter was about
40 feet. (Tr. 2071). In addition to the
ladder and platform, the photographs also show a significant amount of
refractory[36]
that had been blasted across the street at the operator shelter. (Tr. 149; Ex.
C-62 at 1–4). Had the ladder and
platform simply been blown in a different direction as a result of the
explosion, perhaps toward the FCCU, it is reasonable to assume a catastrophic
release would have occurred.
The fact
that a catastrophic release from an adjacent PSM-covered process did not actually
occur under these circumstances does not, in any way, establish that such an
eventuality could not occur. See 29 C.F.R. § 1910.119(b) (deeming as
a single process separate vessels “which are located
such that a highly hazardous chemical could
be involved in a potential release”) (emphasis added). The fact that a larger explosion did not
occur is likely attributable to two factors: (1) CT Walker noticing the excessive
flow of fuel to the firebox and directing the operators to shut it down; and
(2) the Wickes was being fueled by natural gas and was not using the RFG
pipeline at the time of the explosion. The Court is mindful of the fact that
the explosion occurred shortly after the order to shut the bypass valve;
however, the valve connecting the RFG and natural gas lines to the Wickes were
within the blast radius, as exemplified in the photographs taken of the west
end of the boiler after the explosion. If the boiler was running on RFG at the
time, damage to the fuel lines or simply an inability to turn off the valve
after the explosion could lead to a catastrophic release. Although Respondent has argued that the RFG
system only contains approximately 1500 pounds of fuel gas at any given time,
as noted before, that assessment does not take into consideration the source of
that fuel—processes such as the FCCU and Alky.
Under normal operations, the Wickes is constantly consuming fuel and the
FCCU and Alky are constantly producing it.
This constant loop of off-gas production and consumption leads the Court
to conclude that Respondent’s attempt to place artificial boundaries on the RFG
process such that a covered process would not be affected is misguided and
disregards the concrete connection that exists between the Wickes and the FCCU,
for example.[37]
Perhaps the
strongest justification for deeming the Wickes to be part of a single process,
and thus PSM-covered, is the potential impact on the control room. As noted
above, the ladder and platform assembly, along with a significant amount of
refractory, were blown across the street and into the operator shelter, which
housed CT Sullivan and CT Walker. In Delek, the
Commission found that the control room (operator shelter) and the controls
associated therewith were part of the overall FCC unit process:
Delek’s refining process includes operating the FCC unit as a whole, and this is done from the FCC unit’s
control room, which is kept in safe working order by the PPU. Without the PPU
providing positive pressure, hydrocarbon vapors could leak into the control room
and—because of the wiring there—cause the type of catastrophic explosion that
the PSM standard was intended to prevent. And short of such an explosion, the
toxic vapors could harm the employees inside the control room, compromising the
management of the refining process. We find, therefore, that the PPU is an
integral part of the overall FCC unit “process.”
25 BNA OSHC 1365 at *9. The key point in the passage above is that an
incident, such as an explosion at the Wickes, which compromises the management
of a PSM-covered process could cause the type of catastrophic event that the
standard was designed to prevent. As
such, the Commission held that even the positive pressurization unit (PPU),
whose connection to a PSM-covered process is even more attenuated than the
control room itself, was governed by the PSM standards. Id. at *8 (“The PPU’s regulation of the control room’s
positive-pressure atmosphere makes the PPU integral to that “control”—and thus
a “control” itself—because, as discussed above, entry of hazardous hydrocarbon
vapors into the room could prevent the control room from managing the refining
process.”).
Throughout
its brief, Respondent was intently focused on whether the putative impacted
process contains a threshold quantity of HHCs.
The Commission made it clear that the scope of the standard’s coverage
is not so narrow. Instead, the
Commission takes a holistic approach to the issue: “[T]he PSM standard does not require
that every part of a ‘process’ come into contact with hazardous chemicals . . .
. [V]iewing the ‘activity’ involving the FCC unit in
its entirety, the PPU is part of a ‘process’ covered by the PSM standard
because it is an integral part of the ‘manufacturing, handling, [and] on-site
movement of [highly hazardous chemicals].”
Id. at *7. The Court sees no difference between the
potential impact on the control room in Delek and the
circumstances presented here, wherein the control room was actually
in the line of fire of the explosion.
Respondent was presented with direct evidence that this could be the
case in 2008 when Respondent performed a blast study for the FCCU as part of
the PHA revalidation of the Wickes. (Ex. R-94).
At that time, Wynnewood determined that the operator shelter adjacent to
the Wickes should be pressurized and hardened to meet overpressure
requirements. (Ex. R-94). In other
words, an integral aspect of a PSM-covered process could be impacted by an
explosion at the Wickes. Nevertheless, Respondent maintained its narrow view
and concluded that additional measures were unnecessary to protect process
vessels and equipment in the FCCU. (Tr. 1610–1611; Ex. R-94).
Based on the
foregoing, the Court finds that the Wickes was located such that an event, like
the explosion that occurred in this case, could affect or cause a catastrophic
release. Accordingly, the Court finds
that the Wickes boiler is subject to the PSM standards under either the
interconnection or proximity theory of coverage.
3.
Respondent Treated Wickes as
PSM-Covered
As further
support for its argument that the Wickes was a PSM-covered process, Complainant
contends that Respondent essentially treated the Wickes as such. Respondent argues that, to the extent it
treated the Wickes as PSM-covered, it only did so as a matter of best practices
and that taking additional precautions should not subject it to liability. The Court notes that while Respondent’s
treatment of the Wickes, in and of itself, is not sufficient
to establish PSM coverage, it undercuts Respondent’s claims that it
conclusively determined that the PSM standard did not apply.
Complainant
identified the following as examples of the Wickes being treated as part of a
PSM-covered process: (1) In 2008, the
Wickes experienced a “hard start”, and the incident report characterized the
event as a “PSM Incident”; (2) the plot plan and various P&IDs for the FCCU
include the Wickes; and (3) Respondent performed Process Hazard Analyses (PHA)
and implemented Management of Change (MOC) procedures on the Wickes. (Exs. C-8 to C-13,
C-18, C-19, C-31, R-110 at 162). Jackson
contends that he inadvertently checked the “PSM Incident” checkbox while
inputting the findings of an hourly employee that assisted in the incident investigation
and that such documentation does not reflect his or Wynnewood’s opinion as to
PSM coverage. Further, Respondent claims
that Jackson determined the Wickes was not PSM-covered when the PHA
revalidation for the Wickes was performed. (Tr. 1616).
Contrary to
Respondent’s arguments, the Court cannot find any documentary evidence that Respondent
made a conclusive determination that the Wickes was not PSM-covered. (Ex. C-4
at 1535) (“If an employer makes this determination, then, the employer must be
able to proactively demonstrate why the utility system is no longer part of the
covered process.”). The problem for
Respondent is that the documentation that would normally be used to establish
coverage does not reflect the sort of proactive demonstration of non-coverage;
rather, as the Court indicated above, the evaluations performed by, or at the
request of, Respondent either lack any affirmative determination of non-coverage
or should have put Respondent on notice of potential coverage. See Section IV.A.ii.2, supra (discussing blast study and
potential impact on adjacent operator shelter).
Instead, Jackson testified that Respondent “must have ruled out” that an
explosion at the Wickes would impact adjacent processes; however, even he
admitted that his conclusion was “pure speculation”. (Tr. 1620–21).
While it is
true that the PSM standard is performance-based, and thus places the onus on
the employer to determine how to comply, Respondent has not provided a
reasonable basis for its determination.
As noted above, the PHA/Hazop analysis
performed by Jackson was focused on the impact of too little or too much heat
being supplied by the Wickes and how that could cause a loss of containment.
(Tr. 1606–1607). This analysis did not take into account numerous other ways in which a failure of
the Wickes could impact other processes to which it was connected, such as
snuffing steam in the Alky heater’s firebox and emergency steam to the FCC
riser. This narrow view comports with
Respondent’s arguments throughout and fails to account for the Wickes’
significant connections to covered processes throughout the refinery.
B.
Repeat Violations and Successor
Liability[38]
As
a result of the 2012 inspection, Respondent was cited for five repeat
violations, which were issued on March 27, 2013. (Ex. R-1). The citations upon
which the repeat violations were based were issued to Wynnewood Refining while
owned and operated by Gary Williams Energy (GWE), most of which became final
orders of the Commission in April of 2007.[39] (Ex. R-1,
C-28 at 11–12, n.1). Respondent contends
that the present citations are not properly characterized as repeated on three
separate bases. First, Respondent
contends that Complainant failed to comply with its own internal policies
regarding the issuance of repeat citations because more than five years had
elapsed since the underlying citations were issued. Second, Respondent contends that it should
not be held liable for repeat violations that are premised on violations
committed by the previous owner of Wynnewood Refinery. Third, Respondent
contends that the current citations, and the citations which form the basis of
the repeat characterization, are not substantially similar. Based on what follows, the Court finds that
Respondent is not a successor to GWE and that the citations at issue were
improperly characterized as repeated.[40]
Prior
to analyzing the question of successor liability, the Court would like to
briefly address Respondent’s argument that Complainant violated its own
citation policy by issuing the repeat citations more than five years after the
underlying citations were issued. According to Complainant’s Field Operations
Manual, a citation will be issued as a repeated violation if “[t]he citation is
issued within five years of the final order date of the previous citation or
within five years of the final abatement date, whichever is later . . . .” OSHA, Field
Operations Manual, available at https://www.osha.gov/OshDoc/Directive_pdf/CPL_02-00-159.pdf.
Four
out of the five citations were nearly (but not quite) six years old by the time
the current, repeat citations were issued. Respondent contends that, although
there is no statutory restriction on the “look-back” period for repeat
violations, Complainant’s attempt to expand the applicable look-back period
beyond its stated policy creates an “unworkable framework” wherein citations
that were decades old could serve as the basis for a repeat citation.
According
to the Commission, “A violation is properly classified as repeated under
section 17(a) of the Act if, at the time of the alleged repeated violation,
there was a Commission final order against the same employer for a
substantially similar violation.” Hackensack
Steel Corp., 20 BNA OSHC 1387 (No. 97-0755, 2003) (citing Jersey Steel
Erectors, 16 BNA OSHC 1162, 1167–68 (No. 90-1307, 1993), aff'd without
published opinion, 19 F.3d 643 (3rd Cir. 1994)). “[T]he ‘time between violations does not bear
on whether a violation is repeated.” Id.
(citing Jersey Steel, 16 BNA OSHC at
1168).
Just
as Respondent argues here, the employer in Hackensack
argued that the then-current version of the Field Operations Manual (the Field
Inspection Reference Manual) limited repeat citations to a period of three
years after the issuance of the original citation. Id. Citing to previous
decisions, the Commission noted that the FOM and the FIRM “are only [] guide[s]
for OSHA personnel to promote efficiency and uniformity, are not binding on
OSHA or the Commission, and do not create any substantive rights for employers.” Id.
(citations omitted). Accordingly, the
Commission upheld the repeat characterization.
The
Court finds that the enforcement policy of Complainant does not preclude the
issuance of a repeat citation after more than five years. As noted by the Commission in Hackensack, such a policy is only a
guide and does not confer rights upon employers. While Respondent’s concern regarding an
ever-expanding look-back period is legitimate, the citations in this case all occurred
within a six-year period, only slightly longer than the stated policy of
Complainant. Because this Court is bound
to follow the precedent set by the Commission, the Court rejects Respondent’s
argument to vacate the repeat characterization on this basis.
Respondent’s
second argument, however, is far more persuasive. The citations that form the
basis of the repeat violations in this case were issued to GWE, which owned the
Wynnewood Refinery until it was purchased by CVR Energy, Inc. in 2011. (Tr. 1760). Respondent contends that it should not be
held liable for repeat violations that are premised on violations committed by
the previous owner of Wynnewood Refinery.
Complainant argues that Respondent should be characterized as a
successor-in-interest to GWE and therefore liable as a repeat offender under
the Act.
The
Commission addressed the issue of successor liability, albeit in a slightly
different context, in Sharon & Walter
Constr., Inc., 23 BNA OSHC 1286 (No. 00-1402, 2010). In that case, OSHA cited Sharon & Walter
Construction, Inc. (“S&W II”) for repeat violations of the construction
fall protection standards. The
underlying citations were issued to Walter Jensen d/b/a S&W Construction
(“S&W I”). S&W I filed for
bankruptcy and ceased operations approximately six weeks prior to the formation
of S&W II. Walter Jensen was the
sole proprietor of S&W I, as well as the president, director, and solitary
shareholder of S&W II. Both
companies were based in New Hampshire, and both “provided essentially the same
construction services . . . .” Id.
The
starting point of the Commission’s analysis is the language of Section 17(a) of
the Act, which states, “Any employer who . . . repeatedly violates . . . the
Act . . . may be assessed a civil penalty of not more than $70,000 for each
violation.” 29 U.S.C. § 666(a). Applying a plain meaning analysis to the
statute, the Commission found that there is “no language in the statute that
would compel restricting attribution of an employer’s violation history to the
identical legal entity, nor do we find anything that would preclude attribution
of a predecessor’s citation history to a successor.” Sharon & Walter, 23 BNA OSHC 1286 at *7. In other words, the statute is ambiguous in
this context.
The
Commission resolved the ambiguity by looking at the purpose of Section 17(a) in
the context of the Act as a whole. Id.
at 8 (citing Gade v. Nat’l Solid Wastes Mgmt. Ass’n, 505 U.S. 88, 99–100 (1992)). The Supreme Court has held that the Act “is
to be liberally construed to effectuate the congressional purpose”, Whirlpool Corp. v. Marshall, 445 U.S. 1,
10–11 (1990), which is to “assure so far as possible every working man and
woman in the Nation safe and healthful working conditions and to preserve our
human resources.” 29 U.S.C. § 651(b). Thus, to carry out this purpose, the
“enforcement framework creates a deterrent to an employer that might otherwise
ignore potential hazards . . . and an enhanced
deterrent against subsequent infractions ‘once alerted by a citation and final
order.’” Sharon & Walter, 23 BNA
OSHC 1286 at *8 (quoting Dun-Par Eng’d Form Co. v. Marshall, 676 F.2d 1333, 1337 (10th
Cir. 1982)).
Given
its determination that the threat of a repeat characterization is designed as a
deterrent to future bad behavior, the Commission held that “section 17(a) is
most reasonably read to permit, in
appropriate circumstances, the Secretary’s application of a “repeat”
characterization to cases where the employer has altered its legal identity from that of the predecessor employer
whose citation history forms the basis of that characterization.” Id. at *8 (emphasis added). This reading stems from the Commission’s
concern that an overly restrictive application of Section 17(a) “could ‘creat[e] an economic incentive to avoid a penalty by going
out of business and, perhaps, then reincorporating under a different name.’” Id. (quoting Joel Yandell, 18 BNA OSHC 1623, 1625 (No.
94-3080, 1999) (internal citations omitted)).
To the extent that such a possibility could undermine the purpose of the
repeat characterization under 17(a), the Commission found it appropriate to
“allow attribution of a predecessor’s citation history to a successor in
appropriate circumstances.” Id.
At
the urging of the Secretary, and after its own review of relevant case law, the
Commission determined that the substantial continuity test used by the National
Labor Relations Board and the courts “promotes the Act’s goals of ensuring
workplace health and safety by preserving the deterrent effect of a repeat
characterization, and is appropriately adapted to a determination of the
requisite nexus between a successor and predecessor’s violation history for
purposes of ascribing a repeat characterization under the OSH Act.” Id. at *9; see also Nat’l Labor Relations Bd. v. Burns, 406 U.S. 272, 280–81
(1972). The Commission found that “this
test enables us to fully assess the nature and extent of the distinctions and
similarities between a successor and a predecessor based on criteria that are
well-suited to the OSH Act and the facts of each case before us.” Id.
(citing Howard Johnson Co. Inc. v.
Detroit Local Jt. Bd., Hotel and Rest. Employees, 417 U.S. 249, 263, n.9
(1974) (noting successorship cases require an analysis based on “the facts of
each case and the particular legal obligation which is at issue”)). In particular, the Commission noted that the
substantial continuity test focuses on factors that fall into three primary
categories: (1)
nature of the business, (2) jobs and working conditions, and (3)
personnel.
Applying
the foregoing test to the facts of Sharon
& Walter, the Commission found that S&W II was a successor to S&W
I. The nature of the business—roofing
and general construction—did not change. In particular, the Commission noted
that both entities served customers in the same geographic area,
and occupied the same office space and use the same telephone number. Further,
a check drawn on an account belonging to S&W I was used to pay a debt of
S&W II, and S&W II continued performance on a contract entered into by S&W I. Id. at *10. Because the
employing entity and the nature of the business remained “essentially unchanged”,
the jobs and working conditions also remained the same—both companies provided
the same general construction services, which required the same tools and
exposed employees to the same hazards. Id.
As
to the third category—personnel—the Commission noted that “continuity of
personnel who specifically control
decisions related to safety and health is certainly relevant in the context
of the Act because the decisions of such personnel relate directly to the
extent to which the employer complies with the statute’s requirements.” Id. (emphasis added). In that regard, finding that S&W II was a
successor to S&W I was a fairly perfunctory
exercise. As noted above, Walter Jensen
was the sole proprietor of S&W I, and the president, sole shareholder, and
supervisor of S&W II. Accordingly,
“Jensen’s control over decision-making in both companies, including that
related to employee safety and health, weighs heavily in favor of attributing
S&W I’s citation history to S&W II.” Id. Notably, however, the
Commission placed little to no weight on the continuity of nonsupervisory
employees, “because those employees are not responsible for OSH Act compliance
and would not have supervised its implementation.” Id.
In
this case, there is no real dispute as to the first two categories of factors.[41] It is clear that the Wynnewood refinery is
still in the business of refining oil, produces similar products, and services
similar customers. (Tr. 1735–56; Ex. C-16).
Likewise, as testified to by many of Respondent’s employees, the jobs
and working conditions have remained essentially unchanged since Respondent’s
purchase of the refinery from GWE. (Tr. 142).
Thus, the remaining factor to consider is the continuity of personnel
who control the decisions related to safety and health. The Court finds that
this factor, more than the others, is particularly relevant to the issue of
whether a successor should be held liable for the acts of its predecessor.[42]
In
2007, when the original, underlying citations were issued, GWE was the owner of
the Wynnewood Refinery. Nearly all of Respondent’s current and former employees
testified that, upon Wynnewood’s acquisition by Respondent in December 2011,
the new company placed significant emphasis on improving safety and health and
proper implementation of PSM. (Tr. 234, 674–75, 749, 1612). This included changes to policies,
procedures, and the overall culture of safety at Wynnewood Refinery. Some of
the other changes noted by Respondent included: (1) nearly doubling the number
of safety personnel at the refinery, including four new assistant operations
supervisors, who were responsible for procedure development, compliance, PSM,
and occupational safety; (2) new, high-level executives, including the
Executive Vice President for Operations and the Vice President of Environmental
Health and Safety, were more involved in the day-to-day operations, and were
present on a frequent basis to oversee the transition from GWE; (3) a $130
million upgrade to equipment; and (4) more formalized training programs and a
renewed emphasis on “management of change” (MOC) procedures. (Tr. 1701–1703).
In
support of its argument that there was continuity of personnel sufficient to
find successor liability, Complainant points to the following: (1) Dick
Jackson, Respondent’s current PSM Manager, and Darren Rains, Respondent’s
former operations manager,[43]
were members of management before and after the acquisition; and (2) key
personnel and managers, such as Koesler, Howard,
Underwood, and Walker, who were present at the time of the underlying
violations were still working in Zone 2 at the time of the accident. Although these individuals were responsible
for implementing safety and health policies, and may have had input into them,
there was no indication that these individuals were ultimately responsible for
making the decision to change safety and health procedures, PSM policies, and
organizational culture. See Sharon & Walter, 23 BNA OSHC
1286 at *10 (focusing “continuity of personnel” analysis on “who specifically
controls decisions related to safety and health”).
According
to Darin Rains, however, there were significant changes in the management of
Wynnewood. (Tr. 1703). Specifically,
Rains noted that GWE management was less involved in day-to-day operations,
whereas CVR’s corporate management, inclusive of its Vice President of Safety,
Health, and Environment, Chris Swanberg, and
Executive Vice President of Operations, Robert Haugen, were actively involved
in daily operations. This, in and of
itself, is a strong fact in favor of Respondent—new corporate management
responsible for ultimate decision-making in the areas of operations and safety
and health. It should also be noted that
neither of these men, nor any of the other CVR managers, worked for GWE.
In Sharon & Walter, the Commission was concerned with applying
section 17(a) in an overly restrictive manner such that companies could evade
higher penalties by merely changing form, but it is equally problematic to be
over-inclusive. Respondent notes that successor liability has not previously
been imposed under circumstances such as these.
In Sharon & Walter, the
Commission was careful to note that successor liability for repeat violations
should only be applied in “appropriate circumstances” and proceeded to do so
based on a unique set of facts. The
primary concern was manipulation—the Commission repeatedly discussed the
possibility that an employer could avoid liability by “changing its legal
identity for each new project” or “by going out of business and . . . reincorporating
under a different name.” Sharon & Walter, 23 BNA OSHC 1286 at
*8. When viewed through that lens, the
scope of the Commission’s interpretation of section 17(a) becomes clearer: repeat violations based on successor liability
would be appropriate when the cited employer “altered its legal identity from that of the predecessor employer . . . .” Id. (emphasis added). In other words, the Commission sought to
prevent manipulation of the system, not to expand liability.
The
purpose of a repeat violation is to deter an employer from committing
violations by drastically increasing the penalty for subsequent, substantially
similar violations. Dun-Par, 676 F.2d at 1337.
This implies that the employer was responsible for the underlying
violation. While higher penalties are a
deterrent, irrespective of the basis therefor, there must be some justification
for increasing the penalties in the first instance. Respondent did not commit the underlying
violations in this case. Drastically
increasing the penalty for a violation that occurred on someone else’s watch
does not deter future misconduct because there was no past misconduct to deter.
Complainant
seeks to circumvent this problem by arguing that CVR-WR was on notice of the
underlying violations when it acquired Wynnewood from GWE-WR and is therefore
responsible for any obligations stemming from them. Without citing case law, Complainant attempts
to analogize economic obligations acquired in the purchase of a business and
OSHA citations that were incurred by the former owner, stating:
If
the new employer has notice of the obligation, then the price paid for the
business will reflect that knowledge and it is fair to impose the obligation on
the new employer. In the OSHA context,
notice shows culpability on the part of the new employer and supports
imposition of a higher repeat penalty because the new employer had notice of
the violative condition but failed to prevent its occurrence.”
Compl’t Br. at 28. First, a
prior OSHA citation, which has become a final order of the Commission, is not
an outstanding obligation. Second, notice does not, on its own, equal
culpability as argued by Complainant.
The
importance of notice can be seen in the distinction between a willful violation
and a repeat violation. A willful violation is punishment for what an employer knew before it committed a violation. See,
e.g., Sharon & Walter, 23 BNA
OSHC 1286 at *5 (citing Kaspar Wire Works, Inc., 18 BNA OSHC 2178,
2181 (No. 90-2775, 2000) (“The hallmark of a willful violation is the employer’s state of mind at the time of
the violation-an ‘intentional, knowing, or voluntary disregard for the
requirements of the Act or … plain indifference to employee safety.’”)
(citations omitted)). A repeat violation
is punishment for what an employer did
(or did not do) in the past. See Dun-Par Eng’d
Form Co. v. Marshall, 676 F.2d 1333, 1337 (10th Cir. 1982) (“Once an employer has been cited for an
infraction under a standard, this tends to apprise the employer of the
requirements of the standard and to alert him that special attention may be
required to prevent future violations of the standard.”). Thus, in the context of successor liability, the
Court must be mindful of who we are
holding responsible and what we are
holding them responsible for.
The
threat of increased penalties for subsequent violations only makes sense if the
same employer was responsible for the underlying past violation. In the case of Sharon & Walter, though the “employer” was different in name,
the controlling entity (Walter Jensen) did not change. What Complainant proposes—holding CVR-WR, a
separate and distinct purchasing entity, responsible for what GWE-WR did in the
past—expands repeat liability beyond what the Commission envisioned when it
decided Sharon & Walter. Based on the facts and law discussed above,
the Court holds that the citations issued to Respondent were improperly
characterized as repeat.
C.
The PSM Inspection – Docket No. 13-0791
– Inspection No. 663538
i.
Applicable Law
To
prove a violation of an OSHA standard, Complainant must prove, by a
preponderance of the evidence, that: (1)
the cited standard applied to the facts; (2) the employer failed to comply with
the terms of the cited standard; (3) employees were exposed or had access to
the hazard covered by the standard, and (4) the employer had actual or
constructive knowledge of the violative condition (i.e., the employer knew, or with the exercise of reasonable
diligence could have known). Atlantic
Battery Co., 16 BNA
OSHC 2131 (No. 90-1747, 1994).
A
violation is “serious” if there was a substantial probability that death or
serious physical harm could have resulted from the violative condition. 29
U.S.C. § 666(k). Complainant need not
show that there was a substantial probability that an accident would actually occur; he need only show that if an accident occurred,
serious physical harm could result. Phelps Dodge Corp. v. OSHRC, 725 F.2d
1237, 1240 (9th Cir. 1984). If the
possible injury addressed by a regulation is death or serious physical harm, a
violation of the regulation is serious. Mosser Construction, 23 BNA OSHC 1044
(No. 08-0631, 2010); Dec-Tam Corp.,
15 BNA OSHC 2072 (No. 88-0523, 1993).
ii.
Citation 1, Item 1
Complainant alleged a serious
violation of the Act in Citation 1, Item 1 as follows:
29 CFR 1910.119(d)(3)(i)(F): Process
safety information pertaining to the equipment did not include the design codes
and standards employed:
The employer does not ensure process
safety information pertaining to the equipment includes design codes and
standards employed. In the Zone2/CAT
Wickes Boiler Area the employer does not ensure process safety information
pertaining to the equipment included the design codes and standards employed
such as the National Fire Protection Association (NFPA) Standard 85, Boiler and
Combustion Systems Hazard Code, and ASME CSD-1, sections CF-210 & CF-330,
and ASME Section VI for the Wickes boiler burner and gas train exposing
employees to fire and explosion hazards from potential releases of fuel gas and
other flammable liquids or gases.
The
cited standard provides:
Information pertaining to the equipment in the process. (i) Information pertaining to the
equipment in the process shall include . . . [d]esign
codes and standards employed . . . .
29 C.F.R. § 1910.119(d)(3)(i)(F).
Complainant
alleges that Respondent failed to include design codes and standards in the
process safety information (PSI) for the Wickes boiler and the associated gas
train. In particular,
Complainant notes that it requested such information during the
inspection and that none was provided.
Further, Howard, the former Zone 2 Supervisor, stated that he did not
know what design codes and standards were employed with respect to the Wickes
and gas train. (Tr. 703). Respondent
contends that Complainant failed to establish that the design codes cited were
applicable to the Wickes and gas train, noting NFPA 85 has a retroactivity
provision that excludes equipment “that existed or were approved for
construction or installation prior to the effective date of the code.” (Ex.
R-130 at 85-11). Respondent also notes
the boiler passed inspection by the Oklahoma Department of Labor and was
approved for operation one month prior to the explosion.
As
repeatedly noted by Respondent, and echoed by Complainant’s expert, Johnstone,
this is a performance standard. (Tr. 873, 1117). As such, Respondent is entitled to elect
which design codes and standards they wish to employ with respect to a particular piece of equipment. (Id.). Nevertheless, Respondent
must still make a choice as to which standards or codes to apply. Herein lies the problem. Regardless of whether design codes and
standards identified by Complainant in this citation item are specifically
applicable to the Wickes and its gas train, Respondent failed to identify any design codes or standards in their
PSI. (Tr. 703, 874, 1118). Further,
according to Johnstone, Respondent’s P&IDs for the Wickes did not comply
with any known design code or standard. (Tr. 874–75). Although the Wickes may have passed
inspection with the State of Oklahoma—which may or may not have indicated
compliance with certain applicable design codes or standards—this does not
excuse Respondent from its obligations to document that information under the
cited standard. Accordingly, the Court
finds that Respondent violated the terms of the standard.
The
Court also finds that Respondent knew or could have known of the violative
condition. For example, in 2007 the
refinery conducted an investigation of an explosion at
the H-4 boiler. (Ex. C-32). That boiler,
similar to the Wickes, was designed and installed
prior to the purported grandfathering date of NFPA 85. (Ex. C-32 at 4). Nonetheless, the investigation report noted
that consideration should be given to the requirements of NFPA 85 with respect
to the operation sequence of the H-4 boiler. (Id. at 13). This incident
highlighted the importance of applying consensus design codes and standards to
a PSM-covered process and should have placed Respondent on notice that such
information would be equally applicable to the other boilers in its facility.
Further, the
H-4 incident illustrated the impact of failing to utilize and apply such information
to PSM-covered processes; namely, that without having proper PSI, employees are
exposed to explosion and fire hazards. (Tr. 876). According to CSHO Hartung, “When you define
the design code and standard, that sets forth the standard to which all
engineering, design, installation and use and maintenance of that equipment
will be conducted as it’s in the process, as it’s installed, again as it’s
engineered and maintained.” (Tr. 1119).
The purpose of the cited standard is to “enable the employer and the
employees involved in operating the process to identify and understand the
hazards posed by those processes involving highly hazardous chemicals.” 29
C.F.R. § 1910.119(d). If no standard or
code is defined, there is no basis upon which to determine whether a particular
aspect of the process “is appropriate for the operation and that it meets
appropriate standards and codes . . . .” 57 Fed. Reg.
at 6374. Without such a basis, the
ability to identify and understand the hazards of a process is reduced, thereby
exposing employees to potential injury from explosion or fire.[44] As indicated by the incident in this case, as
well as the incidents pre-dating the Wickes explosion, exposure to fire and
explosion hazards can cause serious injury and/or death.
Based on the
foregoing, the Court finds that Respondent violated the standard and that the
violation was serious. Accordingly,
Citation 1, Item 1 is AFFIRMED as a serious violation of the Act.
iii.
Citation 1, Items 2(a), (b), and (c)
Complainant
alleged three serious violations of the Act in Citation 1, Item 2, subparts (a),
(b), and (c). Given their similarity,
all three items will be addressed together.
Complainant’s allegations with respect to Item 2(a) are as follows:
29 CFR 1910.119(e)(3)(i): The process
hazard analysis did not address the hazards of the process:
The employer does not ensure the
process hazard analysis addresses the hazards of the process. In the Zone2/CAT Wickes Boiler Area the
employer did not ensure the 1992 and 2008 Process Hazard Analyses addressed the
hazards of the process where employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or
gasses for hazards of the process such as but not limited to:
a)
Failure to purge or adequately purge
the boiler firebox prior to lighting the burner pilot.
b)
Loss of burner pilot during the
initial start-up of the boiler burner.
c)
Loss of burner flame.
d)
High or prolonged fuel gas flow to
the burner without a pilot or flame present.
e)
Failure of the burner to light.
The cited standard provides that
“[t]he process hazard analysis shall address . . .
[t]he hazards of the process. 29 C.F.R.
§ 1910.119(e)(3)(i).
Complainant’s allegations regarding Item
2(b) are as follows:
29 CFR 1910.119(e)(3)(iii): The process hazard analysis did not address
the engineering and administrative controls applicable to the hazards and their
interrelationship, such as, appropriate detection methodologies to provide
early warning of releases:
The employer does not ensure the
process hazard analysis addresses the engineering and administrative controls
applicable to the hazards and their interrelationship, such as, appropriate
detection methodologies to provide early warning of releases. In the Zone2/CAT
Wickes Boiler Area the employer did not ensure the 1992 and 2008 Process Hazard
Analyses addressed the engineering and administrative controls applicable to
the hazards and their interrelationships such as the appropriate methodologies
to provide early warning where employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or
gasses for occurrences such as but not limited to:
a)
Failure to purge or adequately purge
the boiler firebox prior to lighting the burner pilot.
b)
Loss of burner pilot during the
initial start-up of the boiler burner.
c)
Loss of burner flame.
d)
High or prolonged fuel gas flow to
the burner without a pilot or flame present.
e)
Failure of the burner to light.
The
cited standard provides:
The process hazard analysis shall
address . . . [e]ngineering and administrative
controls applicable to the hazards and their interrelationships such as
appropriate methodologies to provide early warning of releases. (Acceptable
detection methods might include process monitoring and control instrumentation
with alarms and detection hardware such as hydrocarbon sensors.)
29 C.F.R. § 1910.119(e)(3)(iii).
Complainant’s allegations regarding
Item 2(c) are as follows:
29 CFR 1910.119(e)(3)(iv): The
process hazard analysis did not address the consequences of failure of
engineering and administrative controls:
The employer does not ensure the
process hazard analysis addresses the consequences of failure of engineering
and administrative controls. In the Zone2/CAT Wickes Boiler Area the employer
did not ensure the 1992 and 2008 Process Hazard Analyses addressed the
consequences of failure of engineering and administrative controls where
employees were exposed to fire and explosion hazards from potential releases of
fuel gas and other flammable liquids or gasses for occurrences such as but not
limited to:
a)
Failure to purge or adequately purge
the boiler firebox prior to lighting the burner pilot.
b)
Loss of burner pilot during the
initial start-up of the boiler burner.
c)
Loss of burner flame.
d)
High or prolonged fuel gas flow to
the burner without a pilot or flame present.
e)
Failure of the burner to light.
The cited standard provides that
“[t]he process hazard analysis shall address . . . [c]onsequences
of failure of engineering and administrative controls . . . .” 29 C.F.R. § 1910.119(e)(3)(iv).
Respondent’s
primary argument with respect to the foregoing citation is that the PSM
standard does not apply, which the Court disposed of earlier in Section IV.A, supra.
Its secondary argument is that, insofar as the Wickes is subject to PSM
because of its connection to other covered processes, Complainant was required
to prove that the PHAs for the Alky and the FCCU failed to contain the
information alleged to be missing from the Wickes PHA. Resp’t Br. at 53. This argument is
undercut by the fact that Respondent performed a PHA on the Wickes on two
separate occasions—initially in 1992 and a revalidation in 2008.[45]
Insofar as it performed PHAs on the Wickes, Respondent effectively treated it
as a part of a process subject to the PSM standard.
A
review of the disputed PHAs reveal that neither contains an analysis of the
hazards identified in the foregoing citation items. (Ex. C-18, C-19). Paul Howard, who participated in both the
initial analysis and subsequent revalidation, testified that both PHAs should
have identified hazards, the controls, and consequences of failure, but failed
to do so. (Tr. 720–23). The Court agrees
and finds that the terms of the standard were violated.
The
Court also finds that Respondent knew or could have known of the hazard. The
PHAs, which were performed under the ownership of GWE-WR, were available to
Respondent and its employees, and the 2008 PHA was effective for a period of
five years. See 29 C.F.R. §
1910.119(e)(6). Respondent could have
known, with the exercise of reasonable diligence, that the PHA for the Wickes
was deficient. These deficiencies,
especially as they relate to the accident that occurred in this case, clearly
exposed Respondent’s employees to fire and explosion hazards that were
otherwise left unexplained and un-analyzed in the Wickes PHA. Without a complete understanding of the
hazards associated with a process, the impact of administrative and engineering
controls, and the consequences of failure of those controls, employees were
exposed to hazards that were potentially unknown and, if known, may not have
been properly addressed with effective engineering and administrative
controls. As noted above, fire and
explosion hazards can lead to serious physical injuries, including (as happened
in this case) death.
The
Court finds that Complainant established a serious violation of the standards
cited above. Accordingly, Citation 1,
Items 2(a), (b), and (c) are AFFIRMED as serious violations of the Act.
iv.
Citation 1, Items 3(a) and (b)
Complainant
alleged two serious violations of the Act in Citation 1, Item 3, subparts (a)
and (b). Given their similarity, both items
will be addressed together.
Complainant’s allegations with respect to Item 3(a) are as follows:
29 CFR 1910.119(f)(1)(i)(A): The
employer’s written operating procedures covering the steps for each operating
phase did not address initial startup.
The employer’s written operating
procedures covering the steps for each operating phase do not address initial
startup. In the Zone 2/CAT Wickes Boiler
Area the employer did not ensure the written operating procedures covered steps
for each operating phase including initial startup such as but not limited to:
a)
The length of time in which the gas
can flow to the boiler burner without the burner lighting.
b)
A description of how much the main
gas valve can be opened or what the maximum pressure should/can be at the inlet
to the burner.
c)
The length of time the firebox is to
be purged of gas prior to or after a failed burner lighting attempt.
d)
The maximum gas pressure at the
inlet to the gas train on the boiler burner.
e)
The use of natural/purchased gas
versus refinery gas.
Employees were exposed to fire and
explosion hazards from potential releases of fuel gas and other flammable
liquids or gasses.
The cited standard states, “The
employer shall develop and implement written operating procedures that provide
clear instructions for safely conducting activities involved in each covered
process consistent with the process safety information and shall address at
least the following elements: . . . Initial Startup.” 29 C.F.R. § 1910.119(f)(1)(i)(A).
Complainant’s allegations with respect
to Item 3(b) are as follows:
29 CFR 1910.119(f)(3): The operating procedures were not reviewed as
often as necessary to assure that they reflect current operating practice,
including changes that result from changes in process, chemicals, technology,
and equipment, or changes to facilities:
The employer does not ensure
operating procedures are reviewed as often as necessary to assure that they
reflect current operating practice, including changes that result from changes
in process chemicals, technology, and equipment, or changes to facilities. In the Zone 2/CAT Wickes Boiler Area the
employer did not ensure written operating procedures were reviewed as often as
necessary to assure that they reflected current operating practice. Identified errors include but not limited to:
a)
The amount of time the firebox is
purged prior to attempting to light the pilot or after a failed burner lighting
attempt.
b)
The level the gas control valve
bypass is to be opened.
c)
The time the gas control valve
bypass valve is allowed to open before the burner
lights.
Employees were exposed to fire and
explosion hazards from potential releases of fuel gas and other flammable
liquids or gasses.
The cited standard states, “The
operating procedures shall be reviewed as often as necessary to assure that
they reflect current operating practice, including changes that result from
changes in process chemicals, technology, and equipment, and changes to
facilities. The employer shall certify annually that these operating procedures
are current and accurate.” 29 C.F.R. § 1910.119(f)(3).
In response to Complainant’s allegations, Respondent
contends that: (1) it was not feasible to provide precise instructions on how
far or how long to open the gas bypass valve because the fuel composition
changes from hour to hour; (2) the instructions provided to operators during
formal and on-the-job training were consistent (e.g., “no more than a spoke”, “no
longer than a minute”) and that the operators failed to comply; and (3) the
remaining deficiencies identified by Complainant are irrelevant to the boiler
startup.
As
to providing precise instructions regarding the bypass valve, the Court
disagrees that doing so would be infeasible. According to Respondent’s Formal
Incident Report, an earlier iteration of the standard operating procedures
(SOP) for lighting the Wickes included fairly precise
instructions for opening the bypass valve, whereas the most recent version did
not.[46]
(Ex. C-30 at 13). Notwithstanding its
obligation under a 2008 settlement agreement to update its SOPs, Respondent
failed to include all of the earlier startup steps in
its revised SOP. (Id. at 7). Thus, Respondent’s own investigation revealed
as a root cause of the explosion that the “SOP Did Not Include Critical Safety
Information from Earlier Startup Procedures”. (Id.). In addition, any claim
that providing precise instructions was infeasible is belied by the same
report, wherein the investigation team “was able to identify other similar
equipment SOPs in Zone 2 that had more specific instructions on how long a
lighting procedure was to be performed until aborting a task, and contained
specific hazard warnings about the consequence of not aborting the task if
light-off failed in a short time period.” (Ex. C-30 at 8). Further, the fact that Respondent’s employees
may have received training consistent with the earlier procedure does not
obviate the need to include such steps in the updated, written procedures. In fact, the effect of Respondent’s failure
to do so is reflected in the testimony of the witnesses, each of whom gave a
slightly different description of how much to open the valve and for how long.
(Tr. 116–17, 215, 335, 353, 453, 518). Accordingly,
the Court rejects Respondent’s argument as to infeasibility of including more
precise instructions on the bypass valve and finds a violation on this basis.
As
to the remaining deficiencies, first, it is not clear that the gas pressure at
the bypass valve is irrelevant as Respondent suggests. Merely because the pressure valve is not in
an operator’s line of sight does not render that indicator unimportant. According to Respondent’s Incident Report,
“Normal operation data indicated that a 3–5 psig
burner pressure is in the range to support normal operation of the boiler . . . . This data
also shows that the burner pressure should have been between 1.4 to 1.8 psig.” (Ex. C-30 at 12).
The Report indicates that “high burner pressure resulted in a fuel
velocity that far exceeded the condition necessary to light the burner.” (Id.).
To the extent that data available to Respondent revealed a connection
between fuel pressure and the ability to light the burner, Respondent should
not be absolved of including that information as a step in the lighting process
merely because the operator turning the bypass valve does not have pressure
information in his line of sight.
Second,
the Court agrees with Respondent that the SOPs for the Wickes indicate that the
firebox should be purged for 30 minutes prior to lighting the pilot and that
such would be the case for starting the boiler regardless of whether it is the
initial lighting attempt or an attempt to light the boiler after a failed
attempt. (Ex. C-30 at Exhibit 44).
However, the problem with the procedures in place at the time of the
explosion was that they did not account for a failed lighting attempt at any
step in the process.[47] (Id.). Thus, there was no indication, in the SOPs at
least, as to what the next step in the process would be if the lighting attempt
failed.
Third,
Respondent’s argument that the process would be the same irrespective of
whether the Wickes was being lit by natural gas or refinery fuel gas is equally
unavailing. Respondent contends that there are only slight differences between
the flame speed and flammable range of natural and refinery fuel gas and that
such differences were not significant enough to affect the boiler’s startup
procedures. Further, Respondent contends that due to the variability of the
hydrogen content of RFG, it is infeasible for Respondent to create different
SOPs for every potential iteration of fuel gas. According to Respondent’s
Incident Report:
Differences in the flame speed and
flammable range of natural gas versus hydrogen coupled with the high velocity
of fuel and air flowing through the burner ring would prevent the fuel/air
mixture from being lit by the pilot.
Natural gas has a flammable range of 5% to 15% and a flame speed of approximately
1.0 feet/sec. Hydrogen has a flammable range of 4% to 75% and a flame speed of
approximately 10 feet/sec. The velocity
of the fuel moving through the burner tip along with the air flow is crucial to
enable the fuel/air mixture to ignite with a stable flame at the burner
tip. The lower flame speed of natural
gas and the higher than normal velocity of both the fuel and air prevented the
mixture from contacting the pilot flame . . . .
(Ex. C-30 at 5). While it may be infeasible to account for
every iteration of fuel gas that comes through the RFG pipeline, the Court
finds that is not the case for pure natural gas. According to the testimony of
Respondent’s employees, the Wickes runs on natural gas alone only during
turnaround activities, during which time the processes which feed the RFG
pipeline are offline. (Tr. 553–54). Given
the investigative team’s finding that the lower flame speed of the natural gas
contributed to the failed lighting, and in consideration of the fact that
lighting the Wickes with natural gas is a unique and seldom-used process, the
Court finds that Respondent’s SOPs should account for it to avoid accidents
such as the one that occurred in this instance.
In
addition to the foregoing, which addresses 1910.119(f)(1), the Court also finds
that Respondent failed to review the SOPs as often as necessary to assure they
reflect current operating practice. See 29
C.F.R. § 1910.119(f)(3). According to
Underwood and Stephenson, both unit supervisors for Respondent, the purpose of
the review of SOPs is to make sure they are accurate and address the hazards
employees are exposed to, set forth applicable operating limits, consequences
of deviation, and steps to correct deviations. (Tr. 576, 651–52). Underwood stated that he personally reviewed
and approved numerous versions of the SOP for lighting the Wickes prior to the
explosion and admitted that the steps discussed above should have been included
in the SOPs that he reviewed and approved. (Tr. 580–82, 679–80). This not only establishes Respondent’s
failure to comply with 1910.119(f)(3) but also illustrates that Respondent knew
or, with the exercise of reasonable diligence, could have known of the
deficiencies in its SOPs.
The
Court also finds that Respondent’s failure to have clear, complete, and
up-to-date procedures exposed its employees to fire and explosion hazards and
that such exposure had the potential to cause serious injury and/or death. (Tr.
1144). Accordingly, Complainant
established its prima facie case.
Respondent
contends that the foregoing failures were not the product of insufficient procedures, but were instead the result of unpreventable
employee misconduct. In
particular, Respondent notes that operators disregarded their training
and opened the valve too far (approximately a spoke-and-a-half) and for too
long (approximately 5 minutes). (Ex. R-110 at 9). Respondent also notes that Willson, the senior operator supervising the lighting
process, instructed Mr. Mann, who was operating the bypass valve, to keep the
valve open even though he was instructed to close it by Koesler.
In
order to prevail on the affirmative defense of unpreventable employee
misconduct, Respondent must prove that: (1) it has
established work rules designed to prevent the violation, (2) it has adequately
communicated those rules to its employees, (3) it has taken steps to discover
violations, and (4) it has effectively enforced the rules when violations have
been discovered. W.G. Yates & Sons, 459 F.3d 604, 609
(5th Cir. 2006).
First, as noted above, Respondent did not have established rules
designed to prevent the violation—there was no specification in the SOP as to
how long the valve should remain open or how much it should be opened. This, in
and of itself, is sufficient to reject Respondent’s
defense. See Stuttgart Machine Works,
Inc., 9 BNA OSHC 1366 (No. 77-3021, 1981) (“Respondent’s inability to
unambiguously state the content of its rule casts serious doubt on whether
Respondent effectively communicated any rule to its employees.”). Without specific outer limits on the process,
there is no sense in which an employee can be said to comply. One of the witnesses testified that the
procedure for lighting was like a dance, of sorts. (Tr. 353). Second, and relatedly, Respondent’s own Incident
Report indicated that, though the operators seemed to generally understand how
to safely light the Wickes, the knowledge demonstration tests revealed “that
there were no specific questions regarding the lighting the burner of the
Wickes boiler as part of the test.” (Ex. C-30 at 13). This indicates a failure to adequately
communicate the rules to employees and is exemplified by the different
characterizations each employee gave regarding how much to open the valve and
for how long.
While
the Incident Report findings indicate that the valve was open far too wide for
far too long, this was not the sole root cause identified nor, in light of the deficient procedures identified above, was
it the product of unpreventable employee misconduct. (Ex. C-30). Lighting the Wickes, as illustrated by the
history of accidents associated with it, clearly requires attention to detail,
whether that is being cognizant of what fraction of a spoke one is supposed to
turn the bypass valve or tracking the amount of fuel flowing into the firebox.
Tracking those all-too-important details is made all the more
difficult by the fact that it is done infrequently—according to most witnesses,
maybe once per year for the annual boiler inspection. Given that set of
circumstances, it was incumbent upon Respondent to ensure, as the law requires,
a set of procedures that accounted for hazards that Respondent knew existed.
That the accident itself may have been caused, in part, by the misguided
actions of an employee does not absolve Respondent of liability for having
insufficient procedures. See Western
Waterproofing Co., Inc., 7 BNA OSHC 1625 (No. 1087, 1979) (“[A]s a general
rule, whether an employer is in violation of the Act does not depend on the
cause of a particular accident.”); Propellex Corp.,
18 BNA OSHC 1677 (No. 96-0265, 1999) (finding judge mistakenly focused on cause
of accident in determining whether a violation occurred). The responsibility of having adequate
procedures is Respondent’s. See Brown
& Root, Inc., 7 BNA OSHC 2074 (No. 16162, 1979) (“The Act . . . places
final responsibility for compliance on the employer. An employer cannot shift
this responsibility to an employee by a work rule that is not effectively
communicated and enforced.”). The failure to have adequate procedures would be
a violation irrespective of whether an accident occurred, especially in light of Respondent’s history of “hard starts”.
Based on the foregoing, the Court finds that Complainant
established a violation of the cited standards and that the violation was
serious. Accordingly, Citation 1, Items
3(a) and (b) are AFFIRMED as serious violations of the Act.
v.
Citation 1, Item 4
Complainant alleged a serious
violation of the Act in Citation 1, Item 4 as follows:
29 CFR 1910.119(l)(3): Employees involved in operating a process and
maintenance and contract employees whose job tasks will be affected by a change
in the process were not informed of, and trained in, the change prior to
start-up of the process or affected part of the process:
The employer does not ensure
employees involved in operating a process and maintenance and contract
employees whose job tasks will be affected by a change in the process are
informed of, and trained in, the change prior to start-up of the process or
affected part of the process. In the
Zone 2/CAT Wickes Boiler Area the employer did not ensure employees whose job
tasks were affected by a change in the process were informed of an trained on the changes prior to startup of the
process. Employees were exposed to fire
and explosion hazards from potential releases of fuel gas and other flammable
liquids or gasses for process changes such as, but not limited to:
a)
Standard Operating Procedures
covering the start-up of the Wickes Boiler burner after the 2008 Wickes Boiler
Explosion.
b)
Use of temporary power to power the
Wickes boiler during the shutdown/turnaround.
The
cited standard provides:
Employees involved in operating a
process and maintenance and contract employees whose job tasks will be affected
by a change in the process shall be informed of, and trained in, the change
prior to start-up of the process or affected part of the process.
29 C.F.R. § 1910.119(l)(3).
Complainant
alleges that Respondent violated the above-referenced standard by failing to
inform and train employees regarding (1) changes made to the SOP for lighting
the Wickes after the 2008 hard start; and (2) the change to temporary power on
the day of the explosion. Respondent contends that Complainant’s allegations as
to the changes made to the SOP in 2008 are time-barred. As regards the use of temporary power,
Respondent submits that all affected employees were informed of the use of
temporary power and that Complainant failed to prove that the procedures for
lighting the boiler with temporary power would be different than with grid
power.
Complainant’s
argument on the topic of the 2008 SOP changes is somewhat confusing.
Complainant asserts that important warnings contained in the SOPs prior to the
2008 explosion did not make the transition to the any set of SOPs that were
approved in subsequent years. Relying on Howard’s testimony, Complainant
concluded that the procedures were deficient because of this failure.
Complainant then goes on to argue that the failure to train on the changes that
occurred in 2008 exposed employees to fire and explosion hazards. This is
confusing for a couple of reasons: (1)
It is not clear whether Complainant is asserting that Respondent violated the
standard because it failed to include important information in the updated
SOPs, which is covered by a different standard (and an allegation already made
by Complainant); and (2) If the failure to include that information is indeed
the basis for the violation, then it would appear that Respondent is being
charged with the responsibility to train employees on changes that should be
included, but are not. To the extent
that the argument is directed at the failure to account for the implementation
of a ¾” bypass valve to reduce fuel flow to the firebox—neither the allegation
contained in the citation item nor Complainant’s brief clarify exactly what is
being asserted—CSHO Hartung admitted that the SOPs were revised in 2010,
meaning that any change made to the procedures in 2008 are no longer effective,
thereby obviating the need to train on such changes. Further, to the extent
that Complainant is alleging that Respondent failed to train employees on the
change in 2008, such an allegation is time-barred. While there is a question
about the viability of the continuing violations theory, such is not applicable
here where Respondent updated its procedures in 2010. In other words, the door was closed on a
continuing violation theory when Respondent was no longer obligated to train on
changes to the process that were no longer a part of the process. In light of the foregoing, the Court finds that Complainant
failed to establish a violation of the standard based on this particular
instance.
However,
as regards the use of temporary power, the Court finds that it was incumbent
upon Respondent to implement MOC procedures and both inform affected employees
of the use of temporary power and train them regarding its use. CT Sutton, who
was responsible for monitoring the control boards during the Wickes lighting,
stated that the previous CT had reported trouble with the electrical components
controlled by a temporary generator. (Tr. 277).
In particular, CT Sutton noted that the use of
temporary power was impacting the functionality of the vanes, which control air
flow to the firebox. (Tr. 279). He also
stated that, based on his experience in construction, generators equipped with
ground faults (as the generator in this case) can trip out for unknown reasons.
(Tr. 487). In the case of the Wickes, he
was concerned that they could lose power to the controls, such as the vanes,
during the lighting process. (Tr. 487–88).
Though he noted that a loss of power would cause the controls to go into
a fail-safe position, he still “thought they ought to be aware of the situation
they had.” (Tr. 488).
Clearly
there was a change in the process; the Wickes boiler was typically run on grid
power. None of the employees who
testified could recall running the Wickes on temporary generator power before.
(Tr. 278, 305, 347–48). While running on
temporary power that day, the CT reported problems controlling the vanes, which
have a direct impact on creating the atmosphere necessary to ignite the burner
and purging the firebox prior to a lighting attempt. (Tr. 278–79). An operator
expressed a safety concern over the consequences of the generator tripping and
loss of power to the controls. Based on the testimony of Respondent’s
employees, the Court finds that Complainant presented sufficient
evidence to establish that the procedures for lighting the boiler had changed
to the extent that Respondent was obligated to inform and train its employees
regarding that change. To a certain
extent, it could be said that Respondent, through the actions of Operator
Sutton, complied with its obligation to inform affected employees of the change
in the process; however, as testified to by the operators and other employees
present that day, they had not received training on those changes. (Tr. 488–90).
The
Court finds that Complainant has established a violation and that it was
serious. There is no question that Respondent knew that temporary generator power
was going to be used that day, and it does not attempt to argue that it
provided training regarding the change in the process or that such a change was
documented, arguing instead that the change was not material. CSHO Hartung testified that the potential
failure of the generator could impact a number of
controls in the process, which could expose employees to potential fire and explosion
hazards. (Tr. 1161–62). Similar concerns
were expressed by Operator Sutton. (Tr. 490).
Accordingly, Citation 1, Item 4, instance (a) is VACATED, and instance
(b) is AFFIRMED.
vi.
Citation 1, Item 5(a) and (b)
Complainant
alleged two serious violations of the Act in Citation 1, Item 5, subparts (a)
and (b). Given their similarity, both
items shall be addressed together.
Complainant’s allegations with respect to Item 5(a) are as follows:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly
and specifically outline the steps for shutting down, isolating, blocking and
securing machines or equipment to control hazardous energy.
The employer does not ensure the
energy control procedures clearly and specifically outline the steps for
shutting down, isolating, blocking and securing machines or equipment to
control hazardous energy. In the Zone
2/CAT Wickes Boiler Area the employer did not ensure the energy control
procedures for the lockout/tagout of the fuel gas and purchased gas supply
lines to the Wickes Boiler burner clearly and specifically outline the steps
for shutting down, isolating, blocking, and securing equipment to control
hazardous energy. Employees were exposed
to fire and explosion hazards from potential releases of fuel gas and other
flammable liquids or gasses.
The cited standard requires energy
control procedures to include “[s]pecific procedural
steps for shutting down, isolating, blocking and securing machines or equipment
to control hazardous energy.” 29 C.F.R.
§ 1910.147(c)(4)(ii)(B).
Complainant’s allegations with respect
to Item 5(b) are as follows:
29 CFR 1910.147(c)(4)(ii)(D): The energy control procedures did not clearly
and specifically outline the requirements for testing a machine or equipment to
determine and verify the effectiveness of lockout devices, tagout devices, and
other energy control measures:
The employer does not ensure the
energy control procedures clearly and specifically outline the requirements for
testing a machine or equipment to determine and verify the effectiveness of
lockout devices, tagout devices, and other energy control measures. In the Zone 2/CAT Wickes Boiler Area the
employer did not ensure the energy control procedures for the lockout/tagout of
the fuel gas and purchased gas supply lines to the Wickes Boiler burner clearly
and specifically outline the requirements for testing a machine or equipment to
determine and verify the effectiveness of lockout devices. Employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or gasses. Employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or
gasses.
This section of the cited standard requires
that energy control procedures to include “[s]pecific
requirements for testing a machine or equipment to determine and verify the
effectiveness of lockout devices, tagout devices, and other energy control
measures.” 29 C.F.R. § 1910.147(c)(4)(ii)(D).
According
to CSHO Hartung, this citation resulted from OSHA’s request to analyze the
valve and natural gas regulator on the Wickes gas train approximately one month
after the explosion. (Tr. 1176, 1285).
Hartung stated that he wanted to see whether the valve was working as it
was intended, as he understood that it had not been tested in a while. (Id.).
Prior to Respondent carrying out the procedure, Hartung reviewed
Respondent’s LOTO procedures. (Tr. 1178).
Based on how Respondent’s employees carried out the procedure of
removing the valve and regulator and his review of Respondent’s lock-out/tag-out
(LOTO) procedures, Hartung cited Respondent for having deficient LOTO
procedures. Respondent contends that the citation is inappropriate because the
valve removal was only done at the request of CSHO Hartung. Further Respondent argues that Complainant
failed to prove that anyone was exposed to a hazard as a result of the alleged
LOTO deficiency.
The standard
requires such LOTO procedures to be “clearly and specifically” outlined. 29
C.F.R. § 1910.147(c)(4)(ii); see also
Gen. Motors, 22 BNA OSHC 1019 (No. 91-2834, 2007). Respondent’s LOTO
procedures were deficient in two respects: (1) the procedures did not identify
specific valves that may have been used to relieve energy and whether those
valves should be open or closed; and (2) the procedures did not have steps for
testing a machine/equipment to determine whether the lockout was effective.
(Tr. 1177, 1182–83; Ex. C-65). Respondent
did not proffer any evidence to contradict these deficiency findings. Accordingly, the Court finds that the terms
of the standard were violated.
Instead of
attempting to establish that its procedures were complete, Respondent contends
that the removal of the valve would not have occurred but for CSHO Hartung’s
request and that Complainant failed to prove that any of Respondent’s employees
were exposed to a hazard as a result of the deficient procedures. The Court agrees with Complainant. The LOTO
procedure, which was in effect prior to the explosion, was deficient
irrespective of when or for what reason it was implemented. CSHO Hartung testified that he requested to
look at the valve approximately five days before it was removed and that he
waited to perform this particular aspect of his
inspection until Respondent was ready to do it. (Tr. 1178). Further, CSHO
Hartung was well within his rights to request the removal of the valve for
inspection, and Respondent was under an obligation to ensure that its LOTO
procedures were adequate for carrying out that job.[48] As Complainant alleged, the procedures were
not adequate.
The Court
also finds that, contrary to Respondent’s argument, its employees were exposed
to fire and explosion hazards. While it
may be the case that the Wickes had been offline since the explosion, there was
no evidence to suggest that it had been completely isolated from other
equipment such that the removal of the valve, which was upstream from the
Wickes, did not involve the potential for release of hazardous energy. Further,
and more importantly, Respondent’s failure to have adequate procedures for LOTO
exposed employees to fire and explosion hazards regardless of whether the
Wickes had been offline. The failure to
have specific LOTO procedures exposes employees to hazards each time those
procedures are implemented, not just in the particular
context in which the alleged deficiencies came to light. Respondent’s LOTO
form, which is presumably used for each LOTO procedure and modified to fit the
particulars of a particular job, does not have a provision for verifying the
effectiveness of energy control measures, nor is there any indication on the
form or its attachment as to the position of the valves (open or closed) that
were supposed to be a part of the process for isolating the bypass valve for
removal. The purpose of the prescribed
procedure is “to guide an employee through the lockout process.” Drexel Chem. Co., 17 BNA OSHC 1908 (No.
94-1460, 1997). Without an adequate
guide for what is clearly a complex lockout procedure, employees may overlook
critical steps in the process, which could result in an unintentional release
of hazardous energy, such as hazardous hydrocarbons. Accordingly, the Court finds that
Respondent’s employees were exposed to a hazard.
The Court
also finds that Respondent knew or, with the exercise of reasonable diligence,
could have known of the hazardous condition.
Not only is it the responsibility of management to ensure that adequate
procedures are in place, but members of Respondent’s management team were
present at the time the procedures were implemented and the bypass valve was removed. Further, during his interview with CSHO
Hartung, Stephenson admitted that the procedure did not indicate whether
certain valves should be open or closed, nor how an employee should go about
verifying that no energy remained in the system. (Ex. R-9).
Based
on the foregoing, the Court finds that Respondent violated the cited standards
and that the violation was serious. Accordingly,
Citation 1, Items 5(a) and (b) are AFFIRMED.
vii.
Citation 1, Item 6(a) and (b)
Complainant
alleged two serious violations of the Act in Citation 1, Item 6, subparts (a)
and (b). Given their similarity, both
items will be addressed together.
Complainant’s allegations with respect to Item 6(a) are as follows:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed
to control the energy to the machine or equipment were not physically located
and operated in such a manner as to isolate the machine or equipment from the
energy source:
The employer does not ensure all
energy isolating devices that are needed to control the energy to the machine
or equipment are physically located and operated in such a manner as to isolate
the machine or equipment from the energy source. In the Zone 2/CAT Wickes Boiler Area the
employer did not ensure all energy isolating devices for the lockout/tagout of
the fuel gas and purchased gas supply lines such as, but not limited to, the
control valves (FC 702 & FC 704) and bleed valves to the Wickes Boiler were
physically located and operated in such a manner as to isolate the machine or
equipment from the energy source.
Employees were exposed to fire and explosion hazards from potential
releases of fuel gas and other flammable liquids or gasses.
The cited standard provides that
“[a]ll energy isolating devices that are needed to
control the energy to the machine or equipment shall be physically located and
operated in such a manner as to isolate the machine or equipment from the
energy source(s).” 29 C.F.R. § 1910.147(d)(3).
Complainant’s allegations with
respect to Item 6(b) are as follows:
29 CFR 1910.147(d)(5)(i): All potentially
hazardous stored or residual energy was not relieved, disconnected, restrained
or otherwise rendered safe after the application of lockout or tagout devices
to energy isolating devices:
The employer does not ensure all
potentially hazardous stored or residual energy is relieved, disconnected,
restrained, or otherwise rendered safe after the application of lockout or
tagout devices to energy isolating devices. In the Zone 2/CAT Wickes Boiler
Area the employer did not ensure all potentially hazardous stored or residual
energy was relieved after the application of lockout or tagout devices such as
between the two control valves (FC 702 & FC 704) on the fuel gas and
purchased gas supply lines to the Wickes Boiler. Employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or
gasses.
The cited standard states, “Following
the application of lockout or tagout devices to energy isolating devices, all
potentially hazardous stored or residual energy shall be relieved,
disconnected, restrained, and otherwise rendered safe.” 29 C.F.R. § 1910.147(d)(5)(i).
According
to Hartung, the basis for Complainant’s allegations with respect to Citation 1,
Item 6 is the same activity as indicated in Citation 1, Item 5; namely,
Respondent’s failure to take the steps that were required to be documented in
the LOTO procedures. (Tr. 1185–87). Respondent does not contend that it complied
with the requirements of the standard, and, indeed, there is no evidence to
suggest that Respondent’s employees complied.
Respondent failed to identify all of the energy
isolating devices that were needed to remove the bypass valve and did not
ensure that hazardous energy had been removed from the system. Not only does this show that Respondent
failed to comply with the standards cited in Items 6(a) and 6(b), but it also
illustrates the importance of specific, well-documented procedures: If Respondent had documented all appropriate
isolation points, how they would be operated, and the manner in which employees
could verify isolation, then such steps would probably not have been missed. See Control
of Hazardous Energy, 54 Fed. Reg. 36644, 36670 (September 1, 1989) (noting the
importance of detailed procedures in light of the need
to follow directions carefully and the number of variables involved in
controlling hazardous energy). Based on the evidence introduced by Complainant
the Court finds that Respondent violated the cited standards.
Instead, Respondent
contends that Complainant failed to establish that employees were exposed to a
hazard. Specifically, Respondent argues
that: (1) Hartung was present during the
valve removal and would not have allowed the removal of the valve to take place
if there was a serious threat of injury; and (2) the removal of the valve took
place one month after the explosion, which means that any residual gas left in
the pipeline would have dissipated by the time the valve was removed. First, CSHO Hartung’s presence during the
removal of the valve has no bearing on whether Respondent’s employees were
exposed to a hazard. There is no indication in the record that CSHO Hartung
knew whether the process being followed by Respondent’s employees was safe at
the time, nor is it clear at what point in time he made the determination that
Respondent’s LOTO procedures were deficient.
Without additional evidence, the Court finds that CSHO Hartung’s
presence on the day of the valve removal does not make it any more or less
likely that Respondent’s employees were exposed. Second, as noted in the Court’s discussion of
Citation 1, Item 5, supra, there was
no definitive indication that the valve or its associated pipes were free of
hazardous energy at the time the valve was removed. The fact that the Wickes had been offline for
approximately 30 days does not, of itself, obviate the need to protect against the
possibility of hazardous releases of energy. Further, though the boiler was
offline, there was no evidence regarding the presence of hydrocarbons in the
upstream process lines, such as the natural gas and RFG lines. As such, there
was still a possibility for a hazardous energy release. Accordingly, the Court
finds that Respondent’s employees were exposed to a hazard.
As noted
above, members of Respondent’s management team were present at the time the
valve was being removed. Accordingly,
the Court finds that it is proper to impute the knowledge of those managers to
Respondent. See Revoli Const. Co., 19 OSHC 1682 (No. 00-0315, 2001) (holding that knowledge of
supervisors is generally imputable to employer).
Accordingly,
Citation 1 Items 6(a) and 6(b) are AFFIRMED.
viii.
Citation 2, Item 1
Complainant alleged a repeat
violation of the Act in Citation 2, Item 1 as follows:
29 CFR 1910.119(d)(3)(ii): The employer did not document that equipment
complies with recognized and generally accepted good engineering practices.
The employer did not document that
equipment in the process complies with recognized and generally accepted good
engineering practices. In the Zone2/CAT
Wickes Boiler Area the employer did not ensure it documented the Wickes boiler
burner and gas train equipment complied with recognized and generally accepted
good engineering practices such as the National Fire Protection Association (NFPA)
Standard 85, Boiler and Combustion Systems Hazard Code, and ASME CSD-1,
sections CF-310 & CF-330, and ASME Section VI. These practices include, but
are not limited to the following equipment:
1.
Flame scanner/fire eyes.
2.
Automatic pilot gas shutoff valve.
3.
Automatic double block (positive
shutoff) and automatic bleed on gas train to the burner.
4.
Burner management system(s) to
control firebox purge, pilot ignition, burner starting, and shutdown.
The
cited standard provides:
The employer shall document that
equipment complies with recognized and generally accepted good engineering
practices.
29 C.F.R. § 1910.119(d)(3)(ii).
Respondent
contends that the foregoing citation is duplicative of Citation 1, Item 1,
which alleged a violation of 29 C.F.R. § 1910.119(d)(3)(i)(F). The present citation is issued under the same
subsection (d)(3), and relates to the process safety
information that Respondent is required to keep with respect to PSM-covered
processes. Id. §
1910.119(d)(3)(iii). A brief comparison of
Complainant’s allegations illustrate that Complainant essentially replaced the
term “design codes and standards” with “recognized and generally accepted good
engineering practices” and cited the exact same design codes and standards,
such as NFPA 85. According to
Complainant, an employer “typically complies with [(d)(3)(iii)] by developing a
list of the standards and codes used at the facility and putting it in the PSI
file.” Compl’t Br. at 52. This was the exact failure alleged by Complainant
in Citation 1, Item 1. See Section IV.C.ii,
supra. If compliance with the standard requires
documentation of RAGAGEP, and documentation of RAGAGEP requires developing a
list of the standards and codes used at the facility, then the Court sees no
meaningful distinction between Citation 1, Item 1 and Citation 2, Item 1. See Capform, Inc., 13 BNA OSHC 2219, 2224 (No. 84-556,
1989) (finding violations duplicative where abatement of one item will
necessarily result in abatement of the other item as well).
The
Court finds that Citation 2, Item 1 is duplicative of Citation 1, Item 1. Accordingly, Citation 2, Item 1 is VACATED.
ix.
Citation 2, Item 2
Complainant alleged a repeat violation
of the Act in Citation 2, Item 2 as follows:
29 CFR 1910.119(f)(1)(ii): The employer did not implement written
operating procedures that addressed operating limits; including at least the
following elements: consequences of
deviation and the steps required to correct or avoid deviation.
a)
In the Zone 2/CAT Wickes Boiler Area
the employer did not ensure the written operating procedures addressed the
operating limits of the process such as, but not limited to:
1.
Minimum/Maximum gas pressure to the
boiler burner gas train.
2.
Minimum and maximum pressure (PI 721
& PI 711) at the fuel gas inlet to the Wickes.
3.
Minimum and maximum fuel gas flow to
the Wickes boiler burner (FI 702).
4.
Minimum and maximum combustion air
flow to the Wickes boiler burner (FI-706).
5.
Composition of the gas flow streams
to the Wickes boiler burner (fuel gas and purchased gas) including BTU content,
lower explosive limits, etc.
b)
In the Zone 2/CAT Wickes Boiler Area
the employer did not ensure the written operating procedures addressed the
consequence of deviation from the safe upper and lower limits of the process such
as, but not limited to:
1.
Minimum/Maximum gas pressure to the
boiler burner gas train.
2.
Minimum and maximum pressure (PI 721
& PI 711) at the fuel gas inlet to the Wickes.
3.
Minimum and maximum fuel gas flow to
the Wickes boiler burner (FI 702).
4.
Minimum and maximum combustion air
flow to the Wickes boiler burner (FI-706).
5.
Composition of the gas flow streams
to the Wickes boiler burner (fuel gas and purchased gas) including BTU content,
lower explosive limits, etc.
c)
In the ZONE 2/CAT Wickes Boiler Area
the employer did not ensure the written operating procedures addressed the
steps to correct or avoid deviation from the safe upper and lower limits of the
process such as but not limited to:
1.
Minimum/Maximum gas pressure to the
boiler burner gas train.
2.
Minimum and maximum pressure (PI 731
& PI 711) at the fuel gas inlet to the Wickes.
3.
Minimum and maximum fuel gas flow to
the Wickes boiler burner (FI 702).
4.
Minimum and maximum combustion air
flow to the Wickes boiler burner (FI-706).
5.
Composition of the gas flow streams
to the Wickes boiler burner (fuel gas and purchased gas) including BTU content,
lower explosive limits, etc.
Employees were exposed to fire and
explosion hazards from potential releases of fuel gas and other flammable
liquids or gasses.
The
cited standard provides:
[O]perating
procedures shall address at least the following elements . .
. . Consequences of deviation;
and Steps required to correct or avoid deviation.
29 C.F.R. § 1910.119(f)(1)(ii).
This
citation item addresses the same subject matter as Citation 1, Item
3—Respondent’s operating procedures. Citation 1, Item 3 addressed the
procedures from the standpoint of initial startup. In this instance, however, Complainant
alleges that Respondent’s operating procedures were deficient with respect to
their discussion of the limits of the process, the consequences of deviation,
and the steps required to correct or avoid deviation. As in Citation 1, Item 3, Respondent does not
contend that it had procedures that addressed the alleged deficiencies; rather,
it argues that: (1) the standard does not apply; (2) this Citation is
duplicative of Citation 1, Item 3; (3) the deficiencies alleged are irrelevant
to the startup of the boiler; and (4) and there is no meaningful difference
between the use of natural gas and RFG.
The
Court has already found that the standard applies. See Section IV.A, supra. The Court has also found that gas pressure
and flow are relevant to startup operations, as subsequent data revealed not
only typical operating limits, but also consequences of deviation. See Section
IV.C.iv, supra.
While that data may not be in the bypass valve operator’s line of sight, that
does not make such information irrelevant; instead, it merely impacts the manner in which that information is conveyed/relayed. Presumably, the availability of such
information would have a fairly direct impact on the
employee who is responsible for operating the valve and the manner in which
they “crack the valve a small amount and for a short period of time”. See Resp’t Br. At
61. As to the composition of the gas
flow streams, as alleged in Complainant’s fifth subpart, the Court has
previously found that a meaningful difference exists between the use of RFG
(which may be mixed with natural gas) and the use of natural gas alone. As to
any other possible iterations of RFG, the Court cannot definitively find that each and every possibility must be accounted for,
considering the variability of hydrogen. (Tr. 1712). There was not sufficient
evidence to indicate whether accounting for such variability was feasible. However, to the extent that safe outer limits
can be imposed, regardless of composition, the fact that RFG can be variable
does not absolve Respondent of its responsibility to account for such
information and variations in its operating procedures.
Respondent
raises a new argument with respect to this item—that it is duplicative of
Citation 1, Item 3. While the standard
cited is part of the same subsection, and addresses similar subject matter
(operating procedures), the citation items address separate parts of the
procedures. If Respondent were to abate Citation 1, Item 3 by updating the
initial startup procedures, such information would not be sufficient
to comply with Respondent’s obligations to consider and document the potential
consequences of deviation and the steps required to correct or avoid deviation.
Thus, the citation items are not duplicative.
With
respect to the issues of knowledge and exposure, the Court hereby incorporates
its findings on the same issues found in Citation 1, Item 3. See Section IV.C.iv. With respect to
characterization, the Court has already determined that Respondent is not
liable for a repeat violation based on the conduct of GWE-WR. However, given that the hazards alleged in
this citation item are the same as those alleged in Citation 1, Item 3, the
findings of which have been incorporated by reference, the Court finds that the
violation was serious.
The
Court finds that Complainant has established a violation of the cited
standard. Accordingly, Citation 2, Item
2 is AFFIRMED as a serious violation of the Act.
x.
Citation 2, Item 3
Complainant alleged a repeat violation
of the Act in Citation 2, Item 3 as follows:
29 CFR 1910.119(g)(2): The employer did not provide refresher
training at least every three years to each employee involved in operating a
process to assure that the employee understands and adheres to the current
operating procedures of the process.
The employer does not provide
refresher training at least every three years to each employee involved in
operating a process to assure that the employee understands and adheres to the
current operating procedures of the process.
In the Zone 2/CAT Wickes Boiler Area the employer did not ensure
refresher training was provided at least every three years to each employee
involved in operating the Wickes Boiler to assure that the employee understood
and adhered to the current operating procedures. Employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or
gasses.
The
cited standard provides:
Refresher training shall be provided
at least every three years, and more often if necessary, to each employee
involved in operating a process to assure that the employee understands and
adheres to the current operating procedures of the process.
29 C.F.R. § 1910.119(g)(2).
According
to Respondent’s training records, within three years of the accident each of
the individuals that were involved in starting the boiler received training and
was tested with respect to various processes in Zone 2 according to job
description. (Exs. C-44 to C-51).[49] According to those documents, Willson, Kellerhall, Operator
Sutton, Mann, and Koesler were required to
“describe/discuss how to start the Wickes boiler.” (Id.). The testing for CTs
Walker and Sutton did not include a question regarding the Wickes startup
procedure, nor did the testing for Smith, who was manning the sight glass. (Id.).
The only question involving the Wickes posed to Smith asked for a
description of “how to switch the fans on the wickes
boiler.” (C-44, C-45). CT Sutton
testified there is no CT-specific testing related to lighting the boiler. (Tr.
325). Respondent’s own Incident Investigation Report determined that the
training did not cover the steps discussed in an earlier version of the SOP,
which Respondent’s investigation team found should have been included in
subsequent versions of the SOP. (Ex. C-30 at 13).
Many of the employees involved in the
explosion testified they had not seen the 2008 version of the Wickes lighting
procedure or the section of the Operations Manual dealing with the Wickes. (Tr.
166–70, 249, 284, 322, 539; Ex. C-35). Those
same employees gave differing descriptions of how to operate the bypass valve,
which controls the flow of fuel to the Wickes. All of them agreed, however, that the
then-current SOPs were deficient because, at the very least, there was no
indication as to how much to open the valve, or for how long. (Tr. 164, 355,
549; Ex. C-33). The Court finds there is
enough deviation between the various descriptions to suggest that training was
inconsistent and deficient.[50] Considering that the bypass valve was
characterized as “very touchy” and that slight movements could drastically
change the fuel flow rate to the firebox (so much so that Respondent previously
attempted installing a smaller valve), Respondent had an obligation to provide
more specific training and instruction to its employees. J.K. Butler Builders, Inc., 5 BNA OSHC 1075 (No. 12354, 1977) (“A review of applicable case law leads
us to define a work rule as an employer directive that requires or proscribes
certain conduct, and that is communicated to employees in such a manner that
its mandatory nature is made explicit and its scope clearly understood.”). Further, nearly all who testified, including
supervisory personnel, agreed that the Wickes lighting procedures were
deficient and should have included the bolded warnings contained in the 2008
lighting procedure. (Tr. 167–71, 549, 710–11, 714; Ex. C-33, C-35).
Based
on the foregoing, the Court finds that Respondent violated the terms of the
standard by failing to provide thorough and consistent training to its employees
such that they were aware of and could execute the lighting procedure. Respondent knew or should have known of the
violation because its managers were responsible for providing training and for
updating, reviewing, and approving the procedures. See Revoli Constr., Co., 19 BNA OSHC 1682
(No. 00-0315, 2001) (holding that actual or constructive knowledge of
supervisory personnel can be imputed to their employer). Further, due to the failure to properly train
its employees, Respondent exposed them to the hazard of fire and explosion,
which, as described above, can cause serious injury and/or death. Accordingly,
Citation 2, Item 3 is AFFIRMED as a serious violation of the Act.
xi.
Citation 2, Item 4
Complainant alleged a repeat violation
of the Act in Citation 2, Item 4 as follows:
29 CFR 1910.119(j)(2): The employer did not establish and implement
written procedures to maintain the on-going mechanical integrity of process
equipment:
The employer does not establish and
implement written procedures to maintain the on-going mechanical integrity of
process equipment. In the Zone 2/CAT
Wickes Boiler Area the employer did not ensure written procedures were
established and implemented for the testing and inspection of the Low
Combustion Air Flow Fuel Gas Shut-off system safeguard. Employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or
gasses.
The
cited standard provides:
The employer shall establish and
implement written procedures to maintain the on-going integrity of process
equipment.
29 C.F.R. § 1910.119(j)(2).
According
to CSHO Hartung, Respondent failed to have an established and written procedure
to maintain the mechanical integrity of process equipment. (Tr. 1060). Specifically, he noted that the refinery had
relied on a breakdown maintenance system, as opposed to a preventative system
of maintenance to ensure equipment was kept in working order. (Tr. 1062). Although he noted that management was
well-versed in process safety management and the need for such a program, they
did not have an established, written procedure in place. (Tr. 1063).
Respondent
contends that Complainant failed to prove a violation of this performance-based
standard, arguing that it had determined that a procedure to ensure that an air
flow switch worked properly was sufficient and that
Complainant is attempting to supplant its own determination of how to properly
implement the requirements of the standard.
Finally, Respondent contends that, insofar as its procedures were not
compliant, any violation should be considered de minimis because the boiler was inspected annually by the State
of Oklahoma. Any deficiency in
procedure, therefore, would not create a hazard to employees because the boiler
had been deemed safe and functional by a third party.
The
Court finds that Complainant has established a violation of the cited
standard. The standard requires
Respondent to “establish and implement written procedures.” 29 C.F.R. §
1910.119(j)(2). The only evidence of a
written procedure was a document that was labeled “Draft” in multiple locations
throughout the document. (Ex. C-58). In
addition, the document contained editing lines, which are associated with the
“Track Changes” function in Microsoft Word. (Id.). There was no testimony
as to whether this draft was established as the proper procedure, nor, based on
the date of the document, does it appear that Respondent was responsible for
generating it in the first place. The only indication that a procedure for maintaining
mechanical integrity even existed appears in the OSHA 1-B Narrative for this
citation item. (Ex. R-16). In that
narrative, Howard told CSHO Hartung that he could not remember whether there
was a written procedure for testing the airflow interlocks, but that there was
a checklist. (Id.). No such checklist was introduced into the
record.
Based
on the foregoing, it does not appear that Respondent had an established and
written procedure for maintaining the on-going integrity of process equipment.
Although CSHO Hartung noted that Respondent was well-versed in PSM and the
necessity of such a program, this does not make up for not having one. Draft procedures, such as the one at issue,
can produce confusion, especially, as here, where the procedures have edit
marks, leaving the operator to guess at whether the procedure they are
attempting to follow is accurate. Without specific procedures, and an
established program to ensure that process equipment is functioning properly,
Respondent exposed its employees to potential explosion and fire hazards. (Tr. 1158). Contrary to Respondent’s argument, it is of little
consequence that a third party verified the functionality of the boiler’s fuel
controls. The obligation to ensure the ongoing mechanical integrity of the
process equipment lies with Respondent. The failure to have a thorough
procedure to examine the process controls, such as safety interlocks, exposed
employees to serious injury because the purpose of those interlocks is to
automatically close down fuel valves in a low airflow
situation. If those interlocks were to fail, or not work as intended, then the
firebox could be flooded, which can lead to an explosion.
Finally,
based on the fact that, at the very least, it had a
draft procedure for testing the interlocks, Respondent knew or could have known
of the violative condition. Accordingly, Citation 2, Item 4 is AFFIRMED as a
serious violation of the Act.
xii.
Citation 2, Item 5
Complainant alleged a repeat
violation of the Act in Citation 2, Item 5 as follows:
29 CFR 1910.119(l)(1): The employer did not establish and implement
written procedures to manage changes to process chemicals, technology,
equipment, and procedures; and, changes to facilities that affect a covered
process:
a)
In the Zone 2/CAT Wickes Boiler Area
the employer did not ensure management of change procedures were implemented to
manage changes to the process operating procedures such as, but not limited to:
1.
The amount of time the firebox is
purged prior to attempting to light the pilot of after a failed burner lighting
attempt.
2.
The amount that the gas control
valve bypass valve is to be opened.
3.
The time that the gas control valve
bypass valve is allowed open before the burner lights.
b)
In the Zone 2/CAT Wickes Boiler Area
the employer did not ensure management of change procedures were implemented to
manage changes to the process equipment, such as the addition of temporary
power to operate the Wickes Boiler.
Employees were exposed to fire and
explosion hazards from potential releases of fuel gas and other flammable
liquids or gasses.
The
cited standard provides:
The employer shall establish and
implement written procedures to manage changes (except for “replacements in
kind”) to process chemicals, technology, equipment, and procedures; and changes
to facilities that affect a covered process.
29 C.F.R. § 1910.119(l)(1).
This
citation item is a companion to Citation 1, Item 4, which addressed the failure
to inform and train employees on the changes to the operating procedure after
the 2008 explosion. The only difference is that the standard cited in the
present citation item addresses Respondent’s obligation to establish and
implement written procedures to manage those changes. Compare 29 C.F.R. § 1910.119(l)(1), with id. § 1910.119(l)(3).
As such, the arguments proffered by Complainant and Respondent are
virtually the same, as is the Court’s ruling.
Complainant
asserts that, with respect to instance (a), Respondent failed to implement an
MOC in response to changes that were made to the equipment following the 2008
explosion; namely, the introduction of a smaller fuel gas bypass valve. (Tr.
713–14; Ex. C-19). Respondent’s
employees testified, and the Court agrees, that changes made to the valve size
required the implementation of new written procedures as the change impacted
the flow rate of fuel. After it was
determined that the smaller valve would not work, Respondent reverted
back to the original 3-inch valve. (Tr. 312). Notwithstanding the change
back to the original, Complainant contends that Respondent’s failure to update
the SOP to also reflect that change constituted a violation because Respondent
failed to update its SOP to reflect this change “for several years.” Compl’t Br. at 63. The problem for Complainant, however, is that
the SOPs were updated to reflect the change back to the 3-inch valve in 2010.
(Ex. C-36). Complainant asserts that the
failure to implement MOC after the 2008 changes is a continuing violation of
the standard. This would only be correct if there had been no subsequent
changes to the procedure; the moment that the procedures were changed, the violation no
longer continued (at least insofar as Respondent was obliged to implement
written procedures for a process that no longer existed). Therefore, as to instance (a), the Court does
not find a violation of the standard.
However,
with respect to instance (b), the Court finds, as it did in Citation 1, Item 4,
that Respondent was obligated to implement written procedures regarding the use
of temporary power to light the Wickes. See
Section IV.C.v.
Since the Court has already addressed the necessity of implementing MOC
with respect to the use of temporary power, it will incorporate by reference
the findings in Section IV.C.v. Based on those findings, Citation 2, Item 5,
instance (a) is VACATED, and instance (b) is AFFIRMED as a serious violation of
the Act.
xiii.
Citation 3, Item 1
Complainant alleged an other-than-serious violation of the Act in Citation 3,
Item 1 as follows:
29 CFR 1910.147(c)(4)(ii)(A): The energy control procedures did not contain
a specific statement on the intended use of the procedure.
The employer does not ensure energy
control procedures contain a specific statement on the intended use of the
procedure. In the Zone 2/CAT Wickes
Boiler Area the employer did not ensure the energy control procedures for the
lockout/tagout of the fuel gas and purchase gas supply lines to the Wickes
Boiler burner contain a specific statement on the intended use. Employees were exposed to fire and explosion
hazards from potential releases of fuel gas and other flammable liquids or
gasses.
The
cited standard provides:
The procedures shall clearly and
specifically outline the scope, purpose, authorization, rules, and techniques
to be utilized for the control of hazardous energy, and the means to enforce
compliance including, but not limited to, the following: (A) A specific statement of the
intended use of the procedure.
29 C.F.R. § 1910.147(c)(4)(ii)(A).
In his brief, Complainant asserts
that, due to the Court’s page-limit restrictions, he did not include a
discussion of the merits of Citation 3, Item 1, instead opting to rest on the
record evidence. Compl’t Br. at 75. The Court has reviewed the transcript for any
mention of Citation 3, Item 1 from Inspection No. 663538, which was issued by
CSHO Hartung, and cannot find a single mention of either the citation item
itself or 1910.147(c)(4)(ii)(A).[51] Although the OSHA 1-B Narrative was
introduced into evidence as a preliminary matter, no subsequent discussion of
that document occurs in the transcript. (Ex. R-18). Without testimony or supporting evidence, the
Court is not in a position to determine whether a
violation of the standard occurred, whether Respondent had knowledge of the
violation, or whether employees were exposed to a hazardous condition. Without such evidence, the Court finds that
Complainant failed meet its burden of proving a violation of the standard. Accordingly,
Citation 3, Item 1 is VACATED.
D.
The Warehouse Inspection – Docket
No. 13-0644 – Inspection No. 778042
i.
Citation 1, Item 1
Complainant alleged a serious
violation of the Act in Citation 1, Item 1 as follows:
29 CFR 1910.23(a)(2): Every
ladderway floor opening or platform was not guarded by a standard railing, or swinging gate or so offset that a person cannot
walk directly into the opening.
The employer does not ensure every
ladderway floor opening or platform was guarded by a standard railing, or swinging gate or so offset that a person cannot
walk directly into the opening. This
violation was observed on or about November 26, 2012, in the Crude and Alky
Units where the employer did not ensure that ladderway floor openings were
guarded by standard railing, or equivalent means, exposing employees to fall
hazards greater than 4 feet above the ground.
The
cited standard provides:
Every ladderway floor opening or
platform shall be guarded by a standard railing with standard toeboard on all exposed sides (except at entrance to
opening), with the passage through the railing either provided with a swinging
gate or so offset that a person cannot walk directly into the opening.
29 C.F.R. § 1910.23(a)(2).
This
citation item is based on CSHO Rambo observing two separate ladderways that
were either left unguarded or had the swing gate tied back with chicken wire in
the Crude and Alky Units. (Tr. 1426–28, 1492; Ex. C-72). Rambo testified he observed contractor
employees working near the missing and/or tied-back swing gates, which exposed
them to a fall of roughly 15–30 feet. (Tr. 1430). Because the exposed employees were
contractors, Rambo determined that Respondent was liable as the correcting or
controlling employer pursuant to OSHA’s Mult-Employer
Worksite doctrine. (Tr. 1435). Rambo
could not determine who had created the condition or for how long it had
lasted. (Tr. 1492–93).
According
to David Johnson, who was a safety specialist for Respondent from 1995 to 2013,
Respondent instituted a ladderway program, as it were, in response to a
previous inspection citation. (Tr. 2129).
In addition, Johnson testified that Respondent hired two contractors for
this specific turnaround “whose sole job was to go with the safety guy and an
operator to every unit, every ladderway in every unit, identify them, and then
make sure that there was appropriate guarding on them.” (Tr. 2129). Pursuant to this program, Respondent ended up
modifying or installing protection on over 600 different ladderway openings and
placed a priority on all requests to fix such openings. (Tr. 2129–30). According to David Armstrong, Respondent’s
warehouse technician, swing gates are stored in the warehouse and are issued to
supervisors on request. (Tr. 1349–50).
Respondent
contends that Complainant did not establish that it failed to exercise
reasonable diligence such that it could have known of the violative condition,
and the Court agrees. As noted above, there is no evidence indicating how long
the cited condition existed. In order to
determine whether Respondent could have known of the violation, there must be
evidence that Respondent had the opportunity to observe it. See Cranesville
Block Co., Inc./Clark Division, 23 BNA OSHC 1977 (No. 08-0316 et al., 2012) (holding that
complainant’s failure to introduce evidence regarding length of time condition
existed, respondent’s inspection program, or its exercise of reasonable
diligence precluded a finding of constructive knowledge). Rambo testified that he based his
determination of knowledge on the fact that Dan Looney, Respondent’s Safety
Manager, told him that he had observed open ladderways in the past. (Tr. 1493). Looney told Rambo that he would direct the
contractor to fix or close the ladder if he observed the conditions described
above. (Tr. 1493–94). Rambo also
testified that during the turnaround each unit had a supervisor and a safety
technician during each shift, intimating that Respondent had the opportunity to
observe the conditions. (Tr. 1434).
Whether
considering the foregoing under a multi-employer theory, or just the typical
employer knowledge analysis, the Court finds that Complainant has failed to
prove its prima facie case. Whether
Looney saw other open ladders at other locations at some point in time does not
establish that Respondent was aware of the particular
violations at issue in this citation item. In fact, in response to
cross-examination, Rambo admitted that Looney told him they direct contractors
and employees to close swing gates or replace them if they are open or
otherwise in need of repair and that this is what a reasonable employer would
do under such circumstances. (Tr. 1493–94). Complainant did not rebut
Respondent’s claims that it had such a program of inspection and repair in
place. Given that there was no
indication as to how long these two isolated conditions existed,
and considering that Respondent took extensive measures to uncover
violations by implementing an inspection and repair program, the Court finds
that Complainant failed to establish that Respondent knew or could have known
of the condition. Accordingly, Citation
1, Item 1 is VACATED.
ii.
Citation 1, Item 2
Complainant alleged a serious
violation of the Act in Citation 1, Item 2 as follows:
29 CFR 1910.101(b): The in-plant handling, storage, and
utilization of all compressed gases in cylinders, portable tanks, rail tankcars, or motor vehicle cargo tanks were not in accordance
with Compressed Gas Association Pamphlet P-1-1965, which is incorporated by
reference as specified in CFR 1910.6:
The employer does not ensure the in-plant
handling, storage, and utilization of all compressed gases in cylinders,
portable tanks, rail tankcars, or motor vehicle cargo
tanks is in accordance with Compressed Gas Association Pamphlet P-1-1965, which
is incorporated by reference as specified in CFR 1910.6. The violation was
observed on or about October 29, 2012, in the welding shop the employer did not
ensure that compressed gas cylinders were stored with protective caps exposing
employees to struck-by hazards.
The
cited standard provides:
The in-plant handling, storage, and
utilization of all compressed gases in cylinders, portable tanks, rail tankcars, or motor vehicle cargo tanks shall be in
accordance with Compressed Gas Association Pamphlet P-1-1965, which is
incorporated by reference as specified in § 1910.6.
29 C.F.R. § 1910.101(b).
During
Rambo’s inspection of the warehouse, he observed a number of
compressed gas cylinders that did not have caps on them. (Ex. C-72 at
6–8). This was confirmed by Armstrong,
who works in the warehouse. (Tr. 1319).
Armstrong testified that the gas cylinders were used by various
employees and contractors. (Tr. 1322).
According to Rambo, he interviewed the maintenance superintendent,
Johnny Reddell, who told him that the cylinders had
been left in that condition since a dust disturbance closed
down the warehouse for a week and that the caps were only placed back on
the cylinders after he brought it to their attention. (Tr. 1386, 1389–90). Based on his observations and interviews,
Rambo determined that Respondent violated the standard.
First,
the Court rejects Respondent’s argument that the cylinders in question were
actively being used, rather than stored. Armstrong initially testified that the
cylinders were located in the welding shop, which
means that they were not in a storage location and were in use. (Tr.
1363–64). However, under
cross-examination, Armstrong admitted that he did not know whether the
cylinders had been used either in the last 24 hours or on any of the previous
shifts. (Tr. 1372). As noted above,
however, Reddell told Rambo that they placed the caps
back on the cylinders after it had been pointed out to them. If the cylinders
were being used, there would have been no need to place the caps on them.
Further, the Court rejects the idea that because the cylinders were not in a
typical storage location they are not being “stored”. Other than Armstrong’s testimony as to the
location of the cylinders, there was no indication that they were in use at the
time of the inspection. This is
supported by the fact that the various tubes and wires associated with the
cylinder were neatly wrapped around the cylinder. (Ex. C-72 at 6). Because the cylinders were being stored
without caps, the Court finds that Respondent violated the standard.
Second,
the Court finds that Respondent knew or could have known of the condition. According
to Rambo’s testimony, the condition had existed for at least a week. (Tr. 1390). Admittedly, the warehouse had been closed for
most of that time due to a dust disturbance that prevented employees from
working in the warehouse; however, Rambo testified that there were employees
working in the warehouse when he arrived.[52] (Tr.
1389–90). The cylinders were stored in a
fairly conspicuous area that could have been observed
by anyone passing through. (Tr. 1320; Ex. C-72). Because it is not known who created the
condition, Respondent contends that it should not be held liable as a
controlling employer.
“[A]n
employer with overall supervisory authority at a multi-employer work site, who
has hired and entered into contractual relationships with subcontractors who
are performing the work at the site, can be found liable for violations created
by the subcontractors, as long as the controlling employer ‘could reasonably
have been expected to prevent or abate by reason of its supervisory capacity.’”
E.P. Guidi, Inc., 21 OSHC BNA 1413 (No.
04-1055, 2006) (quoting Grossman Steel & Aluminum Corp., 4 BNA OSHC
1185, 1188 (No. 12775, 1975)). In this
case, as opposed to cases like E.P.Guidi, the worksite is owned
and wholly controlled by Respondent.
Further, Respondent’s witnesses testified that, during the turnaround,
each unit was assigned a Wynnewood Refining Company supervisor and safety
technician to ensure compliance with safety rules and, therefore, Respondent took
responsibility for ensuring the safety of both employees and contractors. (Tr. 2111–2112). See
Grossman, 4 BNA OSHC at 1188 (“The general contractor is well situated to
obtain abatement of hazards, either through its own resources or through its
supervisory role with respect to other contractors. It is therefore reasonable to expect the
general contractor to assure compliance with the standards insofar as all
employees on the site are affected.”). Finally,
Armstrong testified that at least one of the supervisors was in the warehouse
approximately 4–5 times per day, meaning that there was ample opportunity to
view the condition, which was located in plain sight.
(Tr. 1358). Thus, the Court finds that
Respondent knew or could have known of the condition.
Further, the
purpose of the standard is to prevent the possibility that a cylinder could
become a projectile if the valve at the top is broken off. (Tr. 1388). Because there were Wynnewood employees in the
warehouse at the time the violation was observed, the Court finds that they, as
well as contractor employees, were exposed to the hazard, and that the
violative condition was serious. (Tr. 1388).
Complainant has established its prima
facie case. Accordingly, Citation 1,
Item 2 is AFFIRMED.
iii.
Citation 1, Item 3
Complainant alleged a serious violation
of the Act in Citation 1, Item 3 as follows:
29 CFR 1910.119(h)(2)(v): The employer did not periodically evaluate
the performance of contract employers in fulfilling their obligations as
specified in paragraph 1910.119(h)(3):
Wynnewood does not have a system to
periodically evaluate the performance of their contractors in fulfilling their
obligations as specified in paragraph 1910.119(h)(3). Wynnewood does not evaluate whether or not each contractor:
a)
Trains their employees in the work
practices necessary to safely perform their job;
b)
Instructs their employees on the
known potential fire, explosion, or toxic release hazards related to their job
and the applicable provisions of the emergency action plan;
c)
Documents, records and maintains a
record that all their employees have received and understand the training
required;
d)
Assures that each employee follows
the safety rules of the facility.
Contractor employees were observed
exiting various process areas without signing out; not wearing appropriate eye
or face protection while mixing and applying refractory products,
and working on scaffolds that were not properly designed or erected. No
formal process to evaluate contractor performance is in place at the refinery.
The
cited standard provides:
The employer shall periodically
evaluate the performance of contract employers in fulfilling their obligations
as specified in paragraph (h)(3) of this section.
29 C.F.R. § 1910.119(h)(2)(v).
After
conducting interviews with members of Respondent’s safety department, CSHO
Rambo determined that Respondent had violated the standard requiring periodic
monitoring of contract employer’s compliance with paragraph (h)(3) of the same
standard. Rambo testified that Looney
had told him that the safety department conducted self-audits but that they did
not maintain documentation of their audits. (Tr. 1457). Rambo also testified that he had never been
provided with documentation of contractor performance audits. (Tr. 1457). Shane Stair, a safety specialist, told Rambo
that he was unsure whether they had an evaluation process for contractors, and
David Johnson, who also testified, told Rambo that they did not evaluate
contractors. (Tr. 1458). In light of the fact that all
three of those men were a part of the safety department, Rambo testified that
“it gave me a sense of no one wanted to take ownership of safety when it came
to others outside of Wynnewood working inside the refinery.” (Tr. 1458).
According
to David Johnson, the turnaround had a significant impact on the operations of
the refinery. During a normal workday, Respondent had approximately three to
four safety personnel to assess safe work practices. (Tr. 2109). During a turnaround, however, Johnson stated
that the safety workforce increased to 40, which included approximately 14
Wynnewood employees. (Tr. 2110). The
rest of the safety crew came from a contractor that specializes in turnarounds,
Total Safety. (Tr. 2111). The crew,
which was split into two shifts and broken out by zone, would review safety
procedures and perform field audits. (Tr. 2113). On cross-examination, Johnson testified that
“we had a system in place for our field safety people to go out and evaluate
how the contractors were working safely” and included verification of those
evaluations through the use of field notes. (Tr.
2149). To the extent that violations
were observed, Johnson testified that the violation was abated
and the offending contractor/employee was counseled; in some instances,
Respondent had to go so far as to remove certain contract employees from the
premises. (Tr. 2120). Johnson also
testified that Respondent utilized a system known as PICS (Pacific Industrial
Contractors Services), which is a third-party contractor that evaluates
potential contractors based on a pre-determined set of criteria. (Tr.
2105–06). Those criteria include an
evaluation of whether the contractor provides the necessary training and
possesses adequate written safety programs to perform the work needed at the
refinery. (Tr. 2108). Based on this
testimony, Respondent contends that it exercised reasonable diligence in
monitoring contractor compliance with (h)(3).
Complainant
alleges that Respondent violated the standard in all respects; namely, that it
failed to periodically evaluate the performance of contractors with respect to
each of the duties listed under (h)(3).
However, based on Respondent’s use of the PICS system to evaluate
contractors, the Court finds that Respondent complied with its obligations as
to (a), (b), and (c) as described in the citation item. Complainant did not present evidence to
suggest that Respondent’s use of the PICS system was insufficient with respect
to those issues. Rather, based on
Rambo’s testimony, Complainant’s focus appears to be instance (d), which claims
that Respondent failed to ensure that contract employers “assures that each
employee follows the safety rules of the facility.” 29 C.F.R. §
1910.119(h)(3)(iv). The primary bases
for the allegation are, as mentioned above, the interviews conducted by Rambo
and Rambo’s discovery of violative conditions around the refinery as recounted
in the body of the citation.
As
noted above, during the turnaround Respondent was responsible for tracking over
1500 additional contract employees at the refinery per shift. In response,
Respondent put together a safety team of 40 people to track, observe, and
assist these employees. However, the
existence of violations, alone, is not sufficient to
establish that Respondent failed to periodically evaluate the performance of
its contractors. Further, though Rambo
testified that multiple safety employees told him that they did not monitor the
performance of contractors, Johnson provided some context for the comments made
to Rambo by Looney. Specifically, Johnson
said that he disagreed with Looney’s purported statement that Respondent
“do[es] not oversee contractors as far as safety when they do their job.” He explained, instead, that contractor
employees are required, as indicated by the standard, to oversee/ensure the
safety of their own employees. See 29
C.F.R. § 1910.119(h)(3)(iv) (“The contract employer shall assure each contract
employee follows the safety rules of the facility . . .”). Johnson then went on to discuss the manner in which Respondent evaluated its contractors from an
initial and ongoing perspective. (Tr. 2105, 2109–2115). Complainant did not
rebut Johnson’s testimony regarding its evaluation process; rather, it merely
pointed out that Respondent failed to provide documentation of the evaluations.
(Tr. 2147). The cited standard, as
compared to other subsections within 1910.119, does not have a written
documentation requirement; rather, it only requires Respondent to perform
periodic evaluations. Based on the foregoing,
the Court finds that Complainant failed to prove a violation of the
standard. Accordingly, Citation 1, Item
3 is VACATED.
iv.
Citation 1, Item 4
Complainant alleged a serious
violation of the Act in Citation 1, Item 4 as follows:
29 CFR 1910.157(c)(1): Portable fire
extinguishers were not mounted, located and identified so that they were
readily accessible without subjecting the employees to injuries:
The employer does not ensure
portable fire extinguishers are mounted, located and identified so that they
are readily accessible without subjecting the employees to injuries. This violation was observed on or about
October 29, 2012, the employer did not ensure fire extinguishers were free from
obstruction and readily accessible exposing employees to the hazards of fire,
trips and falls:
a)
A fire extinguisher in the warehouse
was blocked by boxes.
b)
A fire extinguisher in the pump shop
was blocked by a large crate and air lines.
c)
Two fire extinguishers in the
welding shop were not mounted.
The
cited standard provides:
The employer shall provide portable
extinguishers and shall mount, locate and identify them so that they are
readily accessible to employees without subjecting the employees to possible
injury.
29 C.F.R. § 1910.157(c)(1).
While
in the maintenance warehouse, CSHO Rambo observed a number of
fire extinguishers that were not properly mounted or were otherwise not readily
accessible as required by the standard. (Tr. 1391; Ex. C-72 at 18–20). Respondent contends that, notwithstanding the
existence of the conditions, Complainant failed to prove how long the condition
lasted or that Respondent knew or could have known of the violations. The Court finds that Complainant has
established a violation of the standard.
The testimony was fairly
consistent that the warehouse had an issue with blocked fire
extinguishers. According to Armstrong, he observed fire extinguishers that were
blocked in or were not properly mounted during the turnaround, which he
attributed to the constant influx of materials coming into the warehouse to
fill work orders. Though he admitted
that the turnaround was not the first time he had observed this condition. (Tr.
1324, 1330). He agreed that the
extinguishers identified in Complainant’s exhibits were not readily accessible
and characterized the issue of blocked extinguishers as an “ongoing hazard”.
(Tr. 1330). Armstrong also testified that the warehouse manager’s office was
right next to one of the blocked extinguishers. (Tr. 1327; Ex. C-72 at 18–20). Respondent performed a self-audit at the end
of August 2012, not long before Rambo’s inspection. (Ex. C-74). The first item of that audit identifies
multiple, blocked fire extinguishers, including one “located outside the south
door of the office.” (Ex. C-74).
According to Rambo, Richard McCaulla, the
warehouse manager, told him that he was aware that the fire extinguisher
outside of his office was blocked and explained that the blockage was the
result of an influx of materials and a lack of space.[53] (Tr. 1392).
The
Court finds, consistent with the testimony of Armstrong, that the condition of
blocked or otherwise improperly mounted fire extinguishers was an “ongoing
hazard” in Respondent’s warehouse.
Respondent’s warehouse manager admitted that he was aware of blocked
extinguishers and the reasons therefor; one of the blocked extinguishers was
right outside his office; and an audit of the warehouse revealed this problem
more than a month before CSHO Rambo’s inspection in late October. Thus,
Respondent knew or could have known of the condition. The Court also finds that
Respondent’s failure to have readily accessible fire extinguishers exposed its
employees to potential fire hazards. (Tr. 1329–30). Respondent’s Emergency
Action Plan (EAP) indicates that properly trained employees are expected to use
fire extinguishers “if the fire can be easily extinguished and you have the
proper training.” (Ex. C-78). As noted
by Armstrong, the first minutes of a fire are critical, and precious time would
be wasted in having to remove materials and boxes in order to access a fire
extinguisher. (Tr. 1329). Insofar as
employees are expected to participate in putting out minor fires, the Court
finds that the failure to have readily accessible extinguishers exposed those
employees to potential burn injuries. As such, the Court finds that Complainant
has established a serious violation of the cited standard. Accordingly, Citation 1, Item 4 is AFFIRMED
as serious.
v.
Citation 1, Item 5
Complainant alleged a serious
violation of the Act in Citation 1, Item 5 as follows:
29 CFR 1910.212(a)(3)(ii): Point of operation guards were not designed
and constructed as to prevent the operator from having any part of their body
in the danger zone during the operating cycle:
The employer does not ensure point
of operation guards are designed and constructed as to prevent the operator
from having any part of their body in the danger zone during the operating
cycle. This violation was observed on or
about October 29, 2012, in the pump shop the employer did not ensure a Johnson
horizontal band saw was provided a guard exposing employees to the hazard of
contact with the point of operation.
The
cited standard provides:
The point of operation of machines
whose operation exposes an employee to injury, shall be guarded. The guarding device shall be in conformity
with any appropriate standards therefor, or, in the absence of applicable
specific standards, shall be so designed and constructed as to prevent the
operator from having any part of his body in the danger zone during the
operating cycle.
29 C.F.R. § 1910.212(a)(3)(ii).
CSHO
Rambo identified a horizontal band saw in the warehouse that did not have
proper guarding to protect against point-of-operation hazards. (Tr. 1395; Ex.
C-72 at 21–25). The close-up photographs show two blades that extend lengthwise
across the open space of the machine, running parallel to the name “JOHNSON”
emblazoned across the top. (Ex. 72 at 23–24). As noted by Rambo, there is
nothing to prevent contact with the blades during operation. (Tr.
1396–97). In response to questions about
how long the saw had been in the condition observed by Rambo, Calvin Foley, who
had been the pump shop supervisor for 15 years, stated that it had been that
way since he had worked there. (Tr. 1398–99).
This was echoed by Johnny Reddell,
Respondent’s maintenance manager. (Id.).
Respondent
contends that Complainant failed to prove that it knew or could have known of
the condition. Although Armstrong testified that there was a guard that could
be removed from time to time, he seemed to be somewhat confused as to which
guard was being discussed. Initially, Armstrong indicated that the saw depicted
in Exhibit C-72 was guarded. (Tr. 1334; Ex. C-72 at 21). In response to questions from the Court,
Armstrong testified there was no additional guarding that was removed or
replaced during the turnaround, and, insofar as he discussed guarding that had
been removed, he was referring to the green piece of metal with the handle,
which is located on the left-hand side of the photograph in Exhibit C-72 at 21.
(Tr. 1334–35). Later in his testimony,
Armstrong said that he thought there was a guard in the open area, but he was
not “a hundred percent sure”. (Tr. 1339).
Notwithstanding that testimony, Armstrong admitted that he observed the
saw without the guard, and that the last time he had observed the saw without
this purported guard “was before the turnaround.” (Tr. 1341).
The
Court finds that Respondent violated the standard and that the violation was
serious. The saw, as observed by CSHO Rambo, was improperly guarded and exposed
its users to point-of-operation hazards, such as lacerations and potential
amputations. (Tr. 1396–97). The Court finds that the statements given to CSHO
Rambo establish that the saw, as illustrated in Exhibit 72, was in its normal
operating condition, had been in that condition for quite some time, and that
such condition was known to members of Respondent’s management team. Even if
the Court were to discount those statements, the Court would still find that
Respondent had adequate knowledge of the violation based on Armstrong’s
testimony that his supervisor’s “should’ve knew” about the saw, because they
“walk by the saw as much as I do, and if I’ve seen it, then they [sic] seen
it.” (Tr. 1333). Armstrong testified
that the last time he had seen this purported removable guard was before the
turnaround, which means that many of his supervisors had the opportunity to
observe the unguarded saw, as it was being used by “[j]ust
about everyone in that warehouse . . . .” (Tr.
1332). Accordingly, Citation 1, Item 5
is AFFIRMED as serious.
vi.
Citation 1, Item 6(a), (b), and (c)
Complainant
alleged three serious violations of the Act in Citation 1, Item 6, subparts (a),
(b), and (c). Given their similarity,
both items shall be addressed together.
Complainant’s allegations with respect to Item 6(a) are as follows:
29 CFR 1910.215(a)(2): Abrasive
wheel(s) used on grinding machinery were not provided with safety guard(s)
which covered the spindle end, nut, and flange projections:
The employer does not ensure
abrasive wheels used on grinding machinery are provided with safety guards
which cover the spindle end, nut, and flange projections. This violation was
observed on or about October 29, 2012, in the pump shop the employer did not
ensure abrasive wheels on a grinding machine were provided with safety guards
covering the spindle end, nut, and flange projections exposing employees to the
hazard of caught-by.
The cited standard provides that
“[t]he safety guard shall cover the spindle end, nut, and flange projections, The
safety guard shall be mounted so as to maintain proper alignment with the
wheel, and the strength of the fastenings shall exceed the strength of the
guard . . . .” 29 C.F.R. § 1910.215(a)(2).
Complainant’s allegations with
respect to Item 6(b) are as follows:
29 CFR 1910.215(b)(9): The distance between the grinding wheel
periphery and the adjustable tongue or the end of the peripheral member at the
top exceeded one-fourth inch:
The employer does not ensure the
distance between the grinding wheel periphery and the adjustable tongue or the
end of the peripheral member at the top exceeded one-fourth inch. This
violation was observe on or about October 27, 2012, in
the maintenance shop where the distance between the grinding wheel periphery
and the adjustable tongue guard on a Baldor bench grinder exceeded one-fourth
inch exposing employees to the hazard of caught-by and struck-by flying debris
resulting from an exploding grinding wheel.
The
cited standard provides:
Safety guards . . . where the
operator stands in front of the opening, shall be constructed so that the
peripheral protecting member can be adjusted to the constantly decreasing
diameter of the wheel. The maximum
angular exposure above the horizontal plane of the wheel spindle . . . shall
never be exceeded, and the distance between the wheel periphery and the
adjustable tongue or the end of the peripheral member at the top shall never
exceed one-fourth inch.
29 C.F.R. § 1910.215(b)(9).
Complainant’s allegations with
respect to Item 6(c) are as follows:
29 CFR 1910.215(d)(3): The contact surface(s) of wheel(s),
blotter(s) or flange(s) on grinding machine(s) were not flat and free of
foreign matter:
The employer does not ensure the
contact surfaces of wheels, blotters or flanges on grinding machines are flat
and free of foreign matter. This
violation was observed on or about October 27, 2012, in the maintenance shop
for a Baldor bench grinder where the contact surface of a grinding wheel was
not kept flat and smooth exposing employees to the hazard of struck-by flying
debris from an exploding grinding wheel.
The cited standard provides that
“[a]ll contact surfaces of wheels, blotters and
flanges shall be flat and free of foreign matter.” 29 C.F.R. § 1910.215(d)(3).
CSHO
Rambo provided ample testimony and evidence to establish a violation of the
foregoing standards with respect to the bench grinder, much of which was
confirmed by Armstrong and not contradicted by any other witness. (Tr. 1343). According
to Rambo, the grinding wheel: (1) did
not have adequate guarding to protect against point-of-operation hazards, as
well as potential shrapnel hazards from a well-worn grinding disc; (2) measured
nearly 2.75 inches between the wheel and the guard, when the required distance
is less than one-quarter inch; and (3) was overly worn, full of indentations,
and was otherwise unsafe to use. (Tr. 1401–1410; Ex. C-72 at 26–33). Thus, Respondent violated the terms of the
standard.
Respondent
contends, however, that Complainant cannot prove that it knew or could have
known of the condition. Characterizing Armstrong’s testimony as speculation,
Respondent argues that Complainant failed to show that any member of management
was aware of the condition. Similar to his testimony with respect to the band saw,
Armstrong stated that members of the management team must have seen the
condition of the wheel, considering its location in plain view, the regularity
of its use, and due to the obviously non-compliant condition of the wheel
itself. (Tr. 1344). The Court has no reason to doubt Armstrong’s assessment,
and, in light of the condition and size of the
grinding wheel itself, it is clear that it had been used in a non-compliant
condition for long enough for warehouse management to observe it. The Court credits Armstrong’s testimony based
on his intimate knowledge of the conditions and operations inside Respondent’s
warehouse. Thus, the Court finds that
Respondent knew or, with the exercise of reasonable diligence, could have known
of the condition. This condition exposed
the employees, contractors, and managers that used it to point-of-operation
hazards and potential struck-by hazards due to the condition of the grinding
wheel itself. Both Rambo and Armstrong
testified that these hazards could cause serious injury. (Tr. 1403, 1343).
Based
on the foregoing, the Court finds that Complainant established a violation of
the standard. Accordingly, Citation 1, Items 6(a), (b), and (c) are AFFIRMED as
serious violations of the Act.
vii.
Citation 1, Item 7
Complainant alleged a serious
violation of the Act in Citation 1, Item 7 as follows:
29 CFR 1910.303(g)(1): Sufficient access and working space was not
provided and maintained about all electric equipment (operating at 600 volts,
nominal, or less to ground) to permit ready and safe operation and maintenance
of such equipment:
The employer does not provide and
maintain sufficient access and working space about all
electric equipment (operating at 600 volts, nominal, or less to ground) to
permit ready and safe operation and maintenance of such equipment. This violation was observed on or about
October 27, 2012, in the pump shop where an electrical panel was not accessible
exposing employees to fire and electrical hazards.
The
cited standard provides:
Sufficient access and working space shall be provided and maintained
about all electric equipment to permit ready and safe operation and maintenance
of such equipment.
29 C.F.R. § 1910.303(g)(1).
Rambo
testified that the standard applies, and Respondent does not dispute that
assertion. (Tr. 1412). The testimony of Rambo and the photographs of the
electrical panel show that there was an obstruction in front of the panel,
including a shelf and cabinet. (Tr. 1412–13; Ex. C-72 at 35). Respondent contends that Complainant failed
to prove that the obstruction, as it were, was large enough to block
access. Although the cited standard is
couched in terms that are performance-related, the subsections of
1910.303(g)(1) indicate what constitutes sufficient
access and working space. See, e.g., 29
C.F.R. § 1910.303(g)(1)(i)(C) (“The work space shall
be clear and extend from the grade, floor, or platform to the height required
by paragraph (g)(1)(vi) of this section. However, other equipment associated
with the electrical installation and located above or below the electric
equipment may extend not more than 153 mm (6 in.) beyond the front of the
electric equipment.”). The Court finds
that, based on these parameters, the condition of the electrical panel violated
the terms of the standard.
The
Court also finds that Respondent knew of the condition and that its employees
were exposed to it. According to CSHO
Rambo, both Foley and the electrical supervisor, Eric Amparano,
were aware of the blocked electrical panel. (Tr. 1414). The Court finds that
their knowledge is properly imputed to Respondent. Further, the Court credits Rambo’s testimony
that two individuals working in the pump shop were exposed to potential
tripping hazards or even burns if employees are not able to access the panel in
an emergency. (Tr. 1413). These hazards
have the potential to cause serious injuries, such as burns, contusions, or
broken bones.
Based
on the foregoing, the Court finds that Complainant established a violation of
the standard and that the violation was serious. Accordingly, Citation 1, Item 7 is AFFIRMED.
viii.
Citation 1, Item 8
Complainant alleged a serious
violation of the Act in Citation 1, Item 8 as follows:
29 CFR 1910.305(b)(1)(ii): Unused openings in cabinets, boxes, and
fittings, were not effectively closed:
The employer does not ensure unused
openings in cabinets, boxes, and fittings are effectively closed. This violation was observed on or about
October 29, 2012, in the maintenance shop where the employer did not ensure
that pre-punched knockout was effectively closed on an electrical panel
exposing employees to fire and electrical hazards.
The
cited standard provides:
Unused openings in cabinets, boxes,
and fittings shall be effectively closed.
29 C.F.R. § 1910.305(b)(1)(ii).
CSHO
Rambo observed an open knockout on the panel box identified in Exhibit C-72.
(Ex. C-72 at 36). A knockout is an
opening to receive electrical lines into the panel box. (Tr. 1415). Rambo testified that Amparano,
Respondent’s electrical supervisor, told him he had orchestrated the removal a
cord, which was supposed to provide power to a temporary welder. (Tr.
1416). Apparently
the cord that was selected was insufficient for the power draw of the welder,
so the cord was taken off, and the knockout was left open. (Tr. 1416). On cross-examination, Rambo testified that Amparano told him that the work of changing the cord was
carried out by a contractor. (Tr. 1509).
Nevertheless, it was still carried out at his direction. (Tr. 1509).
Respondent
contends that, due to the fact that the work was
performed by a contractor, Respondent had no reason to know of the violation.
The Court disagrees. Rambo testified that Amparano
directed the work to remove the cord, which took place around the beginning of
the turnaround. (Tr. 1416–17). Rambo
discovered the condition nearly two months later. (Tr. 1417). The electrical panel was located next to the
restroom in a well-traveled area. (Tr. 1349).
Given the location of the condition, the fact that the work to remove
the cord was done at the direction of one of Respondent’s supervisors, and the
length of time that the condition existed, the Court finds that Respondent,
with the exercise of reasonable diligence, could have known of the condition.
Because
the condition was in a well-traveled area, the Court also finds that
Respondent’s employees were exposed to the hazard, which could cause shocks,
burns, and potentially electrocution. (Tr. 1416). Exposure to such hazards could cause serious
injury up to and including death. Based
on the foregoing, the Court finds that Respondent violated the standard and
that the violation was serious.
Accordingly, Citation 1, Item 8 is AFFIRMED as a serious violation of
the Act.
ix.
Citation 1, Item 9
Complainant alleged a serious
violation of the Act in Citation 1, Item 9 as follows:
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords were used as a substitute for
fixed wiring of a structure:
The employer does not ensure
flexible cords are not used as a substitute for fixed wiring of a
structure. This violation was observed
on or about October 29, 2012, in the welding shop where extension cords were
used as a substitute for fixed wiring exposing employees to electrical hazards.
The
cited standard provides:
Unless specifically permitted
otherwise in paragraph (g)(1)(ii) of this section, flexible cords and cables
may not be used . . . [a]s a substitute for the fixed wiring of a structure.
29 C.F.R. § 1910.305(g)(1)(iv)(A).
While
in the warehouse, Rambo observed extension cords strung over beams throughout the
welding shop, including one cord that was wrapped around a metal cable. (Tr.
1417; Ex. C-72 at 37–40). He discovered
that these cords were being used as the primary electrical source for a
workstation. (Tr. 1417). In addition to being used as a primary power source,
Rambo also observed the cords being used to “store” equipment, which was hung
from the ends of the cords. (Tr. 1419; Ex. C-72 at 39–40). Amparano
told Rambo that the extension cords had been used like this for years and
Armstrong testified that they had been like that for “an extended period of
time.” (Tr. 1345, 1420).
Respondent
argues the citation should be dismissed because it alleges, at best, a de minimis violation of the Act. According to Respondent, there was no proof
the alleged violation exposed employees to a safety and health risk; in fact,
Respondent points out that none of the extension cords showed signs of damage. See Resp’t Br. At
76 (citing Dover Elevator, 15 BNA
OSHC 1378 (No. 88-2642, 1991) (“A violation is de minimis when a deviation from the standard has no ‘direct or
immediate’ relationship to employee safety.”)).
The Court disagrees.
In addition
to the line quoted by Respondent, the Commission in Dover also stated, “[N]ormally, that
classification is limited to situations in which the hazard is so trifling that
an abatement order would not significantly promote the objectives of the Act.” Id.
Under the facts of this case, the Court is convinced that Complainant
has established that the violation in this case has a direct and immediate
relationship to employee safety and that abatement of the violation will
promote the objectives of the Act. Not
only were the cords draped over steel beams and cables, but those same cords
were used to suspend equipment, which placed additional strain on the cords.
The Act illustrates that OSHA has made the determination that such a situation
does have a direct and immediate relationship to employee safety. See 29 C.F.R. § 1910.303(a)(2)(x) (“Flexible
cords and cables shall be protected from accidental damage, as might be caused,
for example, by sharp corners, projections, and doorways or other pinch points.”). Further, Rambo testified that sharp edges,
such as the metal cable and the beams, coupled with the additional weight imposed
by the hanging objects, could cause a tear in the cord (or “accidental
damage”). (Tr. 1419). If a tear occurs,
everything that comes into contact with the exposed
wiring could be energized, which would include the beams and metal cables over
which the electrical cords were draped.
Based on the
foregoing, the Court finds that Complainant established a serious violation of
the cited standard, that Respondent knew of the condition, and that
Respondent’s employees were exposed to the possibility of shock, burns, or
electrocution. Accordingly, Citation 1,
Item 9 is AFFIRMED as serious.
x.
Citation 2, Item 1
Complainant alleged a repeat violation
of the Act in Citation 2, Item 1 as follows:
29 CFR 1910.119(h)(2)(iv): The employer did not develop and implement
safe work practices consistent with 29 CFR 1910.119(f)(4), to control the
entrance, presence and exit of contract employers and employees in covered
process areas:
The employer does not develop and
implement safe work practices consistent with 29 CFR 1910.119(f)(4), to control
the entrance, presence and exit of contract employers and employees in covered
process areas. On or about October 25,
2012, and at times prior thereto, the employer did not ensure contract
employees are properly signed in/out process units:
a)
Four (4) JV Industrial Companies
employees failed to sign out of Zone 3.
b)
Two (2) LOP employees failed to sign
out of the FCCU.
c)
One (1) Altair Strickland employee
failed to sign out of the FCCU.
d)
One (1) Total Safety employee, two
(2) OSR employees, one (1) Strategic Contract Resources employee, and one (1)
Wynnewood Refining Company employee failed to sign out of the FCCU.
e)
On October 20, 2012, seven (7) Scaffolding
and Erection Company employees, two (2) Strategic Contract Resources employees
failed to sign out of the Alkylation Unit.
f)
On October 12, 2012, three (3) Koch
employees failed to sign out of the SRU 48002 area in the Alkylation Unit.
The
cited standard provides:
The employer shall develop and
implement safe work practices consistent with paragraph (f)(4) of this section,
to control the entrance, presence and exit of contract employers and contract
employees in covered process areas.
29 C.F.R. § 1910.119(h)(2)(iv).
As
part of his inspection, CSHO Rambo had to sign-in and sign-out of various units
within the refinery. When he signed in, Rambo took the opportunity to review
Respondent’s log books. (Tr. 1445–46).
His examination of the log books in the Alky Unit, the FCCU, and Zone 3
showed 24 instances of a contractor or employee failing to sign out of those
areas over the course of roughly 12 days, beginning on October 12, 2012.[54]
(Tr. 1449; Ex. C-72 at 9–13, C-76). As a
result of his observations, Complainant issued a citation alleging that
Respondent failed to enforce its sign-in/sign-out policy and, therefore, failed
to adequately implement a safe work practice “to control the entrance, presence
and exit of contractor employers and employees in covered process areas.” 29
C.F.R. § 1910.119(h)(2)(iv).
Respondent
contends that Complainant did not prove that it failed to exercise reasonable
diligence to ensure that its contractors complied with applicable safe work
practices, such as signing in and out of covered process areas. In support of
this proposition, Respondent points to its three-tiered system of signing into
and out of process areas, inclusive of its badge process for entering the
refinery, its log book for process areas, and its safe work permit process.
(Tr. 2102, 2121–23). Respondent also
argues that it strictly enforced its sign-in/sign-out policy through auditing
work practices of contractors, as well as the sign-in/sign-out sheets for each
process area. As such, Respondent argues that it took all reasonable efforts to
discover violations and that Complainant failed to prove that it “should have
known of even a single instance where a contractor failed to sign in or out.” Resp’t Br. at 78.
The
Court agrees with Complainant. It is clear that Respondent
had developed and, to a certain extent, implemented a system to control the
entry into and exit from covered process areas. The problem, however, was that
the system was ineffective. Respondent
contends that Complainant failed to prove that it could have known of even a
single instance of a contractor failing to sign out; however, it also claims
that it implemented a strict auditing policy, which included reviewing
sign-in/sign-out sheets on a daily basis. Resp’t Br. at 77. Based on the log books introduced by
Complainant, the Court finds that the auditing policy was not as strict as
Respondent would have it believe. One of
the logs showed three contractors that failed to sign out of the SRU on October
12, 2012. (Ex. C-76). Other logs show
multiple failures to sign out from the FCCU, all occurring on the same day,
October 25, 2012. (Ex. C-72 at 9–13). If
Respondent was reviewing the logs and contractor practices as it suggests (and,
indeed, as it should have been), then it would have been readily aware of its
contractors failing to sign out of covered process units. While the Court is
mindful of the fact that the large number of contractors at the refinery during
the turnaround makes tracking every single one difficult, that only highlights
the importance of ensuring that entry into process areas is properly
controlled. Thus, the Court finds that Complainant established a violation of
the standard and that Respondent, with the exercise of reasonable diligence,
could have known of the violation.
The Court
also finds that employees were exposed to potential hazards. According to David Johnson, it is important
to track the entry into and exit out of process units because “during an
emergency, the most important thing is to make sure everybody is safe.” (Tr.
2138–39). Rambo testified similarly,
stating that in the event of an evacuation, first responders (and Wynnewood
employees) could be exposed to fire and chemical leak hazards if they needed to
enter a process unit to find a non-present subcontractor employee who simply
had not signed out. (Tr. 1449). Respondent
contends that the violation should not be categorized as serious because the
sign-in/sign-out sheets would not be used in the event of a catastrophic
release; employees are instructed to immediately leave the unit and gather at
designated assembly areas. (Tr. 2123–25).
Instead, Respondent states that it uses the entry badge data to determine
who is on the premises in an emergency. The
Court finds the standard Respondent violated addresses more than that.
According to the preamble of the PSM standard, “[T]he objectives of these
additional provisions were to insure that those
persons operating high hazard processes are cognizant of any non-routine work
that is occurring and to insure that those in responsible control of the
facility are also in control of non-routine work.” (Ex. C-2 at 30). The failure to adequately track contractors
and employees, doing non-routine work in covered process areas not only impacts
potential rescue efforts, but it also impacts active and future work projects.
If it is unclear whether certain non-routine work projects are occurring in
process areas, then subsequent entrants into those areas cannot adequately
assess the hazards associated with working in, energizing, or de-energizing a particular unit. Without
the ability to know with certainty whether individuals are in certain area of
the refinery, employees and contractors are subjected to any number of hazards
that might be present, including, as is relevant to a refinery, fire and
explosion hazards. Thus, the Court finds that the violation was serious.
Based on the
foregoing, the Court finds that Respondent violated the standard and that the
violation was serious. Accordingly,
Citation 2, Item 1 is AFFIRMED.
xi.
Citation 3, Item 1
Complainant alleged another-than-serious
violation of the Act in Citation 1, Item 1 as follows:
29 CFR 1910.22(d)(1): In every building or other structure, or part
thereof, used for mercantile, business, industrial, or storage purposes, the
loads approved by the building official were not marked on plates of approved
design securely affixed by the owner of the building, or his duly authorized
agent, in a conspicuous place in each space to which they are related:
In every building or other
structure, or part thereof, used for mercantile, business, industrial, or
storage purposes, the employer does not ensure the second level storage area is
designed, constructed, and maintained to support its maximum intended
load. This violation was observed on or
about October 29, 2012, in the warehouse the employer did not ensure the second
level storage area was designed, constructed, and maintained to support its
maximum intended load.
The
cited standard provides:
In every building or other
structure, or part thereof, used for mercantile, business, industrial, or
storage purposes, the loads approved by the building official shall be marked
on plates of approved design which shall be supplied and securely affixed by
the owner of the building, or his duly authorized agent, in a conspicuous place
in each space to which they relate. Such
plates shall not be removed or defaced but, if lost, removed, or defaced, shall
be replaced by the owner or his agent.
29 C.F.R. § 1910.22(d)(1).
CSHO
Rambo observed a second-level storage area that did not have a posted load
rating. (Tr. 1422). This area was used
for storing gaskets, electrical parts, and shafts, some of which can weigh up
to 150 pounds. (Tr. 1346; Ex. C-72 at 41–42).
According to Rambo, McCaulla told him that the
second-level storage area had never been load-rated, which was echoed by
Armstrong, who testified that he had never seen a load rating for that area.
(Tr. 1348).
The
Court finds that Complainant established a violation of the standard. The
evidence clearly shows that the second-level storage area did not have a load
rating to indicate that it was capable of supporting
the load of the stored materials. Respondent was clearly aware of this failure,
as indicated by McCaulla’s statements to Rambo and
confirmed by Armstrong’s testimony that the storage area had never been rated. The
Court also finds that employees, including Armstrong, were exposed to the
hazard of falling materials and a potentially the collapse of the storage
area—without knowing the load capacity, Respondent could possibly overload the
elevated storage area. Accordingly, Citation 3, Item 1 is AFFIRMED as an other-than-serious violation of the Act.
V.
Penalties
In calculating appropriate penalties for affirmed
violations, Section 17(j) of the Act requires the Commission give due
consideration to four criteria: (1) the size of the employer’s
business, (2) the gravity of the violation, (3) the good faith of the employer,
and (4) the employer’s prior history of violations. Gravity is the primary consideration and is
determined by the number of employees exposed, the duration of the exposure,
the precautions taken against injury, and the likelihood of an actual injury. J.A.
Jones Construction Co., 15 BNA OSHC 2201 (No. 87-2059, 1993). It is well established that the Commission
and its judges conduct de novo
penalty determinations and have full discretion to assess penalties based on
the facts of each case and the applicable statutory criteria. Valdak Corp., 17
BNA OSHC 1135 (No. 93-0239, 1995); Allied
Structural Steel, 2 BNA OSHC 1457 (No. 1681, 1975).
A.
Docket No. 13-0791 – Inspection No.
663538
The citation
items resulting from this inspection, although they allege violations of
different standards, all involve the same basic hazard in the same area of the
refinery: catastrophic releases of highly hazardous chemicals in the start-up
and operation of the Wickes boiler. Unfortunately,
the facts of this case also illustrate the potential gravity of those
violations. Two of Respondent’s
employees died, and many more were exposed to serious injury, as a result of the
explosion that occurred on September 28, 2012.
Further, due to the lack of adequate training, procedures, and hazard
analysis, Respondent’s employees were exposed to those same hazards each time
they lit the Wickes. Respondent was
aware of previous hard-starts (a colloquial term for “mini-explosion”) and
failed to adequately address the conditions and procedures that contributed to
them. Although the Court determined that
a repeat characterization was not appropriate under the facts of this case, the
Court finds that Respondent’s knowledge of previous hard-starts, its subsequent
failure to address the hazards associated with the process, and the potential
for serious injury or death provides a sound basis for the highest penalty
available for serious violations. Thus,
the Court will assess a $7,000.00 penalty for each of the following
violations: Citation 1, Item 1; Citation
1, Items 2(a), (b), and (c); Citation 1, Items 3(a) and (b); Citation 1, Item 4
[allegation b]; Citation 1, Items 5(a) and (b); Citation 1, Items 6(a) and (b);
Citation 2, Item 2; Citation 2, Item 3; Citation 2, Item 4; and Citation 2,
Item 5 [allegation b].
B.
Docket No. 13-0644 – Inspection No.
778042
The
citations contained within this docket are sufficiently unique in terms of the
violation and potential hazard to warrant more individualized discussion. Inasmuch as the citation items are similar,
the Court shall consolidate its discussion of those items.
With respect
to Citation 1, Item 2, the Court finds that the uncapped cylinders have the
potential to become dangerous projectiles that could cause serious injury to
the numerous people that occupied or otherwise used the warehouse during the
turnaround. That said, it appears the
cylinders were secured, which reduced the likelihood that an accident would
occur. In light of
these facts, the Court finds that a penalty of $3,300.00, as proposed by
Complainant, is appropriate.
With respect
to Citation 1, Item 4, it appears that blocked fire extinguishers in the warehouse
were an ongoing and pervasive problem.
CSHO Rambo identified four different extinguishers in the warehouse that
were blocked, not properly mounted, or both. The Court finds that nearly all
of the occupants of the warehouse were exposed to a fire hazard, because
Respondent expected its employees to attempt to put out small fires with the
provided fire extinguishers. However, considering that Complainant did not
identify any imminent fire dangers in the warehouse, the Court finds that the
likelihood of injury is low.
Accordingly, the Court finds that a penalty of $3,300.00, as proposed by
Complainant, is appropriate.
With respect
to Citation 1, Item 5 and Citation 1, Items 6(a), (b), and (c), the Court finds
that the hazards associated with each and the gravity of the violations are fairly similar. Each
of these items deals with point of operation hazards, and the equipment at
issue was used by numerous employees and contractors throughout the turnaround.
Both the saw and the grinder were
improperly guarded and exposed operators to potential lacerations, amputations,
and, in the case of the grinder, struck-by injuries due to the worn-down
grinding wheel. Given the potential for serious injury, and in consideration of
the number of people that used the saw and grinder, the Court finds that a
penalty of $5,500.00 is appropriate for Citation 1, Item 5, and a grouped
penalty of $5,500.00 is appropriate for Citation 1, Items 6(a), (b), and (c).
With respect
to Citation 1, Item 7, the Court finds that the violation was of low gravity.
While the electric panel was blocked to some extent, it was not completely inaccessible.
To be sure, when it comes to possible electric shock or electrocution, time is
of the essence when it comes to shutting down circuits; however, considering
that the panel was still relatively accessible, the Court finds that the
violation’s connection to potential injury was fairly
attenuated. Accordingly, the
Court finds that a penalty of $3,000.00 is appropriate.
With respect
to Citation 1, Item 8, the Court finds that employees were exposed to potential
electric shock, burns, or even electrocution as a result of the open knockout
on the side of the electrical panel. The
panel itself was in a well-traveled area, and the knockout was not properly
protected. However, even though it was
in a well-traveled area, the Court finds it would be unlikely that an employee
would get close enough to the condition to actually cause
injury. Accordingly, the Court finds
that a penalty of $1,000.00 is appropriate.
With respect
to Citation 1, Item 9, Respondent’s employees were exposed to potential burns,
shock, and electrocution due to the use of extension cords as a primary power
source. There was no indication that the hanging cords were damaged in any way;
however, given the fact that the cords were draped over metal beams and cables
and Respondent’s propensity to use those cords both as power source and as
hanging storage, the Court finds that the potential for serious injury was
increased. Accordingly, the Court finds that a penalty of $4,400.00 is
appropriate.
With respect
to Citation 2, Item 1, the Court finds that a lower penalty is appropriate.
When viewed in a vacuum, twenty-four instances of contractors and employees
failing to sign out of a process area seems excessive. However, more than 1500 contractors were
present at the refinery each shift. While the Court agrees with Complainant
that such an influx of people on the premises heightens Respondent’s
responsibility to properly track employees and contractors that are potentially
exposed to PSM-related hazards, the Court is also mindful of the challenges
associated with such a large, sudden, workforce increase. In light of that
fact, and in consideration of the fact that Respondent had a badge-entry system
that allowed them to track all entrants onto the property generally, the Court
finds that a penalty of $2,000.00 is appropriate.
Finally,
with respect to Citation 3, Item 1, the Court finds that Respondent’s employees
were exposed to a hazard due to Respondent’s failure to calculate and post the
load rating for the second-level storage area.
Without knowing the load capacity, Respondent’s employees could have
been exposed to a collapse of the structure due to overloading. However, in light of the
fact that Complainant characterized this citation item as
other-than-serious, the Court finds that its proposed penalty of $1,000.00 is
appropriate.
VI.
Order
Based upon the foregoing Findings of Fact and
Conclusions of Law, it is ORDERED
that:
A.
Docket No. 13-0791 – Inspection No.
663538
B.
Docket No. 13-0644 – Inspection No.
778042
1. Citation 1, Item 1 is VACATED.
2. Citation 1, Item 2 is AFFIRMED, and
a penalty of $3,300.00 is ASSESSED.
3. Citation 1, Item 3 is VACATED.
4. Citation 1, Item 4 is AFFIRMED, and
a penalty of $3,300.00 is ASSESSED.
5. Citation 1, Item 5 is AFFIRMED, and
a penalty of $5,500.00 is ASSESSED.
6. Citation 1, Items 6(a), (b), and (c)
are AFFIRMED, and a grouped penalty of $5,500.00 is ASSESSED.
7. Citation 1, Item 7 is AFFIRMED, and
a penalty of $3,000.00 is ASSESSED.
8. Citation 1, Item 8 is AFFIRMED, and
a penalty of $1,000.00 is ASSESSED.
9. Citation 1, Item 9 is AFFIRMED, and
a penalty of $4,400.00 is ASSESSED.
10. Citation 2, Item 1 is AMENDED to a
serious violation, AFFIRMED as amended, and a penalty of $2,000.00 is ASSESSED.
11. Citation 3, Item 1 is AFFIRMED, and
a penalty of $1,000 is ASSESSED.
/s/Brian A. Duncan |
Date: February 5,
2016 Judge Brian A. Duncan
Denver, Colorado U.S. Occupational Safety and Health
Review Commission
[1] Wynnewood LLC’s petition for discretionary review
also asserts that the Secretary’s serious characterization of some of the PSM
citation items at issue “shows the overreach of the PSM standard.” The Commission requested briefing on this
issue as well as the applicability of the PSM standard, as a
whole, to the Wickes boiler. The
company, however, does not address the serious characterization issue in its
review brief; so we consider that issue
abandoned. See Am. Sterilizer Co., 18 BNA OSHC 1082, 1089 n.15 (No. 91-2494,
1997) (“Under Commission precedent, an issue raised in a petition for review or
direction for review but not addressed in the party’s brief is treated as
abandoned.”). The company did, though,
include in its review brief challenges to the merits of each of the Wickes
boiler-related items that go beyond the issue of applicability and were not
raised in its petition. We decline to
address these additional issues. See Charles
A. Gaetano Constr. Corp., 6 BNA OSHC 1463, 1468 n.7 (No. 14886, 1978)
(“[Where a] respondent did not raise [an] argument in its petition for review[,] . . . the . . . issue
is not before [the Commission].”); J.A.
Jones Constr. Co., 15 BNA OSHC 2201, 2204 (No. 87-2059, 1993) (“It is
well-settled that the Commission has discretion to decline to entertain
arguments by a party dealing with matters on which we did not request
briefs.”).
[2] Two motions remain pending before the
Commission. The American Fuel &
Petrochemical Manufacturers and American Petroleum Institute moved for leave to
file an amicus brief. See Commission Rule 24, 29 C.F.R. §
2200.24 (“The brief of an amicus curiae may be filed only by leave of the Judge
or Commission . . . [and] may be
conditionally filed with the motion for leave.”). That motion is granted.
Wynnewood LLC moved for leave to file a sur-reply to the Secretary’s
reply brief. See Commission Rule 93(b)(3), 29 C.F.R. § 2200.93(b)(3)
(“Additional briefs [other than opening and reply briefs] are otherwise not
allowed except by leave of the Commission.”).
The company’s counsel, however, included the sur-reply brief within the
motion, which violates Commission Rule 40(a), see 29 C.F.R. § 2200.40(a) (“A motion shall not be included in
another document, such as a brief . . . ,
but shall be made in a separate document.”).
In addition, the motion initially failed to “state . . . if
[the Secretary] opposes or does not oppose the motion.” Id. Finally, the motion was
filed almost six weeks after the Secretary filed his reply brief. Cf. Commission
Rule 93(b)(1), 29 C.F.R. § 2200.93(b)(1) (“Any reply brief permitted by
these rules or by order shall be filed within 15 days after the second brief is
served.”). Accordingly, this motion is
denied.
[3] While it appears that Wynnewood Refining Company,
when it was owned by Gary-Williams Energy Corporation, was a Delaware
corporation, the record in this case is not entirely clear on this point. Nevertheless, we will refer to the entity
that existed before February 2012 as “Wynnewood Inc.,” to distinguish it from
Wynnewood LLC, the respondent here.
[4] Under Docket No. 13-0791, the seven PSM items in
Serious Citation 1 at issue on review allege violations of:
§ 1910.119(d)(3)(i)(F), asserting that the Wickes boiler’s process safety
information did not include design codes and standards (Item 1); §
1910.119(e)(3)(i), (e)(3)(iii), and (e)(3)(iv), based on two allegedly
deficient process hazard analyses (Items 2a, 2b, and 2c);
§ 1910.119(f)(1)(i)(A) and (f)(3), for having inadequate operating
procedures and failing to review such procedures (Items 3a and 3b); and §
1910.119(l)(3), for failing to inform employees of a process
change related to the Wickes boiler (Item 4).
The four items in Repeat Citation 2 at issue on review allege violations
of: § 1910.119(f)(1)(ii), in that the operating procedures for the Wickes
boiler did not address the operating limits of the equipment (Item 2);
§ 1910.119(g)(2), for failing to provide refresher training to employees
on operation of the Wickes boiler (Item 3); § 1910.119(j)(2), for failing
to implement written procedures related to the Wickes boiler (Item 4); and §
1910.119(l)(1), for failing to implement procedures to manage
changes related to the Wickes boiler (Item 5).
[5] The additional PSM item that was cited as a repeat
violation under Docket No. 13-0644 alleges a violation of
§ 1910.119(h)(2)(iv), for failing to implement safe work practices to
control the entrance, presence, and exit of contract employers and employees
near the Wickes boiler (Repeat Citation 2, Item 1).
[6] Wynnewood LLC argues that the
purpose of the standard—“to prevent or mitigate
against the consequences of a catastrophic release of HHCs,” 29 C.F.R. §
1910.119 (“Purpose” statement)—would not be served by what the company
characterizes as an “expansive” reading of the “process” definition. Courts, however, “cannot use . . . general
statements of . . . purpose to
override the plain meaning of specific provisions . . . .” Reeves
v. Astrue, 526 F.3d 732, 737 (11th Cir. 2008). In addition, as the judge noted, “[t]here is
nothing patently . . . unreasonable
about considering vessels that are physically connected by pipeline to be part
of the same process, nor is it unreasonable to presume that vessels connected
in such a way could be involved in a potential release of HHCs.”
We also reject the company’s
contention that OSHA failed to give the company notice that the Wickes boiler
was to be treated as a PSM-covered process.
The plain meaning of the provision provided sufficient
notice of OSHA’s position in this case. See Ohio Cast Prods., Inc., 18 BNA OSHC
1912, 1915 (No. 96-0774, 1999) (“[I]n view of our conclusion that the standard’s . . . plain
meaning would be ‘ascertainably
certain’ to an employer[,] . . . we conclude that [the employer] had fair notice of the
means by which the cited standard provides for determining silica
overexposure.”). In addition, we note
that OSHA published an interpretation of the PSM standard in 2007, more than
five years prior to the inspections at issue here, stating that “the definition
establishes two distinct burdens of proof when considering the applicability of
PSM to an interconnected or a co-located process,” with OSHA “presum[ing] that
all aspects of a physically connected process can be expected to participate in
a catastrophic release.” Interpretation
of OSHA’s Standard for Process Safety Management of Highly Hazardous Chemicals,
72 Fed. Reg. 31,453, 31,456-57 (June 7, 2007).
[7] Chairman
MacDougall does not join her colleagues in finding a plain meaning of the
“process” definition, due to the definition’s grammatically
incorrect use of “which.” When
“which” is properly used, it is preceded by a comma and introduces a
“nonrestrictive relative clause”; that clause “contains extra information that
could be left out of the sentence without affecting the meaning.” Oxford Living Dictionaries, “That” or “which”?, Oxford University Press,
https://en.oxforddictionaries.com/usage/that-or-which (last visited Mar. 21,
2019). By contrast, “that” introduces,
without a comma preceding it, a “restrictive relative clause” containing
“essential information about the noun that comes before it.” Id. Here, the “process” definition uses “which”
without a comma, so any attempt to interpret the definition based on its plain
language is guesswork at best, and impossible at worst.
To illustrate the confusion created by the drafters’
construction of this provision, if the sentence is read as a true “which”—i.e.,
unnecessary, extra information—it nullifies most of the words of the sentence:
[A]ny group of
vessels, which are interconnected, and separate vessels, which are
located such that a highly hazardous chemical could be involved in a potential
release, shall be considered a single process.
However,
if the sentence is read as using a “that”—i.e., essential information—then the
statutory interpretation would be that of her colleagues. Unfortunately, the drafters chose “which” and
thus, Chairman MacDougall would conclude that, due to poor drafting, the
definition is ambiguous.
Nevertheless,
Chairman MacDougall finds that the Secretary’s interpretation of the “process”
definition is reasonable and entitled to weight based on the entirety of the
circumstances, including the consistency of the Secretary’s interpretation. See,
e.g., 72 Fed. Reg. at 31,456-57. See also Skidmore v. Swift & Co.,
323 U.S. 134, 140 (1944) (“The weight of [an interpretation] in a particular
case will depend upon the thoroughness evident in its consideration, the
validity of its reasoning, its consistency with earlier and later
pronouncements, and all those factors which give it power to persuade, if
lacking power to control.”).
[8] The parties argue over what this operator shelter was, as well as the significance of it. The Secretary—citing the testimony of the refinery’s process safety manager—asserts that the operator shelter was another name for the FCCU control room. Wynnewood LLC contends that there is a distinction between the control room and the operator shelter, the latter of which was within 40 feet of the Wickes boiler but housed no controls related to the Wickes boiler, FCCU, or any other PSM-covered process. The precise identification of the operator shelter, however, is immaterial to the issue at hand. Given the testimony of the Secretary’s expert regarding the potential for damage to equipment, vessels, and piping resulting from a boiler explosion, the significance of the operator shelter was to show the strength of the blast (given that the shelter was 40 feet away), not that damage to the shelter, in particular, would compromise FCCU processes.
[9] While the judge did not address which party bears the burden of proof with regard to the exemption, it is phrased as an exception, see § 1910.119(a)(1)(ii) (“This section applies to . . . [a] process which involves a Category 1 flammable gas . . . except for . . . .”), so Wynnewood LLC must show that it applies. See C.J. Hughes Constr., Inc., 17 BNA OSHC 1753, 1756 (No. 93-3177, 1996) (“A party seeking the benefit of an exception to a legal requirement has the burden of proof to show that it qualifies for that exception.”).
[10] We note that even if the PSM standard’s applicability here depended on the mere presence of RFG or natural gas, the exemption would still not be met. The preamble “clarif[ies] [OSHA’s] intent not to exclude from coverage hydrocarbon fuels used for process[-]related applications such as furnaces, heat exchangers and the like,” and that is exactly how the RFG and natural gas were being used here—to heat the Wickes boiler. 57 Fed. Reg. at 6367. Rather, the intent, as explained by the American Petroleum Institute in commenting on the proposed rule, was in part “to exclude the enormous number of small business locations across the nation which would not be covered by the . . . rule, except for their on-site storage of hydrocarbon fuels for low-risk applications such as heating, drying, and the like,” which “are not the subject of” the standard. Id.
[11] On review, Wynnewood LLC renews an additional
argument that was rejected by the judge—that OSHA failed to comply with its own
internal citation policy given that the underlying citations became final
orders more than five years prior to the ones at issue here. As we have consistently held, however, OSHA’s
citation policy is “only a guide for OSHA personnel to promote efficiency and
uniformity, [is] not binding on OSHA or the Commission, and
do[es] not create any substantive rights for employers.” Hackensack
Steel Corp., 20 BNA OSHC 1387, 1392 (No. 97-0755, 2003). In other words, “there are no statutory
limitations upon the length of time that a citation may serve as the basis for
a repeated violation.” Id.
See also Triumph Constr. Corp. v.
Sec’y of Labor, 885 F.3d 95, 99 (2d Cir. 2018) (“[T]he Commission did not
abuse its discretion by relying on previous violations more than three years
old, because neither the [OSHA Field Operations] Manual nor the Commission’s
precedent limits OSHA to a three-year look back period.”).
[12] In Sharon &
Walter, Walter Jensen was the sole proprietor of both the predecessor and
successor. 23 BNA OSHC at 1288.
[13] We note that our
dissenting colleague lists nine individuals employed by both Wynnewood LLC and
Wynnewood Inc. with titles indicating safety and health responsibilities, and
she asserts that it is inappropriate to consider management changes above their
level following the purchase by CVR Energy because the new parent company is a
distinct corporate entity. The record,
however, shows that safety policy at
the refinery was not controlled by these managers, either before or after the
purchase. Regardless of whether as a
matter of corporate law the managers our colleague references had the right to
refuse instructions from either of their parent entities, the record shows that
these managers merely implemented the safety policies set by the previous
parent company and then by CVR Energy. Consequently, after the refinery was
purchased, the safety policies at the
refinery changed significantly as a direct result of the different attitude
toward safety CVR Energy brought to bear.
As operations manager Darin Rains testified, “[t]he refinery went
through some pretty drastic changes as a result of the purchase by CVR Energy,”
including increasing the number of safety personnel. Indeed, David Johnson, a safety specialist at
the refinery, described how Chris Swanberg, CVR Energy’s Vice President for
Safety, Health, and Environment, told managers “very clearly and very
emphatically that, under his watch . . . safety
was the highest priority at the refinery,” and that this resulted in specific
safety-related changes:
Safety training was a
priority. Our budget for safety was pretty open. If there
was a safety issue, it was addressed immediately. If we couldn’t resolve it, then . . . it kept
going up to the next level to get resolution.
You know, it was a very dramatic
change.
(Emphasis
added.) In short, a rote application of
the “continuity of personnel” prong that considers only the management
personnel working for each Wynnewood entity paints an inaccurate picture of how
safety policy was set and how safety decisions were made at the refinery. As such, unlike our dissenting colleague, we
conclude that Wynnewood LLC’s changeover in ownership resulted in changes in
management practices, procedures, and culture significant enough to break the
chain of liability stemming from Wynnewood Inc.’s previous actions.
[14]
While we agree that the last prong of the
three-part “substantial continuity” test (continuity of personnel) was not met
in this case—and that Wynnewood Inc. and Wynnewood LLC are therefore not the
same employer for repeat characterization purposes under Sharon & Walter—in our view this may not even be the
appropriate test for determining whether successor liability should be imposed
for purposes of the Occupational Safety and Health Act. We are in favor of revisiting Sharon & Walter, because the view
expressed by Commissioner Thompson in that case seems persuasive—that the substantial
continuity test is not appropriate in determining whether a violation has been
properly characterized as repeat. See 23 BNA OSHC at 1296 n.19.
In addition, we see no rationale here for imposing the OSHA
violation history of Wynnewood Inc. upon Wynnewood LLC, a separate legal entity
not created to avoid responsibilities under the Act. See id.
at 1293 (repeat characterization appropriate “where the cited employer has
altered its legal identity from that of the predecessor employer whose citation
history forms the basis of that characterization”). This is particularly true here where the new management focused on improving
safety, health, and the proper implementation of PSM at the refinery. Nonetheless, given that the Secretary’s repeat characterization has been rejected
pursuant to Sharon & Walter, and in light of the
parties’ failure to ask the Commission to revisit that case (and the lack of briefing on this particular
issue), this question will have to wait for another day.
Chairman
MacDougall notes on this issue, however, as she did in Delek Refining, Ltd., 25 BNA OSHC 1365 (No. 08-1386, 2015), aff’d in part, 845 F.3d 170 (5th Cir.
2016), that the “general rule that a purchasing entity does not have successor
liability applies, such that a corporation that purchases another corporation
‘is not responsible for the seller’s debts or liabilities, except where (1) the
purchaser expressly or impliedly agrees to assume the obligations; (2) the
purchaser is merely a continuation of the selling corporation; or (3) the
transaction is entered into to escape liability.’ ” Id.
at 1378 (MacDougall, Comm’r, concurring and dissenting) (quoting Golden State Bottling Co. v. NLRB, 414
U.S. 168, 182 n.5 (1973)). As she
observed in Delek, “[t]he Supreme Court has referred to
the ‘free transfer of capital’ and the concern of placing restrictions on
successor employers, which might reduce the incentives purchasers have to take
over failing businesses, as factors to be considered in shaping successorship
doctrine.” Id. n.6 (citing Howard
Johnson Co. v. Detroit Local Joint Exec. Bd., Hotel & Rest. Emps. &
Bartenders Int’l Union, 417 U.S. 249, 255 (1974); NLRB v. Burns Int’l Sec. Servs., Inc., 406 U.S. 272, 287-89 (1972)).
Commissioner Sullivan notes, as did Commissioner Thompson in Sharon & Walter, that the substantial continuity test was developed and adopted from cases decided by the National Labor Relations Board in evaluating “the continuing obligations of a successor toward a majority union under the National Labor Relations Act.” 23 BNA OSHC at 1296 n.19. The OSH Act does not serve this purpose, so the doctrine appears particularly inappropriate when deciding whether a predecessor entity’s prior violations should be attributed to a successor. Commissioner Sullivan agrees with Commissioner Thompson that under the OSH Act, “common law master-servant principles apply, including the ‘alter ego,’ doctrine, which is reflected in the federal common law.” Id. Further, “the Commission has the authority to apply this common law equitable remedy to examine the violation history of a predecessor because denial to the Commission of veil piercing authority in appropriate circumstances would not be consistent with United States v. Bestfoods, 524 U.S. 51 (1998).” Id. In short, Commissioner Sullivan believes the common law speaks more directly to successor liability with respect to the OSH Act and to the question of whether a violation is properly characterized as repeat. The substantial continuity test, on the other hand, while appropriate for collective bargaining agreements, creates in his view a disincentive for employers when it comes to hiring or keeping employees of the predecessor entity if applied in the repeat characterization context.
[15] Chairman MacDougall notes that, given the Commission’s conclusion that Wynnewood Inc. and Wynnewood LLC are not the same employer, there is no need to reach the issue of whether there is substantial similarity between the prior and current violations; therefore, there is no reason to address Commissioner Attwood’s discussion of Angelica Textile Servs., Inc., No. 08-1774, 2018 WL 3655794 (OSHRC June 24, 2018), appeal docketed, No. 18-2831 (2d Cir. Sept. 21, 2018).
[16] This provision requires
“written operating procedures that provide clear instructions for safely
conducting activities involved in each covered process consistent with the
process safety information and shall address . . . operating limits.” 29 C.F.R. § 1910.119(f)(1)(ii).
[17] This provision states that
“[r]efresher training shall be provided at least
every three years, and more often if necessary, to each employee involved in
operating a process to assure that the employee understands and adheres to the
current operating procedures of the process.”
29 C.F.R. § 1910.119(g)(2).
[18] This provision states that
“[t]he employer shall establish and implement written procedures to maintain
the on-going integrity of process equipment.”
29 C.F.R. § 1910.119(j)(2).
[19] This provision states that
“[t]he employer shall establish and implement written procedures to manage
changes (except for ‘replacements in kind’) to process chemicals, technology,
equipment, and procedures; and, changes to facilities that affect a covered process.” 29 C.F.R. § 1910.119(l)(1).
[20] This provision states that
“[t]he employer shall develop and implement safe work practices consistent with
paragraph (f)(4) of this section, to control the entrance, presence and exit of
contract employers and contract employees in covered process areas.” 29 C.F.R. § 1910.119(h)(2)(iv).
[21] I agree with my colleagues’
rejection of Wynnewood LLC’s argument that a repeat characterization is
inappropriate here because OSHA failed to comply with its internal citation
policy in relying on prior violations that were more than five years old. As the majority aptly notes, “there are no
statutory limitations upon the length of time that a citation may serve as the
basis for a repeated violation.” Hackensack Steel Corp., 20 BNA OSHC
1387, 1392 (No. 97-0755, 2003).
[22]. Inspection No. 663538 was assigned Docket No.
13-0791. Inspection No. 778042 was
assigned Docket No. 13-0644. For ease of
reference, however, the Court shall refer to the inspections as the PSM
Inspection and the Warehouse Inspection, respectively.
[23]. Paul Howard was his predecessor. (Tr.
684). According to Stephenson, Howard
continued to serve in an advisory capacity once Stephenson took over. (Tr.
672).
[24]. The remaining citation, which addressed a
flare line running from the Alky Unit, was affirmed by Administrative Law Judge
Covette Rooney as a final order of the Commission on September 8, 2008. (Ex.
C-28).
[25]. As will be discussed later in this Decision,
the Wickes boiler, which is the subject of many of the citations at issue in
this case, was a part of, or at least directly adjacent to, the FCCU. (Ex. C-7,
C-11).
[26]. The Wickes boiler does not have a burner
management system (BMS), which allows for remote ignition of the burner. (Tr.
100).
[27]. According to James Willson,
who had worked at the refinery for seven years at the time of the accident said
he had only lit the boiler 4 to 5 times during that period. (Tr. 376).
[28]. A
turnaround is a period of time when the refinery shuts
down temporarily to allow for improvement and maintenance projects. (Tr. 1704).
[29]. For all other chemicals, one must refer to
Appendix A of 29 C.F.R. § 1910.119.
[30]. According to the RMP that Respondent
submitted to the EPA, the Alky Unit stores and/or processes 100,000 pounds of
flammable liquid; the FCCU stores and/or processes 50,000 pounds. (Ex. C-5).
[31]. Delek is currently on review to the Fifth Circuit Court of
Appeals. Nonetheless, it still serves as
precedent for the Court in this case.
[32]. The Court would like to make a brief note
regarding the distinction between normal operations and turnaround
operations. During normal operations,
the system is fueled by a combination of refinery fuel gas and natural gas,
whereas during a turnaround, the Wickes is run by natural gas because there are
no other processes running to produce the RFG.
While this might call into question whether the Wickes is covered during
the period of a turnaround, the Court cites favorably to Respondent’s expert,
Steve Arendt, who stated that the determination of whether a process is covered
does not depend on whether it is in operation or in turnaround status. (Tr.
2095).
[33]. In fact, Complainant has interpreted the
term interconnected such that even energy-isolating devices, such as blocks,
are not sufficient in and of themselves to break the
connection between two physically connected processes. (Ex. C-4 at 1530).
[34]. This also highlights the problematic nature
of Respondent’s definition of interconnection, as it imposes artificial
boundaries that do not comport with the plain reading of the definition of
process.
[35]. Complainant addressed a similar situation to
the one presented here through a letter of interpretation. (Ex. C-4 at
1542). In that letter, Complainant was
asked whether the use of coke oven and blast furnace gases—which are generated as a by-product during steel industry
processes—as fuel for other steel mill processes would be covered by the PSM
standard. (Id.). In response, Complainant stated that the
workplace fuels exception would apply insofar as the by-product gases are not
used in a process involving another highly hazardous chemical covered by the
standard. (Id.). Although it discussed the potential coverage
of a by-product recovery plant, the interpretation did not clarify the extent
to which a particular fuel use is considered to be
“part of a process involving another highly hazardous chemical covered by the
standard.”
[36]. Refractory is a brick-like lining that is
used inside of the Wickes to protect the piping from flame impingement. (Tr.
149).
[37]. The
Court also finds that the fact that the blast caused a ladder and platform to
fly across a street and into an adjacent operator building (which houses the
CTs) suggests that smaller pieces of shrapnel could fly much farther and, as a
result, could impact covered aspects of the FCCU. However, as discussed further below, there is
an even stronger basis upon which to find PSM coverage based on co-location.
[38]. For the purpose of making the distinction
clear, and for this section only, the Court will refer to the two entities involved
in the purchase of Wynnewood as GWE-WR and CVR-WR. As a reminder, CVR-WR is the Respondent in
this case.
[39]. Four out of the five underlying violations,
which were part of OSHA Inspection No. 309785459, became final orders in April
of 2007, after a partial settlement. (Ex. C-28). The remaining violation, which was part of
OSHA Inspection No. 311001234, became a final order on November 10, 2008. (Ex.
C-26).
[40]. This section deals primarily with the
question of whether Respondent is a successor-in-interest to GWE. Because the Court finds that Respondent is
not properly characterized as a successor, it will not address the substantive
argument of whether the present and underlying citations are substantially
similar.
[41]. Respondent contends that Complainant failed
to establish continuity in operations and working conditions due to the
implementation of more formal policies and procedures after the acquisition.
These changes are more germane to the issue of continuity in personnel
responsible for decision-making. While
the implementation of more formal policies and procedures, especially in the
arena of safety and health, may have an impact on the manner
in which a job is carried out, the basic nature of the job and the
conditions of the refinery did not change.
[42]. This sentiment was expressed by the
Commission in Sharon & Walter,
when it held that an individual’s common control over decision-making in both
companies “weighs heavily” in favor of finding successor liability. Sharon & Walter, 23 BNA OSHC 1286 at
*10.
[43]. Mr. Rains is now the Vice President and
General Manager of Respondent’s Coffeyville refinery.
[44]. The Court also finds the Oklahoma State
boiler inspection is not sufficient to establish Respondent’s compliance with its obligation to compile PSI. As Johnstone testified, the state inspection
report did not indicate whether the design complied with any specific
applicable requirements. (Tr. 1016).
[45]. These PHAs occurred when the refinery was
owned by Gary Williams Energy.
[46]. Specifically, the previous SOPs indicated
that the valve should be opened slowly, 1/16 of an inch at a time, and no more
than one spoke. (Ex. C-30 at Exhibit 42).
It also indicated that fuel gas was not to exceed 1,000 MCSFD and that
if ignition was not achieved to close the valve and restart the lighting
sequence. (Id.). The “current” SOPs only instruct an operator
to “LIGHT main burner by slowly opening 3-[inch] bypass valve around 20FC702
until burner lights.” (Id. at Exhibit
44).
[47]. By comparison, the previous iteration of the
SOP indicated when a lighting attempt should be aborted and what steps should
be taken in the event of a failed lighting attempt. (Ex. C-30 at Exhibit 43).
[48]. It should also be noted that the work
requested by CSHO Hartung was not a work activity which never occurred but for
OSHA’s valve examination request. As noted above, Respondent had previously
done work on this valve in order to change the size and restrict the flow of
gas to the firebox of the Wickes. (Tr. 311-12).
[49]. Similar exhibits can be found in R-201,
R-202, R-204, R-212, R-214, R-219, R-221.
[50]. Koesler stated that
he was trained to open the valve “1/4 spoke”, that there was no set amount of
time to leave open, and that he was told to purge “until you thought it was
ok”. (Tr. 113, 116, 121). Kellerhall
testified that he did not recall specific instructions other than that the
valve is “very touchy” and that you “don’t want to leave it open very long.”
(Tr. 219). CT Sutton testified that he
told the investigator that you turn the valve about an inch. (Tr. 301). Willson testified
that he had not been instructed as to any specific instructions regarding the
valve, instead characterizing the process as a “dance”. (Tr. 353). McCurtain stated that he was trained to open
the valve “slightly” or “just a little bit” and that if you don’t achieve
ignition “quickly” or “shortly” to close the valve. (Tr. 518, 528). Finally, Howard, who provided training and
testing, testified that he trained operators to “[s]lowly open it until you
reach one spoke . . . . And if it does light, you move on with the
procedure; if it does not, then you close it off.” (Tr. 693).
[51]. CSHO Rambo also issued a Citation 3, Item 1
in Inspection No. 778042, which was discussed at trial.
[52]. In that respect, the Court rejects
Respondent’s argument that there were no employees in the facility at the time
of the inspection. See Resp’t Br. at 70 n.22.
[53]. The self-audit also identified Mr. McCaulla as the party responsible for correcting the
blocked fire extinguishers and that he was to correct the condition by “15 Oct
12”. (Ex. C-74). CSHO Rambo’s inspection
took place on October 29, 2012. (Tr. 1381).
[54]. To clarify, the logs covered a period of
approximately 12 days, not CSHO Rambo’s inspection. None of the days identified included the day
of the Wickes explosion.